Draft Sectoral Marine Plans for Offshore Renewable Energy in Scottish Waters - Environmental Report Appendix C: Assessment of Technologies
Appendix C to the SEA Environmental Report of the Draft Sectoral Marine Plans for Offshore Renewable Energy in Scottish Waters.
This appendix contains an assessment of technologies.
1 Wind Technology
SEA Topic Areas |
Wind technologies with gravity-base foundation devices |
Wind technologies with monopile or multi-pile foundation devices |
Wind technologies with tripod or steel jacket foundation devices |
Wind technologies with mono or multi-caisson foundation devices |
Floating wind turbines |
---|---|---|---|---|---|
Device Information [1] |
|
|
|
|
|
Biodiversity/ flora/ fauna [2] |
Summary of key potential effects:
Key measures to prevent adverse effects may include: avoidance of sensitive sites; avoidance of sensitive seasons during installation ( e.g. breeding); protocols (such as use of Marine Mammal Observers) to ensure noisy construction activities do not occur when marine mammals are in close proximity; effective device design and project-specific studies to help design appropriate mitigation; carry out detailed routing studies at project level in accordance with 'Holford Rules' best practice guidance on routeing overhead transmission lines onshore. |
||||
Marine Mammals and fish Underwater noise and vibration during installation has the potential to impact on marine fauna ( i.e. seals, otters, cetaceans, basking sharks). There is also the potential for cumulative impacts from multiple noise sources audible to marine mammals and fish during installation and increased vessel disturbance. Potential displacement or disturbance of marine fauna through a combination of factors including noise (and multiple noise sources), vibration, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Potential for injury with marine mammals and impacts during installation period ( i.e. risk of injury to curious seals and dolphins during placement of foundations). Potential for EMF impacts associated with cabling and grid connection infrastructure. Cumulative impacts may occur, particularly affecting mammals and migratory fish, from an increased number of barriers affecting fish movement ( i.e. device arrays, construction vessels/equipment, etc.). Birds Potential for bird-strike with turbine blades is likely to be site-specific. Potential for diving bird collisions with support devices ( i.e. mooring cables if used). However, this is likely to be site and device-specific, and the likelihood of occurrence is not currently known. Potential disturbance of diving bird foraging areas due to surface noise, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Benthic Habitats Potential for creation of artificial habitats for marine organisms resulting from the presence of new structures. This may be aided by reductions in commercial fishing ( e.g. trawling) in areas where wind farms are sited, as this may enhance biodiversity. These benefits could last for the life of the project, or potentially longer depending on the decommissioning scheme. Loss of seabed habitat from the placement of gravity foundation directly on/into the seabed, and potential for adverse impacts from sourcing of fill or dredged material for use in the gravity-based foundation ( i.e. potential risk of impacts to marine fauna from dredging activities, turbidity, potential release of contaminated materials, loss of habitat at source, etc.). Direct adverse impacts to benthic habitats, particularly sensitive habitats such as shellfish growing waters, from sediment dispersion and deposition in the construction phase of works ( i.e. east of Scotland ( e.g. Bell Rock, Inch Cape, Neart na Gaoithe and Forth Array) and west of Scotland ( e.g. Argyll Array, Islay and Kintyre) where shellfish waters are prevalent. It is anticipated that many of the construction and decommissioning effects may be temporary and reversible ( i.e. removal of the gravity base structure and rehabilitation of the seabed). However, some impacts on biodiversity experienced during operation of wind farms are likely to be permanent and irreversible. |
Marine Mammals and fish Underwater noise and vibration on mammals seals, otters and cetaceans during piling. There is also the potential for cumulative impacts from multiple noise sources audible to marine mammals and fish during piling and installation of turbines, and increased vessel disturbance. Potential displacement or disturbance of marine fauna through a combination of factors including noise (and multiple noise sources), vibration, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Potential for injury with marine mammals and impacts during installation period ( i.e. risk of injury to curious seals during piling activities). Can likely be mitigated using a variety of techniques ( i.e. piling jackets, soft start, etc.). Potential for EMF impacts associated with cabling and grid connection infrastructure. Cumulative impacts may occur, particularly affecting mammals and migratory fish, from an increased number of barriers affecting fish movement ( i.e. device arrays, construction vessels/equipment, etc.). Birds Potential for bird-strike with turbine blades is likely to be site-specific. Potential for diving bird collisions with support devices ( i.e. mooring cables if used). However, this is likely to be site and device-specific, and the likelihood of occurrence is not currently known. Potential disturbance of diving bird foraging areas due to surface noise, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Benthic Habitats Potential for creation of artificial habitats for marine organisms resulting from the presence of new structures. This may be aided by reductions in commercial fishing ( e.g. trawling) in areas where wind farms are sited, as this may enhance biodiversity. These benefits could last for the life of the project, or potentially longer depending on the decommissioning scheme. Loss of seabed habitat from the installation process for monopiling into the seabed. Direct adverse impacts to benthic habitats, particularly sensitive habitats such as shellfish growing waters, from sediment dispersion and deposition in the construction phase of works ( i.e. east of Scotland ( e.g. Bell Rock, Inch Cape, Neart na Gaoithe and Forth Array) and west of Scotland ( e.g. Argyll Array, Islay and Kintyre) where shellfish waters are prevalent. It is anticipated that many of the construction and decommissioning effects may be temporary and reversible ( i.e. removal of the turbines with the monopole remaining insitu). However, some impacts on biodiversity experienced during operation of wind farms are likely to be permanent and irreversible. |
Marine Mammals and fish Underwater noise and vibration during piling and the placement of tripod/jacket structures, with potential impacts to marine fauna ( i.e. seals, otters, cetaceans, basking sharks). There is also the potential for cumulative impacts from multiple noise sources audible to marine mammals and fish during piling and installation of turbines, and increased vessel disturbance. Potential displacement or disturbance of marine fauna through a combination of factors including noise (and multiple noise sources), vibration, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Potential for injury with marine mammals and impacts during installation period ( i.e. risk of injury to curious seals during piling activities). Can likely be mitigated using a variety of techniques ( i.e. piling jackets, soft start, etc.). Potential for EMF impacts associated with cabling and grid connection infrastructure. Cumulative impacts may occur, particularly affecting mammals and migratory fish, from an increased number of barriers affecting fish movement ( i.e. device arrays, construction vessels/equipment, etc.). Birds Potential for bird-strike with turbine blades is likely to be site-specific. Potential for diving birds strike to support devices (support structures, mooring cables if used) is likely to be site-specific, and the likelihood of occurrence is not currently known. Potential disturbance of diving bird foraging areas due to surface noise, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Benthic Habitats Potential for creation of artificial habitats for marine organisms resulting from the presence of new structures. This may be aided by reductions in commercial fishing ( e.g. trawling) in areas where wind farms are sited, as this may enhance biodiversity. These benefits could last for the life of the project, or potentially longer depending on the decommissioning scheme. Loss of seabed habitat from the installation process for piling into the seabed. Direct adverse impacts to benthic habitats, particularly sensitive habitats such as shellfish growing waters, from sediment dispersion and deposition in the construction phase of works ( i.e. east of Scotland ( e.g. Bell Rock, Inch Cape, Neart na Gaoithe and Forth Array) and west of Scotland ( e.g. Argyll Array, Islay and Kintyre) where shellfish waters are prevalent. It is anticipated that many of the construction and decommissioning effects may be temporary and reversible ( i.e. removal of the turbines and support structures, and piles remaining insitu). However, some impacts on biodiversity experienced during operation of wind farms are likely to be permanent and irreversible. |
Marine Mammals and fish Underwater noise and vibration during installation has the potential to impact marine fauna ( i.e. seals, otters, cetaceans, basking sharks). There is also the potential for cumulative impacts from multiple noise sources audible to marine mammals and fish during installation and increased vessel disturbance. Potential displacement or disturbance of marine fauna through a combination of factors including noise (and multiple noise sources), vibration, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Potential for injury with marine mammals and impacts during installation period ( i.e. risk of injury to curious seals and dolphins during placement of foundations). Potential for EMF impacts associated with cabling and grid connection infrastructure. Cumulative impacts may occur, particularly affecting mammals and migratory fish, from an increased number of barriers affecting fish movement ( i.e. device arrays, construction vessels/equipment, etc.). Birds Potential for bird-strike with turbine blades is likely to be site-specific. Potential for diving bird collisions with support devices ( i.e. mooring cables if used). However, this is likely to be site and device-specific, and the likelihood of occurrence is not currently known. Potential disturbance of diving bird foraging areas due to surface noise, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Benthic Habitats Potential for creation of artificial habitats for marine organisms resulting from the presence of new structures. This may be aided by reductions in commercial fishing ( e.g. trawling) in areas where wind farms are sited, as this may enhance biodiversity. These benefits could last for the life of the project, or potentially longer depending on the decommissioning scheme. Loss of seabed habitat from the placement of foundation directly on/into the seabed. Direct adverse impacts to benthic habitats, particularly sensitive habitats such as shellfish growing waters, from sediment dispersion and deposition in the construction phase of works ( i.e. east of Scotland ( e.g. Bell Rock, Inch Cape, Neart na Gaoithe and Forth Array) and west of Scotland ( e.g. Argyll Array, Islay and Kintyre) where shellfish waters are prevalent. It is anticipated that many of the construction and decommissioning effects may be temporary and reversible ( i.e. removal of the caisson). However, some impacts on biodiversity experienced during operation of wind farms are likely to be permanent and irreversible. |
Marine Mammals and fish Underwater noise and vibration during installation (placement of concrete anchors and moorlines) has the potential to impact marine fauna ( i.e. seals, otters, cetaceans, basking sharks). There is also the potential for cumulative impacts from multiple noise sources audible to marine mammals and fish during installation and increased vessel disturbance. Potential displacement or disturbance of marine fauna through a combination of factors including noise (and multiple noise sources), vibration, visual and light intensity changes, water quality changes, habitat disturbance or the presence of anchors and vessels. Potential for EMF impacts associated with cabling and grid connection infrastructure. Cumulative impacts may occur, particularly affecting mammals and migratory fish, from an increased number of barriers affecting fish movement ( i.e. device arrays, construction vessels/equipment, etc.). Birds Potential for bird-strike with turbine blades is likely to be site-specific. Potential for diving bird collisions with support devices ( i.e. mooring cables, anchors, etc.). However, this is likely to be site and device-specific, and the likelihood of occurrence is not currently known. Potential disturbance of diving bird foraging areas due to surface noise, visual and light intensity changes, water quality changes, habitat disturbance or the presence of structures and vessels. Benthic Habitats Potential for creation of artificial habitats for marine organisms resulting from the presence of new structures ( i.e. gravity anchors). This may be aided by reductions in commercial fishing ( e.g. trawling) in areas where wind farms are sited, as this may enhance biodiversity. These benefits could last for the life of the project, or potentially longer depending on the decommissioning scheme. Loss of small discrete areas of the seabed habitat from the placement of gravity anchors into the seabed. Direct adverse impacts to benthic habitats, particularly sensitive habitats such as shellfish growing waters, from sediment dispersion and deposition in the construction phase of works ( i.e. east of Scotland ( e.g. Bell Rock, Inch Cape, Neart na Gaoithe and Forth Array) and west of Scotland ( e.g. Argyll Array, Islay and Kintyre) where shellfish waters are prevalent. It is anticipated that many of the construction and decommissioning effects may be temporary and reversible ( i.e. removal of the gravity anchors and removal of the floating turbine structure). However, some impacts on biodiversity experienced during operation of wind farms are likely to be permanent and irreversible. |
|
Population and human health [3] |
Summary of key potential effects on population and human health:
Key measures to prevent adverse effects may include: siting devices away from spatially constrained areas and areas with high vessel densities; siting devices in open water; making use of industry guidance on assessment of effects and use of aids to navigation; use of notifications such as 'Notices to Mariners', publicising information at marina, and Sailing Directions; and adhering to appropriate safety regulations. |
||||
Provision of a new renewable energy supply for the projected increase in the Scottish population for the life of an operating wind farm. Potential for flicker and noise impacts, particularly if located near-shore. Potential impacts on other marine users ( i.e. fishing, recreational, shipping, aquaculture) including the potential displacement of these activities, the risk of collision with turbine structures, and visual impacts associated with the presence of the turbines. Upon decommissioning, these effects will likely be reversible. Potential issues with navigation, although it is noted that this may be managed through the selection of appropriate sites and the MCA to ensure that there are no hazards to shipping. Potential for commercial impacts on the fishing and shipping industries ( i.e. loss of access to fishing areas, reduced catches in such areas from displacement of fish populations, collision risk). Requirement for the installation of new transmission infrastructure to connect the devices to the grid ( i.e. cables on the seabed, terrestrial infrastructure) could, in some circumstances, impact on recreational and commercial activities. Potential impacts, is likely to be site and development specific. Potential for upgrading of nearby port/harbour infrastructure to install and/or maintain turbines. |
Provision of a new renewable energy supply for the projected increase in the Scottish population for the life of an operating wind farm. Potential for flicker and noise impacts, particularly if located near-shore. Potential impacts on other marine users ( i.e. fishing, recreational, shipping, aquaculture) including the potential displacement of these activities, the risk of collision with turbine structures, and visual impacts associated with the presence of the turbines. Upon decommissioning, these effects will likely be reversible. Potential issues with navigation, although it is noted that this may be managed through the selection of appropriate sites and the MCA to ensure that there are no hazards to shipping. Potential for commercial impacts on the fishing and shipping industries ( i.e. loss of access to fishing areas, reduced catches in such areas from displacement of fish populations, collision risk). Requirement for the installation of new transmission infrastructure to connect the devices to the grid ( i.e. cables on the seabed, terrestrial infrastructure) could, in some circumstances, impact on recreational and commercial activities. Potential impacts, is likely to be site and development specific. Potential for upgrading of nearby port/harbour infrastructure to install and/or maintain turbines. |
Provision of a new renewable energy supply for the projected increase in the Scottish population for the life of an operating wind farm. Potential for flicker and noise impacts, particularly if located near-shore. Potential impacts on other marine users ( i.e. fishing, recreational, shipping, aquaculture) including the potential displacement of these activities, the risk of collision with turbine structures, and visual impacts associated with the presence of the turbines. Upon decommissioning, these effects will likely be reversible. Potential issues with navigation, although it is noted that this may be managed through the selection of appropriate sites and the MCA to ensure that there are no hazards to shipping. Potential for commercial impacts on the fishing and shipping industries ( i.e. loss of access to fishing areas, reduced catches in such areas from displacement of fish populations, collision risk). Requirement for the installation of new transmission infrastructure to connect the devices to the grid ( i.e. cables on the seabed, terrestrial infrastructure) could, in some circumstances, impact on recreational and commercial activities. Potential impacts, is likely to be site and development specific. Potential for upgrading of nearby port/harbour infrastructure to install and/or maintain turbines. |
Provision of a new renewable energy supply for the projected increase in the Scottish population for the life of an operating wind farm. Potential for flicker and noise impacts, particularly if located near-shore. Potential impacts on other marine users ( i.e. fishing, recreational, shipping, aquaculture) including the potential displacement of these activities, the risk of collision with turbine structures, and visual impacts associated with the presence of the turbines. Upon decommissioning, these effects will likely be reversible. Potential issues with navigation, although it is noted that this may be managed through the selection of appropriate sites and the MCA to ensure that there are no hazards to shipping. Potential for commercial impacts on the fishing and shipping industries ( i.e. loss of access to fishing areas, reduced catches in such areas from displacement of fish populations, collision risk). Requirement for the installation of new transmission infrastructure to connect the devices to the grid ( i.e. cables on the seabed, terrestrial infrastructure) could, in some circumstances, impact on recreational and commercial activities. Potential impacts, is likely to be site and development specific. Potential for upgrading of nearby port/harbour infrastructure to install and/or maintain turbines. |
Provision of a new renewable energy supply for the projected increase in the Scottish population for the life of an operating wind farm. Potential for flicker and noise impacts, particularly if located near-shore. Potential impacts on other marine users ( i.e. fishing, recreational, shipping, aquaculture) including the potential displacement of these activities, the risk of collision with turbine structures, and visual impacts associated with the presence of the turbines. Upon decommissioning or movement of the array (if undertaken) these effects will likely be reversible. Potential issues with navigation, although it is noted that this may be managed through the selection of appropriate sites and the MCA to ensure that there are no hazards to shipping. Potential for commercial impacts on the fishing and shipping industries ( i.e. loss of access to fishing areas, reduced catches in such areas from displacement of fish populations, collision risk). Requirement for the installation of new transmission infrastructure to connect the devices to the grid ( i.e. cables on the seabed, terrestrial infrastructure) could, in some circumstances, impact on recreational and commercial activities. Potential impacts, is likely to be site and development specific. Potential for upgrading of nearby port/harbour infrastructure to install and/or maintain turbines. |
|
Water and marine environment [4] |
Summary of key potential effects on water quality include:
Key measures to prevent adverse effects may include: siting devices away from sensitive areas, disposal sites, munitions dumps and weapons ranges; using best practice methodologies and technologies to minimise potential impacts during installation; adoption of appropriate management planning in installation works. |
||||
Potential impacts to water quality from installation of turbine foundations and structures ( i.e. turbidity, seabed disturbance from placement of gravity-based supports, contamination from installation equipment and maintenance vessels) and the potential for associated impacts on marine biodiversity, particularly those species dependent on existing water conditions. Potential impacts to the ability of fish species to spawn, respire and feed, and on shellfish growing waters in the vicinity of windfarm sites are also noted. However, the significance of these impacts is currently uncertain. Construction and decommissioning effects are temporary and may be reversible. Potential for cross-contamination in the use of excavated fill material or dredging material as ballast in gravity-based foundations. |
Potential impacts to water quality from installation of turbine monopiles ( i.e. turbidity, seabed disturbance from piling works, contamination from installation equipment and maintenance vessels) and the potential for associated impacts on marine biodiversity, particularly those species dependent on existing water conditions. Potential impacts to the ability of fish species to spawn, respire and feed, and on shellfish growing waters in the vicinity of windfarm sites are also noted, However, the significance of these impacts is currently uncertain. Construction and decommissioning effects are temporary and may be reversible. |
Potential impacts to water quality from installation of turbines and associated structures ( i.e. turbidity, seabed disturbance from piling works and placement of support structures on the seabed, contamination from installation equipment and maintenance vessels) and the potential for associated impacts on marine biodiversity, particularly those species dependent on existing water conditions. Potential impacts to the ability of fish species to spawn, respire and feed, and on shellfish growing waters in the vicinity of windfarm sites are also noted, However, the significance of these impacts is currently uncertain. Construction and decommissioning effects are temporary and may be reversible. |
Potential impacts to water quality from installation of turbine, caisson and seabed preparation activities ( i.e. turbidity, seabed disturbance from preparation/levelling of seabed, potential placement of concrete foundations, placement of caisson and support structures, contamination from installation equipment and maintenance vessels) and the potential for associated impacts on marine biodiversity, particularly those species dependent on existing water conditions. Potential impacts to the ability of fish species to spawn, respire and feed, and on shellfish growing waters in the vicinity of windfarm sites are also noted. However, the significance of these impacts is currently uncertain. Construction and decommissioning effects are temporary and may be reversible. |
Potential impacts to water quality from installation of mooring anchors ( i.e. turbidity, seabed disturbance from placement of gravity anchors, potential for contamination from installation equipment and maintenance vessels) and the potential for associated impacts on marine biodiversity, particularly those species dependent on existing water conditions. Potential impacts to the ability of fish species to spawn, respire and feed, and on shellfish growing waters in the vicinity of windfarm sites are also noted. However, the significance of these impacts is currently uncertain. Construction and decommissioning effects are temporary and may be reversible. |
|
Climatic factors [5] |
Benefits through contribution to decarbonisation of electricity generation through the long-term operation of the wind farms ( i.e. displacement of non-renewable power generation). |
Benefits through contribution to decarbonisation of electricity generation through the long-term operation of the wind farms ( i.e. displacement of non-renewable power generation). |
Benefits through contribution to decarbonisation of electricity generation through the long-term operation of the wind farms ( i.e. displacement of non-renewable power generation). |
Benefits through contribution to decarbonisation of electricity generation through the long-term operation of the wind farms ( i.e. displacement of non-renewable power generation). |
Benefits through contribution to decarbonisation of electricity generation through the long-term operation of the wind farms ( i.e. displacement of non-renewable power generation). |
Marine geology and coastal processes [6] |
Summary of key potential effects on geology:
Key measures to prevent adverse effects may include: siting devices away from sensitive and designated areas; using best practice methodologies and technologies to minimise potential impacts during installation; adoption of appropriate management planning in installation works. |
||||
Direct adverse impacts to the seabed are likely from preparation of the seabed ( i.e. limited dredging) and in the placement of the gravity-base foundation and associated scour protection on the seabed. Potential alteration of sediment dynamics and tidal flows/fluxes from the presence of gravity-based foundation structures on the seabed and presence of turbine masts and support structures in the water column. Impacts such as scouring, deposition and abrasion (particularly in the placement of mooring lines, if used) may also occur due to the foundation structures present at the seabed. However, it is assumed that scour protection would be used for such foundation structures and this may alleviate such risks. Impacts from construction and decommissioning works are likely to be temporary and are often reversible. However, impacts from seabed preparation works are likely to be permanent. Sourcing of fill or dredged material for gravity foundations, and potential impacts of taking fill from other areas. If terrestrial fill or dredged material is used, potential impacts at the source may include: loss of substrata or habitat if taken from suitable undisturbed areas; Potential for release of contaminated materials bonded to dredged sediments; potential for cross-contamination from source areas to windfarm site, particularly if sourced from shipping lanes or harbours; potential impacts on hydrodynamics and water flows at the source location from the removal of sediments; reduced water quality and increased turbidity from sediment disturbance during dredging operations; and potential impacts for marine fauna and flora, including the disturbance and physical injury risk from dredging operations. If material is sourced from the terrestrial environment it will have effects associated with the removal of material and its transportation. |
Potential for direct adverse impacts to the seabed during piling operations. Potential alteration of sediment dynamics and tidal flows/fluxes from the presence of piles and turbine structures into the seabed and presence of the turbine masts and support structures in the water column. Impacts such as scouring, deposition, abrasion (during installation of piles only) and vibration may also occur due to the installation and operation of the wind turbines. Impacts from construction and decommissioning works are likely to be temporary and are often reversible. |
Potential for direct adverse impacts to the seabed during piling operations. Potential alteration of sediment dynamics and tidal flows/fluxes from the presence of piles and turbine structures into the seabed and presence of turbine masts and support structures in the water column. Impacts such as scouring, deposition, abrasion (during installation of piles only) and vibration may also occur due to the installation and operation of the wind turbines. Impacts from construction and decommissioning works are likely to be temporary and are often reversible. |
Likely direct adverse impacts to the seabed from the preparation of seabed areas ( i.e. dredging) and placement of caisson support structures directly on the seabed ( e.g. turbidity, sediment disturbance, loss of geology, potential for release of contaminated materials bonded to sediments). Potential alteration of sediment dynamics and tidal flows/fluxes from the presence of gravity-based foundation structures on the seabed and presence of the turbine masts and support structures in the water column. Impacts such as scouring, deposition and abrasion (particularly in the placement of mooring lines, if used) may also occur due to the foundation structures present at the seabed. However, it is assumed that scour protection would be used for such foundation structures. Impacts from construction and decommissioning works are likely to be temporary and are often reversible. However, impacts from seabed preparation works are likely to be permanent. |
Potential for direct adverse impacts to the seabed from the placement of gravity concrete anchors and moorings directly on the seabed. Potential alteration of sediment dynamics and tidal flows/fluxes from the presence of anchor structures gravity-based foundation structures on the seabed and presence of moorlines in the water column. Impacts such as scouring, deposition and abrasion (particularly in the placement of mooring lines, if used) may also occur due to the foundation structures present at the seabed. However, it is assumed that scour protection would be used for such foundation structures. Impacts from construction and decommissioning works are likely to be temporary and are often reversible. |
|
Historic Environment [7] |
Summary of key potential effects on marine and coastal historic environment include:
Key measures to prevent adverse effects may include: avoid sites of interest and exclusion zones for protected sites; follow Crown Estates 2007 JNAPC Code of Practice for seabed developers; carry out seabed surveys and walkover surveys prior to installation; carry out detailed routing studies at project level in accordance with 'Holford Rules' best practice guidance on routeing overhead transmission lines. |
||||
Potential for placement of gravity-based foundations and scour protection on known and designated historic sites and their exclusion zones, WHS, coastal listed buildings such as lighthouses, scheduled monuments and other unknown, submerged or non-designated archaeological assets features or paleo-landscapes to create adverse impacts. The potential scouring, siltation and deposition around these important sites located in the vicinity of such devices or arrays may also occur. However, adverse effects are likely to be avoided through careful siting of individual device foundations and arrays, although this may be more difficult for larger gravity bases or arrays of bases. |
Potential for piling operations on or close to known and designated historic sites and their exclusion zones, WHS, coastal listed buildings such as lighthouses, scheduled monuments and other unknown, submerged or non-designated archaeological assets features or paleo-landscapes to create adverse impacts. Adverse effects are likely to be avoided through careful siting of device monopiles and arrays. |
Potential for piling operations on or close to known and designated historic sites and their exclusion zones, WHS, coastal listed buildings such as lighthouses, scheduled monuments and other unknown, submerged or non-designated archaeological assets features or paleo-landscapes to create adverse impacts. Adverse effects are likely to be avoided through careful siting of device piles and arrays. |
Potential for placement of foundations and caisson structures directly on the seabed in the vicinity of known and designated historic sites and their exclusion zones, WHS, coastal listed buildings such as lighthouses, scheduled monuments and other unknown, submerged or non-designated archaeological assets features or paleo-landscapes to create adverse impacts. The potential scouring, siltation and deposition around these important sites located in the vicinity of such devices or arrays may also occur. However, adverse effects are likely to be avoided through careful siting of individual device foundations and arrays, although this may be more difficult for larger gravity bases or arrays of bases. |
Potential for placement of concrete gravity anchors directly on the seabed, and installation of mooring lines in the vicinity of known and designated historic sites and their exclusion zones, WHS, coastal listed buildings such as lighthouses, scheduled monuments and other unknown, submerged or non-designated archaeological assets features or paleo-landscapes to create adverse impacts. The potential scouring, siltation and deposition around these important sites located in the vicinity of such anchors may also occur. However, adverse effects are likely to be avoided through careful siting of these anchors and installation of mooring cables. |
|
Landscape/ Seascape [8] |
Summary of key potential effects on land/seascape include:
Key measures to prevent adverse effects may include: maximising the distance of devices from shore; reducing the height of devices above the water surface; reducing the area of sea occupied by the devices; and modifying the position and layout of devices to suit characteristics of the local seascape; carry out detailed routing studies at project level in accordance with 'Holford Rules' best practice guidance on routeing overhead transmission lines; provide screening for substations. |
||||
Potential for turbines and supporting infrastructure ( i.e. additional platforms, construction, maintenance or decommissioning vessels and equipment) to adversely impact on valued receptors ( i.e. designated or valued landscapes/seascapes). In general, greater impacts are likely for near-shore devices than those located further offshore. Field observations of offshore wind facilities in the United Kingdom revealed that the facilities may be visible at distances of 26 miles (42 km) in daytime and 24 miles (39 km) in night-time views. They may be a focus of visual attention at distances of up to 10 miles (16 km). Potential onshore impacts from supporting grid infrastructure and interconnectors with terrestrial grid, although these will likely depend on siting and surroundings ( i.e. proximity to valued or sensitive landscapes/seascapes). The potential for landscape impacts at the source of excavated terrestrial fill material, or from dredging areas for use as ballast in gravity-based foundations has also been identified. |
Potential for turbines and supporting infrastructure ( i.e. additional platforms, construction, maintenance or decommissioning vessels and equipment) to adversely impact on valued receptors ( i.e. designated or valued landscapes/seascapes). In general, greater impacts are likely for near-shore devices than those located further offshore. Field observations of offshore wind facilities in the United Kingdom revealed that the facilities may be visible at distances of 26 miles (42 km) in daytime and 24 miles (39 km) in night-time views. They may be a focus of visual attention at distances of up to 10 miles (16 km). Potential onshore impacts from supporting grid infrastructure and interconnectors with terrestrial grid, although these will likely depend on siting and surroundings ( i.e. proximity to valued or sensitive landscapes/seascapes). |
Potential for turbines and supporting infrastructure ( i.e. additional platforms, construction, maintenance or decommissioning vessels and equipment) to adversely impact on valued receptors ( i.e. designated or valued landscapes/seascapes). In general, greater impacts are likely for near-shore devices than those located further offshore. Field observations of offshore wind facilities in the United Kingdom revealed that the facilities may be visible at distances of 26 miles (42 km) in daytime and 24 miles (39 km) in night-time views. They may be a focus of visual attention at distances of up to 10 miles (16 km). Potential onshore impacts from supporting grid infrastructure and interconnectors with terrestrial grid, although these will likely depend on siting and surroundings ( i.e. proximity to valued or sensitive landscapes/seascapes). |
Potential for turbines and supporting infrastructure ( i.e. additional platforms, construction, maintenance or decommissioning vessels and equipment) to adversely impact on valued receptors ( i.e. designated or valued landscapes/seascapes). In general, greater impacts are likely for near-shore devices than those located further offshore. Field observations of offshore wind facilities in the United Kingdom revealed that the facilities may be visible at distances of 26 miles (42 km) in daytime and 24 miles (39 km) in night-time views. They may be a focus of visual attention at distances of up to 10 miles (16 km). Potential onshore impacts from supporting grid infrastructure and interconnectors with terrestrial grid, although these will likely depend on siting and surroundings ( i.e. proximity to valued or sensitive landscapes/seascapes). |
Potential for turbines and supporting infrastructure ( i.e. additional platforms, construction, maintenance or decommissioning vessels and equipment) to adversely impact on valued receptors ( i.e. designated or valued landscapes/seascapes). In general, greater impacts are likely for near-shore devices than those located further offshore. Field observations of offshore wind facilities in the United Kingdom revealed that the facilities may be visible at distances of 26 miles (42 km) in daytime and 24 miles (39 km) in night-time views. They may be a focus of visual attention at distances of up to 10 miles (16 km). Potential onshore impacts from supporting grid infrastructure and interconnectors with terrestrial grid, although these will likely depend on siting and surroundings ( i.e. proximity to valued or sensitive landscapes/seascapes). |