Schedule 2.1 Total Changes for the Autumn Budget Revision
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Total Budget in the Budget Act | 6,573.130 | 135.500 | 6,708.631 |
Changes Proposed | |||
Funding Changes | 29.060 | 0.000 | 29.060 |
Technical Adjustment | -0.681 | 0.208 | -0.473 |
Net Whitehall Transfers | 5.795 | 0.000 | 5.795 |
Net Transfers within Scottish Block | -53.389 | -27.000 | -80.389 |
Total changes proposed | -19.215 | -26.792 | -46.007 |
6,553.915 | 108.708 | 6,662.624 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Expenditure Limit: | |||
Third Sector | 21.572 | 0.000 | 21.572 |
Housing and Building Standards | 580.991 | 68.300 | 649.291 |
Cladding | 29.694 | 0.000 | 29.694 |
Tackling Child Poverty and Social Justice | 52.126 | 0.000 | 52.126 |
Equalities, Inclusion and Human Rights | 48.846 | 0.000 | 48.846 |
Connected Communites | 92.245 | 0.000 | 92.245 |
Social Security | 458.339 | 67.239 | 525.578 |
Social Security Assistance | 5,137.900 | 0.000 | 5,137.900 |
Ukrainian Resettlement | 102.271 | 0.000 | 102.271 |
Migration Strategy | 2.931 | 0.000 | 2.931 |
Total Expenditure Limit | 6,526.915 | 135.539 | 6,662.455 |
UK Funded AME: | |||
Social Security (AME) | 0.000 | 0.169 | 0.169 |
Total UK Funded AME | 0.000 | 0.169 | 0.169 |
Other Expenditure: | |||
Total Other Expenditure | 0.000 | 0.000 | 0.000 |
Total Budget | 6,526.915 | 135.708 | 6,662.624 |
Total Limit on Income (accruing resources) | 90.000 |
Schedule 3.1 Third Sector
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 21.768 | 0.000 | 21.768 |
Proposed changes | -0.196 | 0.000 | -0.196 |
ABR Proposed Budget | 21.572 | 0.000 | 21.572 |
Summary of proposed changes | |||
Miscellaneous Minor Transfers | -0.196 | 0.000 | -0.196 |
-0.196 | 0.000 | -0.196 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 21.572 | 0.000 | 21.572 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
21.572 | 0.000 | 21.572 | |
Budget Analysis | |||
Third Sector | 21.572 | 0.000 | 21.572 |
Net Expenditure | 21.572 | 0.000 | 21.572 |
Schedule 3.2 Housing
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 654.867 | 68.300 | 723.167 |
Proposed changes | -73.876 | 0.000 | -73.876 |
ABR Proposed Budget | 580.991 | 68.300 | 649.291 |
Summary of proposed changes | |||
Funding from Net Zero for the Fuel Insecurity Fund | 20.000 | 0.000 | 20.000 |
Funding from Net Zero for the insallation of zero emission heating systems as part of the Affordable Homes Programme | 15.000 | 0.000 | 15.000 |
Funding to Local Government for Discretionary Housing Payments | -70.763 | 0.000 | -70.763 |
Funding to Local Government for the Rapid Rehousing Transition Plan | -33.500 | 0.000 | -33.500 |
Funding to Scottish Courts and Tribunal Service for Housing & Property Chamber - Private Rented Sector | -1.823 | 0.000 | -1.823 |
Miscellaneous Minor Transfers | -1.790 | 0.000 | -1.790 |
Funding to Local Government for Housing Support Grant | -1.000 | 0.000 | -1.000 |
-73.876 | 0.000 | -73.876 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 580.991 | 68.300 | 649.291 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
580.991 | 68.300 | 649.291 | |
Budget Analysis | |||
More Homes | 512.951 | 68.300 | 581.251 |
Housing Support | 44.477 | 0.000 | 44.477 |
Fuel Poverty/Energy Efficiency | 22.009 | 0.000 | 22.009 |
Building Standards | 1.554 | 0.000 | 1.554 |
Net Expenditure | 580.991 | 68.300 | 649.291 |
Schedule 3.3 Cladding
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 29.717 | 0.000 | 29.717 |
Proposed changes | -0.023 | 0.000 | -0.023 |
ABR Proposed Budget | 29.694 | 0.000 | 29.694 |
Summary of proposed changes | |||
Miscellaneous Minor Transfers | -0.023 | 0.000 | -0.023 |
-0.023 | 0.000 | -0.023 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 29.694 | 0.000 | 29.694 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
29.694 | 0.000 | 29.694 | |
Budget Analysis | |||
Cladding | 29.694 | 0.000 | 29.694 |
Net Expenditure | 29.694 | 0.000 | 29.694 |
Schedule 3.4 Tackling Child Poverty and Social Justice
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 52.934 | 0.000 | 52.934 |
Proposed changes | -0.808 | 0.000 | -0.808 |
ABR Proposed Budget | 52.126 | 0.000 | 52.126 |
Summary of proposed changes | |||
Funding to Local Government for Free Period Products in Public Places | -2.782 | 0.000 | -2.782 |
Funding to Local Government for Free Period Products in Schools | -2.086 | 0.000 | -2.086 |
Funding from Whitehall for Debt Advice Levy | 5.795 | 0.000 | 5.795 |
Miscellaneous Minor Transfers | -1.735 | 0.000 | -1.735 |
-0.808 | 0.000 | -0.808 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 52.126 | 0.000 | 52.126 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
52.126 | 0.000 | 52.126 | |
Budget Analysis | |||
Communities Analysis | 6.773 | 0.000 | 6.773 |
Social Justice | 45.353 | 0.000 | 45.353 |
Net Expenditure | 52.126 | 0.000 | 52.126 |
Schedule 3.5 SJ Central Government Grants to Local Authorities
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 92.245 | 0.000 | 92.245 |
Proposed changes | 0.000 | 0.000 | 0.000 |
ABR Proposed Budget | 92.245 | 0.000 | 92.245 |
Summary of proposed changes | |||
0.000 | 0.000 | 0.000 | |
0.000 | 0.000 | 0.000 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 92.245 | 0.000 | 92.245 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
92.245 | 0.000 | 92.245 | |
Budget Analysis | |||
Transfer of the Management of Development Funding | 92.245 | 0.000 | 92.245 |
Net Expenditure | 92.245 | 0.000 | 92.245 |
Schedule 3.6 Social Security
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 458.470 | 67.200 | 525.670 |
Proposed changes | -0.131 | 0.208 | 0.077 |
ABR Proposed Budget | 458.339 | 67.408 | 525.747 |
Summary of proposed changes | |||
Miscellaneous minor transfer | -0.452 | 0.000 | -0.452 |
SSS Technical Adjustment - IFRS 16 Leases | 0.321 | 0.208 | 0.529 |
-0.131 | 0.208 | 0.077 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 458.339 | 67.408 | 525.747 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
458.339 | 67.408 | 525.747 | |
Budget Analysis | |||
Social Security Scotland | 298.334 | 4.539 | 302.873 |
Social Security Advice Policy and Programme Costs | 154.532 | 62.700 | 217.232 |
Scottish Welfare Fund Administration | 5.473 | 0.000 | 5.473 |
Social Security (AME) | 0.000 | 0.169 | 0.169 |
Net Expenditure | 458.339 | 67.408 | 525.747 |
Schedule 3.7 Social Security Assistance
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 5,137.900 | 0.000 | 5,137.900 |
Proposed changes | 0.000 | 0.000 | 0.000 |
ABR Proposed Budget | 5,137.900 | 0.000 | 5,137.900 |
Summary of proposed changes | |||
0.000 | 0.000 | 0.000 | |
0.000 | 0.000 | 0.000 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 5,137.900 | 0.000 | 5,137.900 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
5,137.900 | 0.000 | 5,137.900 | |
Budget Analysis | |||
Personal Independence Payment | 2,689.600 | 0.000 | 2,689.600 |
Attendance Allowance | 614.100 | 0.000 | 614.100 |
Scottish Child Payment | 442.100 | 0.000 | 442.100 |
Disability Living Allowance (Adult) | 437.600 | 0.000 | 437.600 |
Carer's Allowance | 371.800 | 0.000 | 371.800 |
Child Disability Assistance (DLA Child and DACYP) | 327.600 | 0.000 | 327.600 |
Industrial Injuries Disablement Scheme | 84.400 | 0.000 | 84.400 |
Carer's Allowance Supplement | 50.000 | 0.000 | 50.000 |
Scottish Welfare Fund | 35.500 | 0.000 | 35.500 |
Low Income Winter Heating Assitance | 23.600 | 0.000 | 23.600 |
Best Start Grant | 19.800 | 0.000 | 19.800 |
Best Start Food Grant | 17.000 | 0.000 | 17.000 |
Funeral Support Payment | 12.100 | 0.000 | 12.100 |
Severe Disablement Allowance | 5.800 | 0.000 | 5.800 |
Child Winter Heating Allowance | 4.700 | 0.000 | 4.700 |
Job Start Payment | 1.200 | 0.000 | 1.200 |
Young Carer Grant | 1.000 | 0.000 | 1.000 |
Net Expenditure | 5,137.900 | 0.000 | 5,137.900 |
Schedule 3.8 Equalities, Inclusion and Human Rights
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 52.937 | 0.000 | 52.937 |
Proposed changes | -4.091 | 0.000 | -4.091 |
ABR Proposed Budget | 48.846 | 0.000 | 48.846 |
Summary of proposed changes | |||
Transfer to Migration Strategy | -2.931 | 0.000 | -2.931 |
Miscellaneous Minor Transfers | -1.160 | 0.000 | -1.160 |
-4.091 | 0.000 | -4.091 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 48.846 | 0.000 | 48.846 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
48.846 | 0.000 | 48.846 | |
Budget Analysis | |||
Equalities, Inclusion and Human Rights | 48.846 | 0.000 | 48.846 |
Net Expenditure | 48.846 | 0.000 | 48.846 |
Schedule 3.9 Ukrainian Resettlement
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 72.292 | 0.000 | 72.292 |
Proposed changes | 29.979 | 0.000 | 29.979 |
ABR Proposed Budget | 102.271 | 0.000 | 102.271 |
Summary of proposed changes | |||
Additional support for Ukranian Resettlement | 30.000 | 0.000 | 30.000 |
Miscellaneous minor transfers | -0.021 | 0.000 | -0.021 |
29.979 | 0.000 | 29.979 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 102.271 | 0.000 | 102.271 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
102.271 | 0.000 | 102.271 | |
Budget Analysis | |||
Ukrainian Resettlement | 102.271 | 0.000 | 102.271 |
Net Expenditure | 102.271 | 0.000 | 102.271 |
Schedule 3.10 Migration Strategy
Details of Proposed Budget
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Original Budget | 0.000 | 0.000 | 0.000 |
Proposed changes | 2.931 | 0.000 | 2.931 |
ABR Proposed Budget | 2.931 | 0.000 | 2.931 |
Summary of proposed changes | |||
Transfer from Equalities, Inclusion and Human Rights | 2.931 | 0.000 | 2.931 |
2.931 | 0.000 | 2.931 |
Operating £m | Capital £m | Total £m | |
---|---|---|---|
Gross Expenditure | 2.931 | 0.000 | 2.931 |
Less: Retained Income | 0.000 | 0.000 | 0.000 |
Capital Receipts Applied | 0.000 | 0.000 | 0.000 |
2.931 | 0.000 | 2.931 | |
Budget Analysis | |||
Migration Strategy | 2.931 | 0.000 | 2.931 |
Net Expenditure | 2.931 | 0.000 | 2.931 |