Autumn Budget Revision 2024-25 – Supporting Document

Supporting document to the Budget (Scotland) Act 2024 Amendment Regulations 2024. Provides details of Level 2 and 3 budgets.


Environmental Standards Scotland

Schedule 2.1 Total Changes for the Autumn Budget Revision

Operating £m Capital £m Total £m
Total Budget in the Budget Act 3.020 0.000 3.020
Changes Proposed
Funding Changes -0.100 0.000 -0.100
Technical Adjustments 0.000 0.000 0.000
Net Whitehall Transfers 0.000 0.000 0.000
Net Transfers within Scottish Block 0.000 0.000 0.000
Total changes proposed -0.100 0.000 -0.100
Proposed Budget following Autumn Budget Revision 2.920 0.000 2.920
Operating £m Capital £m Total £m
Expenditure Limit:
Environmental Standards Scotland 2.920 0.000 2.920
Total Expenditure Limit 2.920 0.000 2.920
UK Funded AME:
Total UK Funded AME 0.000 0.000 0.000
Other Expenditure:
Total Other Expenditure 0.000 0.000 0.000
Total Budget 2.920 0.000 2.920
Total Limit on Income (accruing resources) 0.000

Schedule 3.1 Environmental Standards Scotland

Details of Proposed Budget

Proposed Changes
Operating £m Capital £m Total £m
Original Budget 3.020 0.000 3.020
Proposed Changes -0.100 0.000 -0.100
ABR Proposed Budget 2.920 0.000 2.920
Summary of proposed changes
Miscellaneous minor transfers -0.100 0.000 -0.100
-0.100 0.000 -0.100
Proposed Budget following Autumn Budget Revision
Operating £m Capital £m Total £m
Gross Expenditure 2.920 0.000 2.920
Less: Retained Income 0.000 0.000 0.000
Capital Receipts Applied 0.000 0.000 0.000
2.920 0.000 2.920
Budget Analysis
Environmental Standards Scotland 2.920 0.000 2.920
Net Expenditure 2.920 0.000 2.920

Contact

Email: Finance.Co-ordination@gov.scot

Back to top