APPENDIX FOUR: HOME ARGYLL LAUNCH IMPLEMENTATION TIMETABLE
Date |
Activity |
Responsibility |
Progress |
w/b 7th August |
|||
ONGOING |
Ensure that ICT systems can be adapted to new policy |
Partner RSLs |
|
w/b 14th August |
|||
14th August |
Provide list of all applicants for review of duplication between lists |
Partner RSLs |
|
14th August |
Agree responsibility for duplicate applicants |
Partner RSLs |
|
14th August |
Agree to record and analyse duplicates in applications 14th-21st August |
Partner RSLs |
|
14th August |
Agree to establish a Health and Housing Need sub group and confirm attendees |
Consultant and Partner RSLs |
|
14th August |
Decision on printing Choice of Area forms |
Partner RSLs |
|
14th August |
Agree publicity material/communication with applicants and other stakeholders |
Partner RSLs |
|
14th August |
Agree information sharing arrangements between partner |
Partner RSLs |
|
14th August |
Agree arrangements for sharing information when allocating |
Partner RSLs |
Date |
Activity |
Responsibility |
Progress |
w/b 14th August |
|||
14th August |
Agree future meeting dates |
Partner RSLs |
|
By 18th August |
Print (and distribute if necessary) Choice of Area forms |
Partner RSLs |
|
By 18th August |
Analyse duplication of applications between partners |
Consultant |
|
By 18th August |
Set up central database of all applicants |
Consultant |
|
By 16th August |
Develop procedural training programme for staff and send out agenda |
Consultant |
|
By 18th August |
Ensure HOME Argyll website is up to date and reflects launch arrangements |
ABC |
|
By 18th August |
Check key partners happy with site content - CS and Crofters Commission |
Consultant |
|
By 18th August |
Sign off HOME Argyll site and pay invoice |
Consultant |
|
By 18th August |
Sign Escrow Agreement |
ABC |
|
By 18th August |
Explore whether applicants can be offered access to the internet |
Partner RSLs |
|
By 18th August |
Finalise letter to be sent out with application forms |
Consultant and Partner RSLs |
Date |
Responsibility |
Activity |
Progress |
w/b 14th August |
|||
All week |
Ensure all staff aware of procedures for re-registration |
Partner RSLs |
|
All week |
Ensure all staff aware of HOME Argyll website and its contents |
Partner RSLs |
|
All week |
Ensure all staff aware of focus on housing information and advice |
Partner RSLs |
|
w/b 21st August |
|||
21st August |
Procedural Training - Rothesay |
Consultant facilitates |
|
21st August |
HOME Argyll site goes live |
Consultant to check and co-ordinate |
|
21st August |
Application Forms to be delivered |
Printer |
|
21st-25th August |
Re-registration letters issued |
Partner RSLs |
|
23rd August |
Procedural Training - Oban |
Consultant facilitates |
|
By 25th August |
Draft Procedural Manual for staff |
Consultant and Partner RSLs |
|
By 25th August |
Develop standard forms |
Consultant and Partner RSLs |
Date |
Responsibility |
Activity |
Progress |
w/b 28th August |
|||
29th August |
Steering Group meeting |
Partner RSLs/Consultant |
|
29th August |
First meeting of Health and Housing Need sub group - training and discussion of responses to date |
Consultant facilitates |
|
31st August |
Procedural Training - Ardrishaig |
Consultant facilitates |
|
All week (ongoing) |
Send out acknowledgement slips for applications received - state which landlords interested in |
Partner RSLs |
|
All week (ongoing) |
Copy forms to other partner RSLs |
||
w/b 4th September |
|||
4th September |
Procedural Training - Dumbarton |
Consultant facilitates |
|
All week |
Staff trained on using ICT systems with new policies and procedures |
Partner RSLs |
|
8th September |
Deadline for initial responses to be received |
Partner RSLs |
|
8th September |
Database of responses to be sent to ACHA |
Partner RSLs |
Date |
Activity |
Responsibility |
Progress |
w/b 11th September |
|||
11th September |
Analyse non respondents and update database |
ACHA |
|
12th September |
Issue reminder letters (with option to state form returned to another RSL) |
Partner RSLs |
|
12th September |
Steering Group meeting |
Partner RSLs/ Consultant |
|
All week (ongoing) |
Begin processing forms |
Partner RSLs |
|
All week (ongoing) |
Issue pointing letters as processed |
Partner RSLs |
|
By 15th September |
Agree arrangements for homelessness information sharing |
Homelessness/Partner RSLs/ Consultant |
|
15th September |
Final responses required |
Partner RSLs |
|
15th September |
Database of responses to be sent to ACHA |
Partner RSLs |
|
w/b 18th September |
|||
18th September |
Housing lists close - preallocate as much as possible |
Partner RSLs |
|
All week |
Input new application forms |
Partner RSLs |
|
All week |
Ensure information on ALL applicants sent to appropriate RSLs |
Partner RSLs |
Date |
Activity |
Responsibility |
Progress |
w/b 25th September |
|||
All week |
Ensure information on ALL applicants sent to appropriate RSLs |
Partner RSLs |
|
26th September |
Steering Group meeting |
Partner RSLs/ ODS |
|
By 29th September |
Issue letter saying removed from list if not responded |
Partner RSLs |
|
w/b 2nd October |
|||
All week |
Assess who has NOT responded to review (to any RSL) |
Partner RSLs |
|
w/b 9th October |
|||
9th October |
|||
10th October |
Steering Group meeting |
Partner RSLs/ ODS |
|
Ongoing |
|||
October 2006 onwards |
Keep up to date with ICT progress |
Partner RSLs - lead ACHA |
|
November 2006 onwards |
Roll out health and housing need training |
Partner RSLs |
|
2007 |
Stock familiarisation programme |
Partner RSLs |
|
2007 |
Establish links with Move UK |
Partner RSLs |
|
2007 |
Joint mutual exchange procedures |
Partner RSLs |