Delivery Assurance Group (DAG) report: quarter 1 2021 to 2022
Report summarising what has been achieved for customers against Scottish Water's Delivery Plan for the 2021 to 2027 period during the first quarter of 2021 to 2022.
Appendix A: Summary of milestone achievement
The table below provides a summary of the number of milestones ahead, behind and on track at Quarter 1 2021-22.
Milestone | Number Ahead (over 3 months early compared to baseline) | Number on Track | Number Behind (Over 3 months late compared to baseline) | Total Number | Percentage on Track |
---|---|---|---|---|---|
Start on Site | 0 | 17 | 0 | 17 | 100.0% |
Project Acceptance | 0 | 48 | 4 | 52 | 92.3% |
Financial Close | 0 | 4 | 1 | 5 | 80.0% |
Total | 0 | 69 | 5 | 74 | 93.2% |