Delivery Assurance Group (DAG) report: quarter 1 2021 to 2022

Report summarising what has been achieved for customers against Scottish Water's Delivery Plan for the 2021 to 2027 period during the first quarter of 2021 to 2022.


Appendix B: Key projects of interest

This appendix provides summaries of key projects that may be of interest to stakeholders.

SR15 Completion

Ayrshire Strategic Resilience

Ayrshire Strategic Resilience is a major infrastructure project to connect the Glasgow water supply to Ayrshire.

The main risks to delivery are related to construction and is being actively managed.

Pipelaying progressing on three fronts and accelerating work on private land to make best use of weather conditions.

Project has set up virtual town hall to provide information on the works and measures we are taking to minimise disruption and all residents along route have received information letter.

Project Acceptance (Committed List Date)

23/24 Q2

Project Acceptance (Forecast)

23/24 Q4

Water Portfolio

SR21 Bonnycraig Water Treatment Works (WTW) Growth & Quality

The Bonnycraig project creates the new treatment capability, improves existing storage and roadway and decommissions the existing treatment capacity.

Constructions risks to the successful delivery, within required timescale are being closely managed.

Bulk earthworks are progressing well.

Project Acceptance (Committed List Date)

23/24 Q4

Project Acceptance (Forecast)

23/24 Q3

Wastewater portfolio

Barmore Road, Tarbert

Barmore Road Tarbert is a flooding project to remove unacceptable flooding risk to 4 properties internally, 1 externally and 2 areas of highway flooding. This project creates online storage in the form of combined sewerage within the busy main road (A83), in popular area for residents and tourist alike.

Traffic management has been well managed, working closely with BEAR/Transport Scotland

Traffic management expected to be lifted in August 2021.

Community relationships have been excellent, and a final community newsletter is planned to thank the community for their patience during the period of construction.

Project Acceptance (Committed List Date)

21/22 Q4

Project Acceptance (Forecast)

21/22 Q3

Contact

Email: waterindustry@gov.scot

Back to top