6. Overall Project Progress CE&FS&SS Portfolio
The CE&FS&SS Portfolio comprises 4 sub portfolios: Digital, Flourishing Scotland, Property and Estates and Other Services. Detail on progress within each of the sub-portfolios can be found in Appendix C. Year to date performance is at the middle of the range (Figure 13). All milestones are within the range.
SOS
Performance on the Start on Site milestone (Figure 14) remains good. The Flourishing Scotland and Other sub-portfolios achieved the central plan target. 8 projects have now started on site. 1 of these (Server and Storage Project) starting in Q2.
Acceptance
The Gate 100 Acceptance milestone (Figure 15) on all 4 of the sub programmes is within the range. 13 projects have achieved GATE 100 Acceptance. 1 project (Inverness Laboratory Extension) had been delayed but is now substantially complete with acceptance forecast in Q3.
Financial Completion
14 projects have achieved the gate 110 milestone to date. 2 of these in Q2 (Dumfries Office Marchmount and Lincluden Depots in the Property sub-programme and Cost Investment Intelligence in the Digital sub programme).