Scottish Water - Delivery Assurance Group: performance progress report - quarter four 2022-2023

Sets out how Scottish Water is progressing with the delivery of projects and programmes included on the ‘Committed List’ and confirms the position up to the end of March 2023 (Q4 2022/23).


6. Overall Project Progress CE&FS&SS Portfolio

The CE&FS&SS Portfolio comprises 4 sub portfolios: Digital, Flourishing Scotland, Property and Estates and Other Services. Detail on progress within each of the sub-portfolios can be found in Appendix C. Year to date performance at 49 points is at the top of the 40 to 49 range (Figure 13). All milestones are within the range.

Figure 13: Indicator of progress of Overall Delivery (IPOD) at Quarter 4 2022/2023 for all CE&FS&SS Portfolio projects
Chart showing IPOD points achieved or forecast for all milestones against target range for all projects in CE&FS&SS Portfolio

Start On Site

Performance on the Start On Site milestone (Figure 14) remains good. The Flourishing Scotland and Other sub-portfolios achieved the central plan target. 17 projects have now started on site, against a range of 11 to 17. 7 of these projects started in Q4.

Figure 14: Indicator of progress of Overall Delivery (IPOD) at Quarter 4 2022/2023 for Start On Site of all CE&FS&SS Portfolio projects
Chart showing IPOD points achieved or forecast for Start on Site milestone against target range for all projects in CE&FS&SS Portfolio

Acceptance

The Gate 100 Acceptance milestone (Figure 15) on all 4 of the sub programmes are within the range. 16 projects have achieved Gate 100 Acceptance, against a range of 15 to 16. 2 projects achieved acceptance in Q4.

Figure 15: Indicator of progress of Overall Delivery (IPOD) at Quarter 4 2022/2023 for Gate 100 (Project Acceptance) of all CE&FS&SS Portfolio projects
Chart showing IPOD points achieved or forecast for Project Acceptance milestone against target range for all projects in CE&FS&SS Portfolio

Financial Completion

16 projects have achieved the Gate 110 milestone to date, against a range of 14 to 16. 2 projects achieved this gate in Q4.

Figure 16: Indicator of progress of Overall Delivery (IPOD) at Quarter 4 2022/2023 for Gate 110 (Financial Completion) of all CE&FS&SS Portfolio projects
Chart showing IPOD points achieved or forecast for Financial Completion milestone against target range for all projects in CE&FS&SS Portfolio

Contact

Email: waterindustry@gov.scot

Back to top