Delivery Assurance Group (DAG) report: quarter 3 2021-2022

Report summarising what has been achieved for customers against Scottish Water's Delivery Plan for the 2021 to 2027 period during the third quarter of 2021 to 2022


Appendix A: summary of milestone attainment position at Q3 2021/22

Table 1: summary milestone position at Q3
Gate lower limit (-3 months) Baseline upper limit (+ 3 months) Q3 Actual Q3 Status Status at Q2
SOS (G95) 32 48 52 47 Within target range Within target range
Acceptance (G100) 112 149 184 109 Below target range Within target range
Financial Completion (G110) 5 37 79 51 Within target range Within target range
Total 149 234 315 207 Within target range Within target range

Both the Start on Site (G95) and the Financial Completion (G110) Milestones are currently within the target range and are forecast to remain within the range at year end. The Acceptance (G100) milestone is currently slightly below the target range but forecast to recover at year end. Although we have experienced 3rd party delays and delay due to COVID-19 restrictions, most of the delay associated with projects achieving acceptance (G100) is a result of construction risks being realised.

Table 2: Forecast of milestone position at year end
  lower limit (-3 months) Baseline upper limit (+ 3 months) Q3 Year End Forecast Q3 Year End Status Forecast Year End Status Forecast at Q2
SOS (G95) 48 52 55 53 Within target range Within target range
Acceptance (G100) 149 184 210 164 Within target range Within target range
Financial Completion (G110) 37 79 130 111 Within target range Within target range
Total 234 315 395 328 Within target range Within target range

We are forecasting that all the milestone areas will be within the target range at year end.