Renewable and zero emissions heating systems in affordable housing projects: evaluation
An evaluation of renewable and zero emissions heating systems in 21 Scottish affordable housing projects. This study assesses the estimated, actual, and counterfactual costs of the projects’ heating systems and determines the drivers behind decision making.
Appendix B. Individual project data
B0. Overview
In this appendix, the information collected for each project is presented in two tables – an overview and then a per-unit cost breakdown. The second table has not been included if insufficient data was provided, and this is explained in the project's overview. If data is not available but it has been possible to estimate a value, cells are marked with a (B) and the estimation is explained underneath. Where information is yet to be established because the project is at an early stage, cells are marked (P).
An example overview table is provided below, which lists and explains the metrics considered for each of the projects.
Metric | Information |
---|---|
Location | The project's local authority area |
Unit count | The number of affordable housing units included in the project |
Unit types | The number of different affordable housing unit types included in the project |
Progress | Whether the project is in the pre-construction phase, under construction or complete |
On-gas grid | Whether the project is situated on or off the gas grid |
Section 75 | Whether or not the project forms the Section 75 affordable housing obligation for a larger development |
Sustainability target | The energy demand target that the project is designed to achieve |
Heating system | The technology (or technologies) that are included in the project's heating and hot water generation and storage system |
Capex extent | The components and services included in the capital expenditure (capex) cost provided |
Capex source | The source of the capex figure |
Opex | Whether the project estimated an operational cost (opex) to the occupants to run the heating system |
Counterfactual | Whether the project has costed an alternative (counterfactual) heating system |
B1. Solar PV (individual)
Project 1
An overview of Project 1 is provided in Table 22. A per-unit table has also been provided.
Metric | Information |
---|---|
Location | North Ayrshire |
Unit count | 34 |
Unit types | 7 |
Progress | Under construction |
On-gas grid | No |
Section 75 | No |
Sustainability target | Aspect Silver Level 1 and 2 |
Heating system | Rooftop solar PV modules, electric boiler |
Capex extent | Installed costs of PV, boiler |
Capex source | Averaged actual costs |
Opex | Estimates provided |
Counterfactual | None considered |
Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
---|---|---|---|---|---|---|---|
Description | 2-bed mid (A) | 2-bed mid (B) | 2-bed end | 2-bed bungalow | 2-bed WC bungalow | 3-bed det. | 4-bed WC det. |
Count | 3 | 6 | 8 | 8 | 2 | 3 | 4 |
Footprint (m2) | 88 | 84 | 83 | 63 | 63 | 119 | 112 |
Heat demand | 3598 | 3523 | 3902 | 3485 | 3561 | 5227 | 5000 |
Heat demand per m2 | 41.0 | 41.7 | 47.1 | 55.4 | 56.6 | 44.0 | 44.6 |
Installation capex | £5,538 | £5,538 | £5,538 | £5,538 | £5,538 | £5,538 | £5,538 |
PV capex | £1,870 | £1,870 | £1,870 | £1,870 | £1,870 | £1,870 | £1,870 |
Network capex | Not considered | ||||||
Total capex | £7,408 | £7,408 | £7,408 | £7,408 | £7,408 | £7,408 | £7,408 |
Capex per m2 | £84.4 | £87.8 | £89.5 | £117.8 | £117.8 | £62.4 | £66.0 |
Est. opex | £475 | £465 | £515 | £460 | £470 | £690 | £660 |
Est. opex per m2 | £5.4 | £5.5 | £6.2 | £7.3 | £7.5 | £5.8 | £5.9 |
Project 2
An overview of Project 2 is provided in Table 24. A per-unit table has also been provided.
Metric | Information |
---|---|
Location | North Ayrshire |
Unit count | 18 |
Unit types | 7 |
Progress | Under construction |
On-gas grid | No |
Section 75 | No |
Sustainability target | Aspect Silver Level 1 and 2 |
Heating system | Rooftop solar PV modules, electric boiler |
Capex extent | Averaged actual costs |
Capex source | Actual costs |
Opex | Estimates provided |
Counterfactual | None considered |
Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
---|---|---|---|---|---|---|---|
Description | 3-bed end | 3-bed terrace | 2-bed end | 2-bed mid | 2-bed WC bungalow | 3-bed WC det. | 4-bed WC det. |
Count | 1 | 2 | 7 | 2 | 3 | 2 | 1 |
Footprint (m2) | 96 | 93 | 63 | 63 | 63 | 119 | 143 |
Heat demand | 4205 | 3712 | 3598 | 3333 | 3598 | 5152 | 6606 |
Heat demand per m2 | 44.0 | 39.9 | 57.2 | 53.3 | 57.2 | 43.4 | 46.3 |
Installation capex | £4,675 | £4,675 | £4,675 | £4,675 | £4,675 | £4,675 | £4,675 |
PV capex | £1,603 | £1,603 | £1,603 | £1,603 | £1,603 | £1,603 | £1,603 |
Network capex | Not considered | ||||||
Total capex | £6,278 | £6,278 | £6,278 | £6,278 | £6,278 | £6,278 | £6,278 |
Capex per m2 | £65.7 | £67.5 | £99.8 | £100.4 | £99.8 | £52.9 | £44.0 |
Est. opex | £555 | £490 | £475 | £440 | £475 | £680 | £872 |
Est. opex per m2 | £5.8 | £5.3 | £7.6 | £7.0 | £7.6 | £5.7 | £6.1 |
Project 3
An overview of Project 3 is provided in Table 26. A per-unit table has also been provided.
Metric | Information |
---|---|
Location | North Ayrshire |
Unit count | 2 |
Unit types | 1 |
Progress | Complete |
On-gas grid | No |
Section 75 | No |
Sustainability target | Gold |
Heating system | Rooftop solar PV modules, Sunamp heat battery |
Capex extent | Sunamp and PV installation |
Capex source | Actual costs |
Opex | Estimates provided |
Counterfactual | Gas boilers and PV to meet Silver Aspects 1 and 2 |
Unit | 1 |
---|---|
Description | 2-bed terrace |
Count | 2 |
Footprint (m2) | 85 |
Heat demand | 3462 |
Heat demand per m2 | 40.5 |
Installation capex | £4,950 |
PV capex | £1,603 |
Network capex | Not considered |
Total capex | £3,520 |
Capex per m2 | £8,470 |
Est. opex | £99.2 |
Est. opex per m2 | £269 |
Alt capex | 3.1 |
Alt capex per m2 | £4,180 |
Est. alt opex | 48.9 |
Est. alt per m2 | 309 |
Project 4
An overview of Project 4 is provided in Table 28, and per-unit data in Table 29. A partial data set has been provided for this project, so the units' heat demand has been estimated.
Metric | Information |
---|---|
Location | North Lanarkshire |
Unit count | 2 |
Unit types | 1 |
Progress | Complete |
On-gas grid | Yes |
Section 75 | Yes |
Sustainability target | Gold |
Heating system | Rooftop solar PV modules, Sunamp heat battery |
Capex extent | Heating system installation, including electrician costs |
Capex source | Developer |
Opex | Not provided – estimated from maximum Gold heat demand |
Counterfactual | Not costed |
Unit | 1 |
---|---|
Description | 2-bed semi |
Count | 2 |
Footprint (m2) | 83 |
Heat demand | 2502 (B) |
Heat demand per m2 | 30 (B) |
Installation capex | £4,132 |
PV capex | £4,794 |
Network capex | Not considered |
Total capex | £8,926 |
Capex per m2 | £107.0 |
Est. opex | £246 (B) |
Est. opex per m2 | £2.9 (B) |
B2. Air Source Heat Pumps (Individual)
Project 5
An overview Project 5 is provided in Table 30, and per-unit data in Table 31. All available information is included, although a counterfactual has not been costed.
Metric | Information |
---|---|
Location | Perth & Kinross |
Unit count | 4 |
Unit types | 3 |
Progress | Pre-construction |
On-gas grid | No |
Section 75 | Yes |
Sustainability target | Silver |
Heating system | ASHPs only |
Capex extent | Heating system installation |
Capex source | Developer's estimates |
Opex | Developer's estimates |
Counterfactual | Direct electric heaters (costs not provided) |
Unit | 1 | 2 | 3 |
---|---|---|---|
Description | 3-bed semi | 2-bed GF flat | 2-bed 1F flat |
Count | 2 | 1 | 1 |
Footprint (m2) | 99 | 60 | 70 |
Heat demand | 5639 | 3656 | 4321 |
Heat demand per m2 | 57.0 | 60.9 | 61.7 |
Installation capex | £5,500 | £5,500 | £5,500 |
Network capex | Not considered | ||
Other heating capex | N/A | ||
Total capex | £5,500 | £5,500 | £5,500 |
Capex per m2 | £55.6 | £91.7 | £78.6 |
Est. opex | £437 | £366 | £400 |
Est. opex per m2 | £4.4 | £6.1 | £5.7 |
Project 6
An overview of Project 6 is provided in Table 32, and per-unit data in Table 33. All available data has been shared.
Metric | Information |
---|---|
Location | Argyll & Bute |
Unit count | 300 |
Unit types | 8 |
Progress | Under construction |
On-gas grid | No |
Section 75 | No |
Sustainability target | Silver |
Heating system | ASHPs only |
Capex extent | Heating system installation |
Capex source | Developer's estimates |
Opex | Developer's estimates |
Counterfactual | Shared biomass (costed in feasibility study) |
Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
---|---|---|---|---|---|---|---|---|
Description | 2-bed terrace | 2-bed WC semi | 3-bed semi | 4-bed semi | 1-bed flat | 1-bed WC flat | 2-bed flat | 2-bed flat |
Count | 111 | 16 | 81 | 18 | 27 | 13 | 31 | 3 |
Footprint (m2) | 89 | 95 | 106 | 122 | 52 | 69 | 77 | 97.5 |
Heat demand | 2790 | 3047 | 3045 | 3125 | 2309 | 2431 | 2601 | 2707 |
Heat demand per m2 | 31.3 | 28.7 | 25.0 | 40.6 | 44.4 | 35.2 | 26.7 | 28.5 |
Installation capex | £4,944 | £4,944 | £5,933 | £5,933 | £5,933 | £5,933 | £5,933 | £5,933 |
Network capex | Considered negligible | |||||||
Total capex | £4,944 | £4,944 | £5,933 | £5,933 | £5,933 | £5,933 | £5,933 | £5,933 |
Capex per m2 | £55.6 | £46.6 | £48.6 | £77.0 | £114.1 | £86.0 | £60.8 | £62.4 |
Est. opex | £368 | £402 | £404 | £412 | £305 | £321 | £345 | £357 |
Est. opex per m2 | £4.1 | £3.8 | £3.3 | £5.4 | £5.9 | £4.7 | £3.5 | £3.8 |
Alt capex | £3,093,400 for whole site (approx. £10,300 per unit) | |||||||
Alt capex per m2 | £115.7 | £97.2 | £84.4 | £133.8 | £198.1 | £149.3 | £105.6 | £108.4 |
Est. alt opex | £310 (B) | £338 (B) | £340 (B) | £347 (B) | £257 (B) | £270 (B) | £290 (B) | £300 (B) |
Est. alt per m2 | £3.5 (B) | £3.6 (B) | £3.2 (B) | £2.8 (B) | £4.9 (B) | £3.9 (B) | £3.8 (B) | £3.1 (B) |
Project 7
An overview of Project 7 is provided in Table 34, and per-unit data in Table 35.
Metric | Information |
---|---|
Location | Angus |
Unit count | 10 |
Unit types | 1 |
Progress | Completed |
On-gas grid | No |
Section 75 | Yes |
Sustainability target | SAP: 81 (Project set up before the introduction of current standards) |
Heating system | ASHPs only |
Capex extent | Heating system installation |
Capex source | Contractor's actual costs |
Opex | Estimates provided |
Alternative | Gas boilers |
Unit | 1 |
---|---|
Description | 3-bed semi |
Count | 10 |
Footprint (m2) | 100m2 |
Heat demand | 3571 (B) |
Heat demand per m2 | 35.7 (B) |
Equipment capex | £10,738 |
Labour capex | |
Network capex | Not considered |
Other heating capex | N/A |
Total capex | £10,738 |
Capex per m2 | £107 |
Est. opex | £500 |
Est. opex per m2 | £5.0 |
Alt capex | £2,944 |
Alt capex per m2 | £29 |
Est. alt opex | £421 (B) |
Est. alt per m2 | £4.2 (B) |
Project 8
An overview of Project 8 is provided in Table 36. A per-unit table has not been provided because the project is at an early stage and has not been costed in detail yet.
Metric | Information |
---|---|
Location | Scottish Borders |
Unit count | 4 |
Unit types | Not yet established (P) |
Progress | Preconstruction |
On-gas grid | Yes |
Section 75 | No |
Sustainability target | Silver with Gold aspects |
Heating system | ASHPs and MVHR |
Capex extent | Heating system installation |
Capex source | Housing associations' previous projects |
Opex | Not yet established (P) |
Alternative | No alternative considered |
Project 9
An overview of Project 9 is provided in Table 37. A per-unit table has not been provided because the project contact was not able to share any cost data.
Metric | Information |
---|---|
Location | Highland |
Unit count | 14 |
Unit types | 5 |
Progress | Pre-construction |
On-gas grid | No |
Section 75 | No |
Sustainability target | Bronze |
Heating system | Air to Water heat pumps; Air to Air heat pumps |
Capex extent | Not provided |
Capex source | Not provided |
Opex | Not provided |
Project 13
An overview of Project 13 is provided in Table 38, and per-unit data in Table 39. Notably, this project is the only one to date to have considered the impact of heating systems on network costs. The alternative capex in Table 39 includes an equal share of the £107k cost for the LPG system infrastructure.
Solar PV has been included as part of the heating system in the tables because the project's opex and capex figures include the impact of this technology. (This is included in the 'Other Capex' row in Table 39.)
Metric | Information |
---|---|
Location | Highland |
Unit count | 117 (87 with individual ASHP systems) |
Unit types | 9 |
Progress | Pre-construction |
On-gas grid | No |
Section 75 | No |
Sustainability target | Silver |
Heating system | ASHPs, rooftop PV and Sunamp heat batteries |
Capex extent | Installation of heating system |
Capex source | Contractor's quotation |
Opex | Estimates provided |
Alternative | LPG |
Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
---|---|---|---|---|---|---|---|---|
Description | 2-bed semi (A) | 2-bed semi (B) | 3-bed semi (A) | 3-bed semi (B) | 4-bed det. | 2-bed bungalow | 3-bed bungalow | 2-bed cottage flat |
Count | 20 | 10 | 24 | 8 | 7 | 4 | 2 | 12 |
Footprint (m2) | 92.1 | 92.1 | 103 | 103 | 117 | 89 | 108.0 | 80.3 |
Heat demand | 2570 | 2570 | 2730 | 2750 | 3580 | 3064 | 3914 | 2230 |
Heat demand per m2 | 27.9 | 27.9 | 26.5 | 26.7 | 30.6 | 34.4 | 36.2 | 27.8 |
Installation capex | £6,672 | £6,672 | £6,672 | £6,672 | £6,672 | £6,672 | £6,672 | £6,672 |
Network capex | Additional £79,806 (£682 per home) | |||||||
Sunamp + PV capex | £4,346 | £4,346 | £4,728 | £4,346 | £5,603 | £4,728 | £4,728 | £3,955 |
Total capex | £11,700 | £11,700 | £12,082 | £11,700 | £13,119 | £12,082 | £12,082 | £11,309 |
Capex per m2 | £127.0 | £127.0 | £117.3 | £113.6 | £112.1 | £135.7 | £111.9 | £140.8 |
Est. opex | £244 | £244 | £239 | £241 | £352 | £287 | £298 | £170 |
Est. opex per m2 | £2.7 | £2.7 | £2.3 | £2.3 | £3.0 | £3.2 | £2.8 | £2.1 |
Alt capex | £9,875 | £9,875 | £10,235 | £10,375 | £11,835 | £11,235 | £11,735 | £11,015 |
Alt capex per m2 | £107.2 | £107.2 | £99.4 | £100.7 | £101.1 | £126.2 | £108.7 | £137.2 |
Est. alt opex | £371 | £371 | £389 | £389 | £588 | £501 | £466 | £323 |
Est. alt per m2 | £4.0 | £4.0 | £3.8 | £3.8 | £5.0 | £5.6 | £4.3 | £4.0 |
Project 14
An overview of Project 14 is provided in Table 40. A per-unit table has not been provided as this project contact was not able to share any cost data.
Metric | Information |
---|---|
Location | Glasgow City |
Unit count | 2 |
Unit types | 1 |
Progress | Complete |
On-gas grid | Yes |
Section 75 | No |
Sustainability target | Platinum |
Heating system | ASHPs, MVHR and Sunamp heat batteries |
Capex extent | Not provided |
Capex source | Not provided |
Opex | Not provided |
Alternative | Gas |
Project 15
An overview of Project 15 is provided in Table 41, and per-unit data in Table 42. Notably, this is the only project to include solar thermal hot water generation, which has been denoted as the 'Other Capex' costs in Table 42.
Metric | Information |
---|---|
Location | Dumfries & Galloway |
Unit count | 5 |
Unit types | 3 |
Progress | Under construction |
On-gas grid | No |
Section 75 | No |
Sustainability target | Silver |
Heating system | ASHPs, MVHR and solar thermal hot water generation |
Capex extent | Heating and hot water system installation |
Capex source | Quantity surveyor's estimates |
Opex | From SAP reports |
Alternative | None considered |
Unit | 1 | 2 | 3 |
---|---|---|---|
Description | 2-bed semi | 3-bed semi | 2-bed amenity bungalow |
Count | 2 | 2 | 1 |
Footprint (m2) | 87.0 | 101 | 69 |
Heat demand | 1215 | 1044 | 1120 |
Heat demand per m2 | 14.0 | 10.3 | 16.2 |
Equipment capex | £10,457 | £10,457 | £10,457 |
Labour capex | |||
Network capex | Not considered | ||
Other heating capex | £3,680 | £3,680 | £3,680 |
Total capex | £14,137 | £14,137 | £14,137 |
Capex per m2 | £162 | £140 | £205 |
Est. opex | £199 | £171 | £183 |
Est. opex per m2 | £2.3 | £1.7 | £2.7 |
B3. Air Source Heat Pumps (shared)
Project 16
An overview of Project 16 is provided in Table 43. A per-unit table has not been provided because the project is at an early stage and has not been costed in detail yet.
Metric | Information |
---|---|
Location | Scottish Borders |
Unit count | 21 |
Unit types | Not yet established (P) |
Progress | Pre-construction |
On-gas grid | Yes |
Section 75 | No |
Sustainability target | Silver with Gold aspects |
Heating system | Shared ASHPs with heat interface units in each flat |
Capex extent | Not yet established (P) |
Capex source | Not yet established (P) |
Opex | Not yet established (P) |
Alternative | No alternative considered |
Project 17
An overview of Project 17 is provided in Table 44. A per-unit table has not been provided because the project is at an early stage and has not been costed in detail yet.
Metric | Information |
---|---|
Location | City of Edinburgh |
Unit count | 41 |
Unit types | Not yet established (P) |
Progress | Pre-construction |
On-gas grid | Yes |
Section 75 | No (although development will have non-social let flats) |
Sustainability target | 100% improvement versus Silver (considered to define 'Net Zero') |
Heating system | Shared ASHPs with heat interface units in each flat |
Capex extent | Not yet established (P) |
Capex source | Not yet established (P) |
Opex | Not yet established (P) |
Alternative | Alternatives considered but these will not be costed |
Project 13 (1-bed flats)
An overview of Project 13 is provided in Table 38, within the individual ASHP section, as the majority (87 of 117 units) incorporate individual systems. However, the development has 30 one-bed flats which are served by five separate communal ASHP systems, one per block.
Costs for these systems are presented in Table 45 below.
Unit | 1 |
---|---|
Description | 1-bed flats, 5 blocks of 6 |
Count | 30 |
Footprint (m2) | 48.6 |
Heat demand | 1532 |
Heat demand per m2 | 31.5 |
Installation capex | £8,857 |
Network capex | £682 |
Sunamp + PV capex | £4,017 |
Total capex | £13,556 |
Capex per m2 | £278.9 |
Est. opex | £150 |
Est. opex per m2 | £3.1 |
Alt capex | £11,015 |
Alt capex per m2 | £226.6 |
Est. alt opex | £251 |
Est. alt per m2 | £5.2 |
B4. Ground Source Heat Pumps (Shared)
Project 18
An overview of Project 18 is provided in Table 46, and per-unit data in Table 47. The capex for the GSHP system was provided as a single cost for the whole development.
Metric | Information |
---|---|
Location | West Lothian |
Unit count | 16 (plus one staff building) |
Unit types | 1 |
Progress | Pre-construction |
On-gas grid | Yes |
Section 75 | No |
Sustainability target | Silver |
Heating system | Shared GSHPs loop with individual heat pumps, underfloor heating |
Capex extent | Shared GSHPs loop and individual heat pump installation |
Capex source | Quantity Surveyor's estimates |
Opex | Estimated by Mechanical Consultants |
Alternative | Direct electric heaters (with solar PV to pass SAP) |
Unit | 1 |
---|---|
Description | 1-bed terrace |
Count | 16 |
Footprint (m2) | 47.7 |
Heat demand | 2,857 |
Heat demand per m2 | 60 |
Installation capex | £10,871 |
Network capex | Not considered |
Other heating capex | N/A |
Total capex | £10,871 |
Capex per m2 | £228 |
Est. opex | £400 |
Est. opex per m2 | £8.4 |
Alt capex | £4,659 (inclusive of solar PV) |
Alt capex per m2 | £97.7 |
Est. alt opex | £1,400 |
Est. alt per m2 | £29.4 |
Project 19
An overview of Project 19 is provided in Table 48, and per-unit data in Table 49.
Metric | Information |
---|---|
Location | City of Edinburgh |
Unit count | 84 |
Unit types | 5 |
Progress | Under construction |
On-gas grid | Yes |
Section 75 | Yes |
Sustainability target | Aspect Silver Levels 1 and 2 |
Heating system | Shared GSHPs loop with individual heat pumps, underfloor heating |
Capex extent | Shared GSHPs loop and individual heat pump installation |
Capex source | Actual costs |
Opex | Estimated by developer |
Alternative | Gas boilers |
Unit | 1 | 2 | 3 | 4 | 5 |
---|---|---|---|---|---|
Description | 2-bed terrace | 2-bed end | 3-bed terrace | 3-bed end | 4-bed semi |
Count | 16 | 16 | 34 | 10 | 8 |
Footprint (m2) | 82 | 82 | 97 | 97 | 125 |
Heat demand | 1674 (B) | 1674 (B) | 1980 | 1980 (B) | 2552 (B) |
Heat demand per m2 | 20.4 (B) | 20.4 (B) | 20.4 | 20.4 (B) | 20.4 (B) |
Equipment capex | £11,500 | £11,500 | £11,500 | £11,500 | £11,500 |
Labour capex | |||||
Network capex | Not considered | ||||
Other heating capex | N/A | ||||
Total capex | £11,500 | £11,500 | £11,500 | £11,500 | £11,500 |
Capex per m2 | £140 | £119 | £119 | £92 | £92 |
Est. opex | £88 (B) | £88 (B) | £104 | £104 (B) | £135 (B) |
Est. opex per m2 | 1.1 (B) | 1.1 (B) | 1.1 | 1.1 (B) | 1.1 (B) |
Alt capex | £4,000 | £4,000 | £4,000 | £4,000 | £4,000 |
Alt capex per m2 | 49 | 41 | 41 | 32 | 32 |
Est. alt opex | £118 (B) | £118 (B) | £139 | £139 (B) | £180 (B) |
Est. alt per m2 | 1.4 (B) | 1.4 (B) | 1.4 | 1.4 (B) | 1.4 (B) |
B5. Biomass (shared)
Project 20
An overview of Project 20 is provided in Table 50, and per-unit data in Table 51. Rather than a purpose-built biomass plant for the housing development, the heat source for this project is an industrial scale biomass combined heat and power plant. The capex for the system in this project was provided as a single cost for the whole development, so the figures presented below assign an equal portion of the total cost to each of the units.
Metric | Information |
---|---|
Location | Fife |
Unit count | 85 |
Unit types | 11 |
Progress | Under construction |
On-gas grid | Yes |
Section 75 | Yes |
Sustainability target | Silver |
Heating system | Shared biomass heating from Markinch biomass plant |
Capex extent | District heating network and heat interface units in each property |
Capex source | Actual costs |
Opex | Central estimates provided |
Alternative | Gas boilers – not costed |
Unit | 1 | 2 | 3 | 4 | 5 |
---|---|---|---|---|---|
Description | 2-bed terrace | 3-bed terrace (A) | 3-bed terrace (B) | 2-bed WC semi | 2-bed semi |
Count | 28 | 15 | 11 | 4 | 2 |
Footprint (m2) | 83.2 | 93 | 116.8 | 79.8 | 95.3 |
Heat demand | 5,410 (B) | 6,047 (B) | 7,594 (B) | 5,189 (B) | 6,196 (B) |
Heat demand per m2 | 65 (B) | 65 (B) | 65 (B) | 65 (B) | 65 (B) |
Installation capex | £8,837 | £8,837 | £8,837 | £8,837 | £8,837 |
Network capex | Inherent to above costs | ||||
Other heating capex | N/A | ||||
Total capex | £8,837 | £8,837 | £8,837 | £8,837 | £8,837 |
Capex per m2 | £106 | £95 | £76 | £111 | £93 |
Est. opex | £139 (B) | £155 (B) | £195 (B) | £133 (B) | £159 (B) |
Est. opex per m2 | £1.67 (B) | £1.67 (B) | £1.67 (B) | £1.67 (B) | £1.67 (B) |
Unit | 6 | 7 | 8 | 9 | 10 | 11 |
---|---|---|---|---|---|---|
Description | 4-bed det. | 4-bed WC semi | 4-bed semi | 5-bed detached | 2-bed cottage flat | 2-bed WC cottage flat |
Count | 2 | 4 | 2 | 5 | 6 | 6 |
Footprint (m2) | 112.8 | 98.1 | 122.2 | 120 | 83.8 | 79 |
Heat demand | 7,334 (B) | 6,378 | 7,945 (B) | 7,802 (B) | 5,449 (B) | 5,137 (B) |
Heat demand per m2 | 65 (B) | 65 | 65 (B) | 65 (B) | 65 (B) | 65 (B) |
Equipment capex | £8,837 | £8,837 | £8,837 | £8,837 | £8,837 | £8,837 |
Labour capex | ||||||
Network capex | Inherent to above costs | |||||
Other heating capex | N/A | |||||
Total capex | £8,837 | £8,837 | £8,837 | £8,837 | £8,837 | £8,837 |
Capex per m2 | £78 | £90 | £72 | £74 | £105 | £112 |
Est. opex | £188 (B) | £164 | £204 (B) | £200 (B) | £140 (B) | £132 (B) |
Est. opex per m2 | £1.67 (B) | £1.67 | £1.67 (B) | £1.67 (B) | £1.67 (B) | £1.67 (B) |
Project 21
An overview of Project 21 is provided in Table 53. A per-unit table has also been provided.
Metric | Information |
---|---|
Location | North Ayrshire |
Unit count | 123 |
Unit types | 15 |
Progress | Under construction |
On-gas grid | Yes |
Section 75 | No |
Sustainability target | Aspect Silver Levels 1 and 2 |
Heating system | Shared biomass heating |
Capex extent | DHN installation costs (inc. back-up system) |
Capex source | Actual costs (averaged from development total) |
Opex | Estimates Provided |
Alternative | Gas DHN |
Unit | 6 | 7 | 8 | 9 | 10 |
---|---|---|---|---|---|
Description | 2-bed bungalow (A) | 2-bed bungalow (B) | 2-bed WC bungalow | 2-bed house (A) | 2-bed house (B) |
Count | 5 | 7 | 4 | 13 | 13 |
Footprint (m2) | 63 | 63 | 63 | 88 | 84 |
Heat demand | 4,111 | 3,889 | 4,111 | 4,778 | 4,222 |
Heat demand per m2 | 65 | 62 | 65 | 54 | 50 |
Installation capex | £11,355 | £11,355 | £11,355 | £11,355 | £11,355 |
Network capex | Inherent to above costs | ||||
Other heating capex | N/A | ||||
Total capex | £11,355 | £11,355 | £11,355 | £11,355 | £11,355 |
Capex per m2 | £245 | £177 | £206 | £237 | £183 |
Est. opex | £110 | £150 | £160 | £145 | £175 |
Est. opex per m2 | £2.38 | £2.34 | £2.91 | £3.02 | £2.81 |
Alt capex | £3,015 | £3,015 | £3,015 | £3,015 | £3,015 |
Alt capex per m2 | 65.1 | 47.0 | 54.8 | 62.8 | 48.5 |
Est. alt opex | £110 | £150 | £160 | £145 | £175 |
Est. alt per m2 | £2.38 | £2.34 | £2.91 | £3.02 | £2.81 |
Unit | 6 | 7 | 8 | 9 | 10 |
---|---|---|---|---|---|
Description | 2-bed bungalow (A) | 2-bed bungalow (B) | 2-bed WC bungalow | 2-bed house (A) | 2-bed house (B) |
Count | 5 | 7 | 4 | 13 | 13 |
Footprint (m2) | 63 | 63 | 63 | 88 | 84 |
Heat demand | 4,111 | 3,889 | 4,111 | 4,778 | 4,222 |
Heat demand per m2 | 65 | 62 | 65 | 54 | 50 |
Installation capex | £11,355 | £11,355 | £11,355 | £11,355 | £11,355 |
Network capex | Inherent to above costs | ||||
Other heating capex | N/A | ||||
Total capex | £11,355 | £11,355 | £11,355 | £11,355 | £11,355 |
Capex per m2 | £245 | £177 | £206 | £237 | £183 |
Est. opex | £110 | £150 | £160 | £145 | £175 |
Est. opex per m2 | £2.38 | £2.34 | £2.91 | £3.02 | £2.81 |
Alt capex | £3,015 | £3,015 | £3,015 | £3,015 | £3,015 |
Alt capex per m2 | 47.9 | 47.9 | 47.9 | 34.1 | 35.7 |
Est. alt opex | £185 | £175 | £185 | £215 | £190 |
Est. alt per m2 | £2.94 | £2.78 | £2.94 | £2.43 | £2.25 |
Unit | 11 | 12 | 13 | 14 | 15 |
---|---|---|---|---|---|
Description | 3-bed house | 3-bed WC house | 4-bed house (A) | 4-bed house (B) | 4-bed bungalow |
Count | 20 | 1 | 3 | 1 | 2 |
Footprint (m2) | 96 | 119 | 108 | 112 | 130 |
Heat demand | 4,667 | 5,778 | 5,556 | 5,778 | 6,444 |
Heat demand per m2 | 49 | 49 | 51 | 52 | 50 |
Installation capex | £11,355 | £11,355 | £11,355 | £11,355 | £11,355 |
Network capex | Inherent to above costs | ||||
Other heating capex | N/A | ||||
Total capex | £11,355 | £11,355 | £11,355 | £11,355 | £11,355 |
Capex per m2 | £135 | £119 | £96 | £105 | £101 |
Est. opex | £190 | £210 | £260 | £250 | £260 |
Est. opex per m2 | £2.25 | £2.20 | £2.19 | £2.31 | £2.32 |
Alt capex | £3,015 | £3,015 | £3,015 | £3,015 | £3,015 |
Alt capex per m2 | 31.5 | 25.4 | 27.9 | 26.9 | 23.2 |
Est. alt opex | £210 | £260 | £250 | £260 | £290 |
Est. alt per m2 | £2.20 | £2.19 | £2.31 | £2.32 | £2.23 |
Contact
Email: 2024heatstandard@gov.scot
There is a problem
Thanks for your feedback