Feasibility Report of a Deep Geothermal Single Well, Aberdeen Exhibition and Conference Centre
Report of study which examined the technical, logistical, contractual and economic feasibility of installing a deep geothermal single well system at the new site of the Aberdeen Exhibition and Conference Centre.
Project Costs
From experience of previous projects, we have developed good estimates of the costs required for each of the stages listed above.
These are summarised below and listed in detail against the proposed programme in the following sections.
Table 9: Summary of milestones and associated costs for the project
Date | Costs | |||
---|---|---|---|---|
Work Package | 1 | Agreements, Contracts and Permitting | Month 7 | £147,440 |
Work Package | 2 | Completion of well/ System | Month 14 | £1,713,150 |
Work Package | 3 | System testing | Month 21 | £153,050 |
Work Package | 4 | Integration | Month 27 | £279,000 |
Work Package | 5 | System operation report | Costs met internally | |
Total cost of project | £2,292,640 |
Operational Costs - Staffing
TOTAL | ||||||||
---|---|---|---|---|---|---|---|---|
Engineer | £4,480 | £4,480 | £5,040 | £5,040 | £5,040 | £4,480 | £4,480 | £33,040 |
Senior Engineer | £6,000 | £6,000 | £6,000 | £3,000 | £1,000 | £22,000 | ||
Director | £4,500 | £4,500 | £6,750 | £9,000 | £4,500 | £4,500 | £4,500 | £38,250 |
Sub Consultants | £6,650 | £13,300 | £14,250 | £11,400 | £8,550 | £54,150 | ||
Total | £8,980 | £21,630 | £31,090 | £34,290 | £23,940 | £18,530 | £8,980 | £147,440 |
TOTAL | ||||||||
---|---|---|---|---|---|---|---|---|
Engineer | £4,480 | £5,600 | £5,600 | £5,600 | £2,240 | £2,240 | £2,240 | £28,000 |
Senior Engineer | £6,000 | £8,000 | £10,000 | £10,000 | £10,000 | £10,000 | £54,000 | |
Director | £4,500 | £4,500 | £6,750 | £9,000 | £9,000 | £9,000 | £4,500 | £47,250 |
Sub Consultants | £5,700 | £3,800 | £28,500 | £28,500 | £28,500 | £28,500 | £123,500 | |
Total | £8,980 | £21,630 | £28,280 | £29,230 | £23,380 | £18,530 | £8,980 | £252,750 |
TOTAL | ||||||||
---|---|---|---|---|---|---|---|---|
Engineer | £5,040 | £5,600 | £5,600 | £5,600 | £5,600 | £5,600 | £3,360 | £36,400 |
Senior Engineer | £7,000 | £6,000 | £8,000 | £10,000 | £10,000 | £10,000 | £2,000 | £53,000 |
Director | £2,250 | £2,250 | £6,750 | £9,000 | £9,000 | £9,000 | £4,500 | £42,750 |
Sub Consultants | £1,900 | £1,900 | £2,850 | £2,850 | £3,800 | £3,800 | £3,800 | £20,900 |
Total | £8,980 | £21,630 | £28,280 | £29,230 | £23,380 | £18,530 | £8,980 | £153,050 |
TOTAL | |||||||
---|---|---|---|---|---|---|---|
Engineer | £5,040 | £5,600 | £5,600 | £5,600 | £5,600 | £3,360 | £30,800 |
Senior Engineer | £5,000 | £6,000 | £8,000 | £10,000 | £10,000 | £4,000 | £43,000 |
Director | £2,250 | £2,250 | £2,250 | £4,500 | £4,500 | £3,000 | £18,750 |
Sub Consultants | £3,800 | £1,900 | £2,850 | £3,800 | £3,800 | £1,900 | £18,050 |
Total | £8,980 | £21,630 | £28,280 | £29,230 | £23,380 | £18,530 | £110,600 |
Capital Equipment and Travel
Equipment | |||
---|---|---|---|
Item | No.of items | Price per item (ex VAT) | Total |
Polypropylene Pipe | 1950 | £30 | £58,500 |
Pump | 1 | £10,000 | £10,000 |
Riser | 300 | £20 | £6,000 |
Thermistor string | 1950 | £4 | £7,800 |
Surface pipework | Numerous | £1,000 | £1,000 |
Steel weights | Numerous | £1,800 | £1,800 |
Cable ties and sundries | Numerous | £4,500 | £4,500 |
Connection pipework | Numerous | £800 | £800 |
Bleed valve and isolation valves | 4 | £450 | £1,800 |
Temp and flow sensors/ meters | Numerous | £2,200 | £2,200 |
Pump control system | 1 | £3,800 | £3,800 |
Bleed valve control system | 1 | £2,400 | £2,400 |
Insulation | Numerous | £400 | £400 |
Fittings | Numerous | £900 | £900 |
Heat exchanger | 1 | £6,000 | £6,000 |
Filtration unit | 1 | £2,500 | £2,500 |
Equipment total | £110,400 | ||
Drilling | |||
Detail | No. | Cost per item | Total |
Drilling and completion of well* | 1 | £1,350,000 | £1,350,000 |
Other total | £1,350,000 | ||
Integration | |||
Detail | No. | Cost per item | Total |
Equipment | 1 | £155,000 | £155,000 |
Other total | £155,000 | ||
Total Capex | £1,615,400 | ||
* See detailed cost breakdown | |||
Travel | |||
Journey required and reason | No. of Journeys | Cost per Journey | Total |
Site visits for negotiation | 4 | £200 | £800 |
Site visits for M&E analysis | 4 | £200 | £800 |
Site supervision during installation* | 3 | £3,000 | £9,000 |
Site visits during testing* | 2 | £1,400 | £2,800 |
Equipment total | £13,400 | ||
*Multiple nights at location @ £100 per night |
Detailed Drilling Costs
The total cost of drilling and casing the well at the AECC site is shown in Table 10. The costs for the drilling are based on a recent tender process for a similar project in England.
Table 10: Detailed expected drilling costs
Resource Management
Geothermal Engineering Ltd (GEL) will be responsible for running and managing the project but will work closely with Arup and the University of St. Andrews on project delivery. The company has extensive experience of geothermal projects (heat and power) in the UK and abroad. The company has recently installed and tested the DGSW technology in an existing deep well as part of the DECC funded Energy Entrepreneurs Fund and delivered the project on time and on budget. The team for this project will consist of the following staff members:
Entity | Name | Role |
---|---|---|
GEL | Ryan Law | Chief geologist and project director |
David Bridgland | Chief engineer and financial controller | |
Peter Ledingham | On site operations and Health and Safety | |
Adrian Jackson | On site management and installation of equipment | |
Arup | Mike Collins | Well design, project management and client liaison |
David Brown | Planning and permitting | |
Barry Austin | M&E building integration | |
Stephen Cook | Heat network contracts | |
Eversheds LLP | Stephen Hill | Legal |
GEL has worked with all of these parties on a number of previous parties and already has a strong working relationship in place.
Contact
Email: Johann MacDougall
There is a problem
Thanks for your feedback