Flood prevention schemes: guidance for local authorities

Guidance on making flood prevention schemes for local authorities.


ANNEX C: OPTIMISM BIAS DATA FOR FLOOD PREVENTION COSTS

The following data and other details have been abstracted from the note issued by Defra to operating authorities in March 2003 (reference 11).

Starting (upper bound) Optimism Bias factor for
Starting (upper bound) Optimism Bias factor for

Strategy costs (pre-feasibility stage):
Scheme costs (detailed design stage):

60%
30%

The risk components contributing to the above factors are detailed in the following table.

Risk components contributing to above factors (%, summing to 100 - see next page for definitions)

Average % for flood defence projects

Procurement

Late contractor involvement in design

1

Dispute and claims occurred

11

Other

1

Project specific

Design complexity

4

Degree of innovation

4

Environmental impact

13

Other

9

Client specific

Inadequacy of the Business Case

23

Funding availability

2

Project management team

1

Poor project intelligence

8

Environment

Public relations

5

Site characteristics

4

External influences

Economic

5

Legislation/regulations

4

Technology

4

Other

1

The risk components (except for those described "Other") may be reduced for individual strategies or schemes if demonstrable action to minimise risks has been taken, or other evidence is provided that risks are not applicable to the degree indicated. In which case, the revised sum of risk components should be divided by 100 and multiplied by either 60 or 30 to obtain the new Optimism Bias factor.

Example of Optimism Bias approach: After an assessment of risk components, the "environmental impact" component for a strategy plan is halved (ie reduced by 6.5). The new optimism bias factor equals:

(100-6.5)/100 x 60 = 56

So the best estimate of Present Value strategy costs is increased by 56%, with this adjustment applying to operating and maintenance expenditure as well as capital expenditure.

Definitions of risk components

Procurement

Late contractor involvement in design

Late involvement of the contractor in the design leads to redesign or problems during construction.

Dispute and claims occurred

Disputes and claims occur where no mechanisms exist to manage effectively adversarial relationships between project stakeholders.

Other

Other factors that relate to procurement which affect the final project cost.

Project specific

Design complexity

The complexity of design (including requirements, specifications and detailed design) requires significant management, impacting on final project costs.

Degree of innovation

The degree of innovation required due to the nature of the project requires unproven methods to be used.

Environmental impact

The project has a major impact on its adjacent area leading to objection from neighbours and the general public.

Other

Other project specific factors which affect the final project cost.

Client specific

Inadequacy of Business Case

The project scope changes as a result of the poor quality of requirement specifications and inadequate project scope definition.

Funding availability

Project delays or changes in scope occur as a result of the availability of funding.

Project management team

The project management team's capabilities and/or experience impact on final project costs.

Poor project intelligence

The quality of initial project intelligence (eg preliminary site investigation, user requirements surveys etc) impacts on the occurrence of unforeseen problems and costs.

Environment

Public relations

A high level of effort is required to address public concern about the project, which impacts on the final project cost.

Site characteristics

The characteristics of the proposed environment for the project are highly sensitive to the project's environmental impacts (eg greenfield site with badger setts, or contaminated brownfield site).

External influences

Economic

The project costs are sensitive to economic influences such as higher-than-expected construction cost inflation, oil price shocks etc.

Legislation/regulations

The project costs are sensitive to legislation and regulation changes, eg health and safety and building regulations.

Technology

The project costs are sensitive to technological advancements, eg the effects of obsolescence.

Other

Other external influencing factors which affect the final project cost.

Contact

Email: Central Enquiries Unit ceu@gov.scot

Back to top