Scottish Education Management Information System (SEEMiS) Early Years System: FOI release

Information request and response under the Freedom of Information (Scotland) Act 2002


Information requested

You asked what the expected roll out date is for the SEEMiS Early Years System and why has it been delayed?

1. What is expected roll out date for the SEEMiS Early Years System?

2. Why has it been delayed?

Response

The answer to your question isÍž

1. What is expected roll out date for the SEEMiS Early Years System?

The SEEMiS Early Years System development is currently due to complete between January and March 2024. The roll out or go live date is yet to be agreed with the 32 local authorities.

2. Why has it been delayed?

Development completion has been delayed due to unforeseen contractual issues.

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact

Please quote the FOI reference
Central Enquiry Unit
Email: ceu@gov.scot
Phone: 0300 244 4000

The Scottish Government