A list of the schools that were put forward for Phase 3 of the Learning Estate Investment Programme (LEIP), including the relevant local authority name and the date of application.

Response

I enclose the information you requested - within the below table.

Consideration of Phase 3 bids has been delayed due to a number of factors, which could not have been anticipated when the original invitation to bid was issued.

For example, there has been significant market volatility affecting a number of current Phase 1 and 2 projects which required further analysis and consideration, including the impact of this on Phase 3.

As a result of this market volatility, adjustment to 20 Phase 1 and 2 projects was agreed and communicated to local authorities over the summer. The impact of reinforced autoclaved aerated concrete on a small number of Scottish schools is also an issue which we are taking into consideration.

This has meant that this important decision, which will impose a very significant cost to the public purse for the next 30 years, has been subject to delay to ensure that all relevant factors are fully considered.

However, the Cabinet Secretary for Education and Skills has committed to updating Parliament on Phase 3 by the end of October 2023.

Table
Please see the following list of the schools that were put forward for Phase 3 of the LEIP, including the relevant local authority name and the date of application:

Local Authority

Date of submission

Project(s)

Aberdeen City

31/10/2022

  • St Peter’s Primary School
  • Hazlehead Academy

Aberdeenshire

21/10/2022

  • Single replacement for Fraserburgh North and St Andrew’s Primary Schools
  • Dunnotar Primary School and Carronhill School

Argyll & Bute

28/10/2022

  • Mull Campus

Clackmannanshire

31/10/2022

  • Lochies School

Dumfries & Galloway

28/10/2022

  • Dumfries Academy and Loreburn Primary School

Dundee City

31/10/2022

  • Western Gateway Primary School

East Ayrshire

28/10/2022

  • North West Kilmarnock Campus

East Dunbartonshire

31/10/2022

  • Balmuildy Primary School
  • Lenzie Academy

East Lothian

31/10/2022

  • East Linton Primary School

East Renfrewshire

28/10/2022

  • Carolside Primary School
  • Cross Arthurlie Primary School

Edinburgh

28/10/2022

  • St Catherine’s Primary School

Falkirk

28/10/2022

  • Carrongrange School extension

Fife

31/10/2022

  • Auchmuty High School extension
  • Single replacement for Glenwood and Glenrothes High Schools

Highland

31/10/2022

  • Beauly, Dunvegan, and Park Primary Schools
  • St Clement’s School
  • Tornagrain Primary School

Midlothian

31/10/2022

  • Rosewell Primary School Campus
  • King’s Park Primary School

Moray

28/10/2022

  • Buckie High School
  • Forres Academy

North Lanarkshire

28/10/2022

  • Chryston High School extension
  • Gartcosh Primary School

Orkney Islands

28/10/2022

  • ASN Centre

Perth & Kinross

31/10/2022

  • Primary School in Bertha Park

Renfrewshire

31/10/2022

  • Thorn Primary School

Scottish Borders

31/10/2022

  • Hawick High School

Shetland Islands

28/10/2022

  • Brae Campus

South Ayrshire

31/10/2022

  • Girvan Primary School

South Lanarkshire

28/10/2022

  • Holy Cross High School extension, and St Andrew’s & St Bride’s High School extension
  • Kear School
Stirling 28/10/2022
  • Primary School in South Stirling Gateway
West Lothian 31/10/2022
  • Single replacement for Riverside and Letham Primary Schools

 

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact

Please quote the FOI reference
Central Enquiry Unit
Email: ceu@gov.scot
Phone: 0300 244 4000

The Scottish Government
St Andrews House
Regent Road
Edinburgh
EH1 3DG

Back to top