Numbers of homes approved and completed under National Acquisition Programme: FOI release

Information request and response under the Freedom of Information (Scotland) Act 2002.


Information requested

Information on the numbers of homes approved and completed in 2023-24 under the government’s national acquisition programme. The information requested is further detail for each local authority area in Scotland to the information supplied in response to Scottish Parliamentary Questions S6W-26978, and S6W-27110 by Mark Griffin.

The detail requested, separately for each local authority area in Scotland in 2023-24 is in the table below. The aim is to understand, for each local authority area:

  • The balance between acquisitions for social let and affordable let. Comparing data in S6W-26978 and recently published AHSP statistics points to affordable let being around 6% of NAP approvals and completions, but this is likely to vary significantly between local authority areas.
  • Balance between new build off the shelf purchases and second-hand acquisitions by local authority area distinguishing between houses acquired by local authority landlords from those acquired by RSLs.

Response

Please find attached a table with the requested breakdown of the 2023-2024 National Acquisition Programme (NAP) approvals and completions broken down by local authority area, in the format provided in your request.

The following tables summarise the findings, in respect of the points made in your request. 

National Acquisition Programme (NAP)

Total Number of Homes

Total Social Let Homes

% of all Homes

Total Affordable Let Homes

% of all Homes

Approvals

1,620

1,530

94%

90

6%

Completions

1,498

1,413

94%

85

6%

National Acquisition Programme (NAP)

Total Number of Homes

Total Second Hand Purchases Social Let Homes

Total New Build Off the Shelf Purchases from Developers Social Let Homes

Total Second Hand Purchases Affordable Let Homes

Total New Build Off the Shelf Purchases from Developers Affordable Let Homes

Approvals

1,620

1,373

42

157

48

Completions

1,498

1,327

37

86

48

Please note that in the response to the parliamentary question S6W-27110 dated 13 May 2024, the answer notes a total of 1,622 homes approved through the NAP. That figure was based on the information available to us at the time of responding, and has since changed, as noted in the tables above and attached, to 1,620 homes approved.

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

foi-202400424101 - information released

Contact

Please quote the FOI reference
Central Enquiry Unit
Email: ceu@gov.scot
Phone: 0300 244 4000

The Scottish Government
St Andrews House
Regent Road
Edinburgh
EH1 3DG

Back to top