Building standard 3.3 - flooding and groundwater guidance review: research
Research to inform the review of guidance which supports Standard 3.3, including identifying current good practice on flooding and groundwater and suggesting improvements and adoption of a good practice guide for local authorities.
4. Suggested good practice template
A good practice approach
4.1 From the above, the planning system tries to address flooding issues from the outset, but there still could be a role for building standards officers in checking mitigation measure compliance (such as finished floor level and Property Flood Resilience, PFR) and identifying flood risk if not considered at planning stage or if the development is of a type not considered in the planning process (e.g. permitted development).
4.2 Table 4-1 provides a suggested checklist for good practice on verifying building standards compliance on flooding and groundwater which could be used by Building Standards Surveyors (verifiers) as part of the building warrant assessment process and as part of reasonable inquiry checks on site. It suggests checking on flood risk and communicating with the Local Authority flood officer, as appropriate, early on in the building warrant process. The checklist could also be reviewed to place any action already undertaken as part of a planning consent into account.
4.3 With respect to Property Flood Resilience (PFR), the CIRIA C790 Code of Practice is recommended including Post Installation Audit of PFR measures. The alignment of CIRIA C790 with building standards processes is summarised in Table 4-2.
4.4 As noted in the preceding section, PFR training may be beneficial to Building Standards Surveyors for checking compliance. Alternatively, the PFR compliance check could be outsourced to appropriately qualified specialists.
4.5 An earlier draft of the suggested good practice template was circulated for comment to the eight Local Authorities who had submitted survey responses (Appendix F). Responses from six of those LAs were obtained (Appendix G) and the feedback used in the approach suggested here. An additional response was also received via LABSS and is included in Appendix G.
Stage |
Item |
Answer |
---|---|---|
Building warrant |
Is flooding and groundwater an issue at this site? (e.g. local knowledge and/or SEPA Flood Map check) |
|
Building warrant |
Has this issue been addressed during the planning application process? If not, consultation with the flood officer is recommended. |
|
Building warrant |
Are all relevant documents available? E.g.:
And been accepted by the relevant officer (e.g. flood officer; structural engineer)? |
|
Building warrant |
If flood mitigation measures have been used do they meet the BSI standards: BS 8000-0:2014, BS 8533:2017 and BS 85500:2015? |
|
Inspection |
Does the location of the development and finished floor level comply with the approved plans? |
|
Inspection |
If Property Flood Resilience (PFR) has been used is there evidence of it following the Code of Practice as defined in CIRIA C790? (See accompanying table) |
|
Submission of Completion Certificate by relevant person |
Is evidence of the following available? All flood risk:
For PFR; required information:
For PFR; optional information:
|
CIRIA C790 Standard |
Building Standards process |
Relevant Reference |
---|---|---|
Stage 1 Hazard Assessment |
Building Warrant: Flooding type(s), depth, speed, duration and frequency. Property survey (existing) and design review (new build); specified materials/building elements, and proposed PFR solution. |
C790B: Chapter 12 |
Stage 2 Property Survey (existing buildings) |
C790B: Chapter 13 Draft BS85500 Clause 4.4 |
|
Stage 3 Options development and design |
C790B: Chapters 14, 23, 25 |
|
Stage 4 Construction |
Completion Certificate: On-site checks/inspections to verify specified PFR solutions have been achieved (CCNP*). Evidence of in-situ and wet testing. Receive post installation audit (PiA). Receive Homeowner Flood Plan (or O&M manuals). |
C790B: Chapter 15 |
Stage 5 Commissioning and handover |
C790B: Chapter 16 |
|
Stage 6 Operation and maintenance |
C790B: Chapters 17 & 24 |
*Construction Compliance and Notification Plan (CCNP)
Contact
Email: buildingstandards@gov.scot
There is a problem
Thanks for your feedback