Solvent Emissions (Scotland) Regulations 2004: guidance

Guidance on the Solvent Emissions (Scotland) Regulations 2004.


Guidance on the Solvent Emissions (Scotland) Regulations 2004

6. APPLICATION TIMETABLES AND ARRANGEMENTS

6.1 When Should Applications be Made?

Operators of currently regulated SED Installations (i.e. SEDIs already regulated in full or in part under an EPA authorisation or a PPC permit) must apply to SEPA for a variation to include the requirements of the SER 2004, as relevant to their operations, unless SEPA has already included SED requirements (eg as a result of reviewing the authorisation / permit).

Operators of currently unregulated SEDIs must apply for a PPC permit (e.g. dry cleaners).

The SER 2004 does not state specific 'application timescales' for each SER activity. Instead, the date by which the operator is required to apply is determined by a number of factors, including whether the SEDI is 'new' or 'existing'; the nature of the operations undertaken; the type of VOCs used; and how the operator intends to comply with the SER 2004. These factors and the application timescales are detailed further in the following sections.

6.2 Application Timescales for 'New' SED Installations

The date the operator of a 'new' SEDI has to apply is determined by two factors, namely;

whether the SEDI is already regulated (either fully or partly under PPC or EPA); and

when the SEDI was put into operation (i.e. between 1 April 2001 and 28 January 2004, or after 28 January 2004).

In addition SEPA is required, where appropriate, to conduct variations to installations issued with an EPA 90 authorisation between 1 April 2001 and 28 January 2004 to include SED compliant conditions by 28 May 2004.

Figure 2 details the application windows for scenarios where there are 'new' SEDIs.

Figure 2: Application Timescales for 'New' SEDIs

diagram

6.3 Application Timescales for 'Existing' SED Installations

The date the operator of an 'existing' unregulated SEDI has to apply for a PPC Part B permit is determined by the 3 factors listed in Table 3 below.

Table 3: Application Timetables for Existing SEDIs

Scenario

Application Timescale

The operations involve the use of any substances/preparations with the risk phrases R40, R45, R46, R49, R60 and R61 (but excluding the use of R40 substances/preparations in dry cleaning operations).

No later than 28 May 2004

Compliance with the SER 2004 will be achieved via a reduction scheme.

No later than 31 October 2005

All other operations

No later than October 2006

Table 4: Risk Phrases and Definitions

Risk Phrase *

Definition

R40

Possible Risk of Irreversible Effects

R45

May Cause Cancer

R46

May Cause Heritable Genetic Damage

R49

May Cause Cancer by Inhalation

R60

May Impair Fertility

R61

May Cause Harm to the Unborn Child

1. * Taken from the Chemicals (Hazard Information and Packaging for Supply) Regulations 2002 ("CHIP 3")

Figure 3 below details the application windows for the various scenarios for 'existing' SEDIs.

Figure 3: Application Timescales for 'Existing' SEDIs

diagram

6.4 Further Application Rules for Existing Installations

There are a number of additional factors which require to be taken into account when determining the date by which an existing installation must make an application to SEPA. These factors are as follows :

  • Whether VOC abatement equipment has been installed, and when

  • If a substance allocated a risk phrase is to be used in future

  • A substance is re-allocated a specific risk phrase

  • Whether the operation is to undergo a substantial change

These scenarios are explained further in table 5 below

Table 5: Additional Factors Affecting Application Deadline

Scenario

Current Status of Installation

Application Timeframe

Operator has installed VOC Abatement equipment between 1 April 2001 and 28 Jan 2004

Regulated (1)

Application to vary permit/authorisation made by 28/05/2004

Unregulated

Apply for a new permit by 28/05/ 2004

Operator to install new VOC abatement equipment after 28 Jan 2004

Regulated

Application to vary authorisation/ permit must be made before equipment is installed. (2)

Unregulated

Application for new permit made and granted before the equipment is operated.

A substance or preparation in use becomes reassigned to take a relevant risk phrase (3)

Regulated

Application for variation to be made within 4 months from the date of reassignment

Unregulated

Application for a permit to be made within 4 months of the date of reassignment

An operator wishes to start using a substance or preparation assigned with a relevant risk phrase (3)

Regulated

Application for variation to be made and granted before the substance can be used

Unregulated

Application for a permit to be made and granted before the substance can be used.

Scenario

Current Status of Installation

Application Timeframe

Operator proposes to undergo a substantial change to the activity (4)

Regulated

Application for a substantial change variation made and granted before any change is implemented.

Unregulated

Where deemed "new" then application for permit made and granted before change may be implemented

Where deemed "existing" then application for permit made in accordance with the timetable set out in Figure 3 above.

(1) Operators who currently hold a Part A authorisation may apply for a permit for the whole PPC installation rather than the part affected only by SED and may therefore bring forward the timeframe for full transfer of the installation to PPC.

(2) In this scenario the equipment cannot be INSTALLED until the variation to the permit or authorisation has been granted. This is different to the current regimes of PPC and EPA where equipment could be installed but not operated.

(3) This scenario affects any substance which is re-assigned any of the following risk phrases: R40, R45, R46, R49, R60, R61

(4) Operators proposing to use such substances or preparations for the first time will be expected to provide a strong justification against the criteria in Article 7(1) of the SED for why less harmful alternatives cannot be used.

6.5 Expected Dates of Transfer

In recognition of the factors described above it is anticipated that ,with regard to existing installations, the 10 currently unregulated SED sectors (i.e. those sectors not previously regulated under EPA 1990 or PPC 2000) are likely to come into regulation in the timeframes described in Table 6 below :

Table 6: Likely Application Dates for Existing Unregulated SEDIs

Industrial Sector

Likely Application Date

1

Surface cleaning using > 1 tonnes of solvent/yr, with the risk phrases R40, R45, R46, R49, R60 or R61

by 28/05/2004

2

Formulation and/or finishing of pharmaceutical products using > 50 tonnes of solvent/yr

by 28/05/2004

3

Rubber conversion not using carbon black using > 15 tonnes of solvent/yr

by 28/05/2004

4

Vehicle refinishing using 0.5 - 1 tonnes solvent/yr

by 31/10/2005

5

Vehicle coating using 0.5 - 5 tonnes solvent/yr

by 31/10/2005

Industrial Sector

Likely Application Date

6

Coating other than in the course of manufacturing using > 5 tonnes of solvent/yr

by 31/10/2005

7

Dry Cleaning (no threshold)

by 31/10/2006

8

Surface cleaning using > 2 tonnes of solvents/yr, other than those with the specified risk phrases

by 31/10/2006

9

Manufacturing less than 1000m3 of wood products using > 25 tonnes of solvent/yr

by 31/10/2006

10

Animal and vegetable oil extraction and purification using > 10 tonnes solvent/yr

by 31/10/2006

6.6 SEPA Variations

Operators are not required to apply for a variation to their authorisation/permit in any of the above circumstances where SEPA has already varied the authorisation/permit to include all necessary SED conditions.

Where the operator does not make an application for variation in respect of a 'partly regulated SEDI' then they must make an application for a permit for the whole SEDI.

Contact

Email: Central Enquiries Unit ceu@gov.scot

Back to top