Housing Infrastructure Fund: round 1 loan and grant payments
- Published
- 5 October 2021
- Topic
- Housing
Details of loan and grant projects approved under the first round of the Housing Infrastructure Fund.
HIF Grant |
||
Applicant |
Project/Works |
Funding Approved (£m) |
Argyll and Bute Council |
Dunbeg, Lorn/Kirk Road infrastructure works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
2.129 |
Glasgow City Council |
Maryhill Locks Land remediation/grouting works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
0.623 |
Highland Council |
Evergreen Fund Funding allocated to Council to operate HIF grant and loan schemes in the Highland Council area on the same basis as the main HIF fund. |
19.000 |
Moray Council |
Bilbohall - Expert Advice* Expert Advice funding to assisting Masterplanning for site. |
0.020 |
CEC |
Granton Waterfront Road infrastructure works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
0.100 |
Falkirk Council |
M80 J7/ A803 Motorway junction/road infrastructure works outwith curtilage of development site to open up access and support delivery of affordable and private homes on adjacent sites. |
2.544 |
Stirling Council |
Raploch, Stirling Land remediation/road improvements infrastructure works outwith curtilage of development site to open up access and support delivery of affordable homes on various sites. |
1.660 |
East Lothian Council |
Blindwells 1 - Expert Advice* Expert Advice funding to assisting Masterplanning for site. |
0.131 |
CEC |
Edinburgh Fountainbridge Decontamination/Roads/Services infrastructure works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
1.100 |
Dumfries and Galloway Council |
Gretna Major water capacity upgrade works outwith curtilage to open up access and support delivery of affordable and private homes in Gretna. |
2.500 |
East Lothian Council |
Blindwells 2 - Expert Advice* Expert Advice funding to assisting transport strategy for site. |
0.075 |
Link HA |
Ravenscraig Phase 1 Road infrastructure works linked to railway bridge works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
1.359 |
Link HA |
Ravenscraig Phase 2 Road infrastructure works to railway bridge linked to road junction works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
0.395 |
Link HA |
St Ninians Paisley Road infrastructure works outwith curtilage of development site to open up access and support delivery of affordable homes on site. |
0.426 |
Queens Cross HA |
Hamiltonhill, Glasgow Canal drainage infrastructure works outwith curtilage of development site to open up access and support delivery of affordable and private homes on site. |
2.488 |
Stirling Council | Balmaha Access road, drainage and site treatment works outwith curtilage to support delivery of affordable housing on site. |
0.345 |
HIF Loan | ||
Grandhome Trust | Grandhome Roads/drainage/services infrastructure works to open up access for affordable and private homes on site. |
7.900 |
Kingdom Park Ltd | Kingdom Park Roads/drainage/services infrastructure works to open up access for affordable and private homes on site. |
5.999 |
Total |
|
£48.794m |