Independent Assurance: Programme: Cladding Remediation Project Assessment Review (PAR)
Independent Assurance Review carried out for the Cladding Remediation Programme - 14 to 16 June 2023.
3. Blockers to delivery
Ref No: 1
Blocker: Legal powers not sufficient to enable Critical Incident Management with urgency required.
Describe specific nature of blocker: Will require legislation.
Consequence if not resolved: Inability to respond quickly and obtain a satisfactory resolution and create a threat to life.