Infrastructure Investment Plan 2021-22 to 2025-26: major capital projects progress update - September 2021
The following information relates to projects with a capital value of £5 million or more which are at the outline business case (or equivalent) approved stage or beyond.
Rural and Environment
Project - RBGE - Edinburgh Biomes
Business Case Approved Stages:
Project will transform the current failing estate – home to Scotland’s national biodiversity research collections, to a create a world-class facility that will produce climate, economic, wellbeing and environmental benefits, as part of a green economic recovery for Scotland.
The FBC outlines that the total cost of the project will be £89.9 million and the full programme will be completed by October 2027 with the public entrance Glasshouse the final planned phase of work.
(Scottish Government funding amounts to £58 million 2021-2026).
(Framework agreement is procurement route for project)
Contact For Public Enquiries:
Karen Thomas
Progress at March 2021
N/A
Progress at September 2021
Advance works commenced on site in September 2021 with the main works estimated to start January 2022.