Water Industry - Scottish Government Investment Group - Development List performance progress report: quarter one 2023-2024

Report to ensure the water industry is developing a sufficient programme of investment to meet the objectives that Ministers set at the start and to address the needs on the ‘Development List’ up to the end of September 2023 (quarter 1 2023 to 2024).


5. Summary

The IPPDG members are asked to:

  • Note the developing maturity of the current Investment forecast.
  • Note that the Q1 Progress to Committed List (PCL) was 112.3%, indicating that the rate of overall progress is more than sufficient to achieve planned investment levels.
  • Note the progress and learning on project investment appraisals.

Contact

Email: waterindustry@gov.scot

Back to top