Publication - Progress report
Investment Planning and Prioritisation Group (IPPG) report: quarter 1 2022 to 2023
Progress of interventions to meet the needs on the development list – report Quarter 1 2022-23
Appendix 2
2021-22 | 2022-23 | 2023-24 | 2024-25 | 2025-26 | 2026-27 | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
6 Year Investment £m | Previous (Q4) | Current (Q1) | Variance | Previous (Q4) | Current (Q1) | Variance | Previous (Q4) | Current (Q1) | Variance | Previous (Q4) | Current (Q1) | Variance | Previous (Q4) | Current (Q1) | Variance | Previous (Q4) | Current (Q1) | Variance |
Deliver Live | 755.2 | 763.7 | 8.5 | 560.3 | 678.8 | 118.5 | 310.6 | 390.6 | 80.0 | 111.3 | 113.1 | 1.8 | 52.0 | 55.6 | 3.6 | 42.5 | 35.9 | -6.6 |
Prepare Live | 33.9 | 27.1 | -6.8 | 152.8 | 124.1 | -28.7 | 205.9 | 204.8 | -1.0 | 120.4 | 119.0 | -1.4 | 67.4 | 89.1 | 21.7 | 26.2 | 29.1 | 2.8 |
Plan Live | 9.8 | 8.1 | -1.7 | 106.7 | 83.7 | -23.0 | 200.3 | 250.0 | 49.7 | 288.3 | 267.4 | -20.9 | 445.3 | 447.3 | 2.1 | 301.8 | 311.5 | 9.7 |
Not Live | 0.0 | 0.0 | 0.0 | 129.9 | 60.0 | -69.9 | 321.1 | 277.0 | -44.2 | 509.0 | 452.8 | -56.3 | 577.1 | 521.3 | -55.7 | 605.1 | 539.0 | -66.2 |
Completion Risk | 0.0 | 0.0 | 0.0 | 10.4 | 10.1 | -0.3 | 10.4 | 10.0 | -0.4 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
Total | 799.0 | 799.0 | 0.0 | 960.1 | 956.8 | -3.4 | 1,048.3 | 1,132.4 | 84.1 | 1,029.0 | 952.3 | -76.7 | 1,141.8 | 1,113.4 | -28.4 | 975.6 | 915.5 | -60.2 |
Planned Investment Level | 799.0 | 799.0 | 0.0 | 858.0 | 858.0 | 0.0 | 898.0 | 898.0 | 0.0 | 942.2 | 942.2 | 0.0 | 992.3 | 992.3 | 0.0 | 1,059.3 | 1,059.3 | 0.0 |