Water - Investment Planning and Prioritisation Group (IPPG) report: quarter 3 -2022 to 2023

Sets out how Scottish Water is progressing in developing interventions to address the needs on the ‘Development List’ up to the end of December 2022 (quarter 3 2022 to 2023).


Appendix B: Tabular information for Figure 1: 6 Year Investment Profile – PPD stage comparing investment forecast at the end of Quarter 2 2022-23 (previous) and at the end of Quarter 3 2022-23 (current) investment.

6 Year Investment (£m) 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27
Previous Current Variance Previous Current Variance Previous Current Variance Previous Current Variance Previous Current Variance Previous Current Variance
(Q2) (Q3) (Q2) (Q3) (Q2) (Q3) (Q2) (Q3) (Q2) (Q3) (Q2) (Q3)
Deliver Live 767.8 770.3 2.5 782.6 821.8 39.3 474.0 560.0 85.9 113.5 161.6 481.0 66.4 77.7 11.3 41.9 40.9 -1.1
Prepare Live 25.3 24.8 -0.5 80.0 79.9 -0.1 204.2 257.7 53.6 124.7 226.9 102.2 81.0 136.9 55.9 54.7 61.2 6.5
Plan Live 5.9 3.9 -2.0 53.4 38.5 -15.0 240.3 198.1 -42.2 274.8 312.5 37.7 425.1 464.3 39.2 378.2 441.3 63.1
Not Live 0.0 0.0 0.0 0.0 0.0 0.0 362.6 220.2 -142.4 705.6 676.4 -29.2 846.4 822.1 -24.3 978.5 961.3 -17.2
Completion Risk 0.0 0.0 0.0 10.1 0.0 -10.1 10.0 12.1 2.1 0.0 12.1 12.1 0.0 0.0 0.0 0.0 0.0 0.0
Total 799.0 799.0 0.0 926.1 940.2 14.2 1291.1 1248.1 -43.0 1218.6 1389.5 170.9 1418.9 1501.1 82.1 1453.4 1504.7 51.3
Planned Investment Level 799.0 799.0 0.0 858.0 858.0 0.0 898.0 898.0 0.0 942.2 942.2 0.0 992.3 992.3 0.0 1059.3 1059.3 0.0