5. Summary
The IPPG members are asked to:
- Note the developing maturity of the current Investment forecast.
- Note that the Q4 Progress to Committed List (PCL) was 113.6%, indicating that the rate of overall progress is more than sufficient to achieve planned investment levels.
- Note the progress and learning on project investment appraisals.