Planning Applications Statistics 2023/24: Quarterly (April 2023 to September 2023)

Statistics on planning applications and decision-making timescales for the first two quarters of 2023-2024. Data are collected as part of the Planning Performance Framework from local and planning authorities.


Glossary

Categories of Planning Applications

For planning applications, developments are put into one of five categories: local, major, other, Environmental Impact Assessments (EIAs) and national. This publication covers the first four as National Developments are dealt with by Scottish Ministers.

Local developments include applications for changes to individual houses, smaller developments of less than 50 homes, less than 2 hectares and less than 20 megawatts. Major developments include applications for 50 or more homes, greater than 2 hectares or more than 20 megawatts.

The full range of applications can include changes to properties, new builds, minerals, business & industry, waste management, electricity generation, freshwater fish farming, marine finfish farming, marine shellfish farming, telecommunications, Approval of Matters Specified in Conditions, Prior Notifications and other developments. The classification of all development types can be found in the planning series circular Go to Hierarchy of Developments web page.

Stopping the Clock

In some cases it is appropriate to remove a length of time from the total decision time. “Stopping the clock” is used where there has been a lengthy delay caused by the applicant or external consultees. This is not under the planning authority’s control and the authority cannot progress with an application.

Legacy Cases

On 3rd August 2009 changes were made to the statutory development management system and handling of planning applications. A few legacy cases from before then remain. They can have a large effect on average decision times so they are not included in the main analysis. They are reported separately in tables in the supporting spreadsheet file. No legacy cases were reported in the six month period.