Planning and Environmental Appeals Division (DPEA): annual review 2022 to 2023

Planning and Environmental Appeals Division's annual review of its performance for 2022 to 2023.


Appendix A: Statistics On Workload And Performance Against Targets

Table 1: Volume Of Cases* Handled By DPEA

Volume Of Cases Handled By DPEA
Business year In hand at start of the year Received Delegated appeals decided Reports submitted Withdrawn In hand at end of the year
2022-23 209 625 502 58 62 212
2021-22 199 577 468 53 46 209
2020-21 191 438 365 37 28 199
2019-20 213 601 470 69 84 191
2018-19 216 710 586 40 87 213

*Includes appeal and non-appeal cases

The total number of cases sisted/suspended as at 31 March 2023 was 29.

Table 2: Types Of Cases Received

Types Of Cases Received
Type Of Case 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023
Planning permission appeals 291 227 229 258 245
Planning enforcement appeals 89 94 37 76 82
Conservation area consent, listed building consent and listed building enforcement appeals 80 69 48 51 56
Advertisement consent, discontinuance notice and advertisement enforcement appeals 73 51 33 23 43
High Hedge appeal 33 17 8 20 16
All other types of appeal 46 45 46 66 61
Subtotal: all types of appeals 612 503 401 494 503
Called-in application 2 1 1 3 1
Called-in listed building consent - demolition 1 0 0 0 0
Completion Notice 0 1 0 0 0
Compulsory Purchase Order 8 10 5 5 3
Core Paths Plan 0 2 1 1 0
Extinguishment of Public Right of Way 3 2 0 0 0
Flood Prevention Scheme 1 0 0 1 0
Listed Building Notified Application 0 0 1 0 0
Local Development Plan 6 6 4 3 4
Notification Direction 0 2 0 0 1
Notified application 5 6 6 8 13
Power Station 0 1 0 0 0
Public path creation/diversion/extinguishment order 1 0 0 1 0
Purchase Notice 0 1 0 0 0
Revocation order 0 0 0 1 0
Roads order 16 5 2 0 2
Section 36 Wind Farm 4 5 8 5 9
Section 37 Transmission line 0 0 0 5 1
Stopping up order 3 2 1 5 1
Strategic Development Plan 0 1 0 0 0
Traffic Regulation Order 5 1 0 1 2
Wayleave 43 52 8 44 85
Subtotal: all types of non-appeal cases 98 98 37 83 122
All Cases Received 710 601 438 577 625

Table 3: Breakdown Of Cases Received By Their Characteristics

Breakdown Of Cases Received By Their Characteristics
Characteristics 2017-2018 2018-2019 2019-2020 2020-2021 2022-2023
Advertisement 78 57 33 24 46
Agricultural 8 7 9 7 12
Animal (cattery, kennel, stable etc.) 7 5 3 4 4
Building Alterations (householder) 94 86 72 72 64
Building Alterations (non-householder) 28 20 12 20 17
Business 37 28 22 9 23
Car park 24 23 12 17 17
Caravan and Campsites 13 9 4 13 16
Cemetery/Religious Building 2 2 1 1 3
Chimney/Flue 4 4 1 0 0
Community Asset Transfer 2 4 3 4 4
Compulsory Purchase Order 6 7 4 5 3
Demolition 14 15 13 13 23
Designation of Building/Monument 2 3 2 6 2
Development Plan (Local) 6 6 4 3 5
Development Plan (Strategic) 0 1 0 0 0
Dock/Harbour 0 1 1 1 0
Environmental Appeal 5 3 4 7 7
Fencing/Wall 29 30 20 31 16
Fish Farm 1 6 1 5 2
Flood Prevention Scheme 1 0 0 1 0
Hazardous Substance 0 1 0 0 0
Hedge 32 17 8 20 15
Holiday/Leisure 18 19 10 22 8
Hospital/Medical Centre 0 0 2 1 0
Hot Food Takeaway 9 8 5 9 4
Hotels 25 46 20 23 1
House in Multiple Occupation 1 8 1 4 8
Housing (10 or more houses) 59 55 50 54 38
Housing (more than one house) 21 22 22 23 24
Housing (single dwelling) 58 46 47 43 65
Hydro/Solar Power 0 2 1 0 1
Industrial 1 3 1 4 3
Landscaping 37 37 15 37 38
Leisure Facility/Ground 9 4 7 10 6
Meteorological/Anemometrical Mast 1 0 0 1 0
Mineral Extraction 3 0 3 3 3
Nursing/Care/Retirement Home 4 2 3 3 4
Other 23 5 4 22 13
Path 6 9 5 8 2
Petrol Station 3 4 0 1 1
Power Station/Energy from Waste 5 3 0 2 4
Recycling 1 1 0 1 0
Restaurant/Cafe/Licensed Premises 16 7 13 9 12
Retail (food) 5 10 13 6 2
Retail (non-food) 5 14 9 2 7
Road/Bridge 43 23 14 9 12
Scheduled Monument 0 0 0 1 1
School/Educational 2 6 4 2 5
Shed/Garage 26 20 24 27 13
Short stay accommodation 0 0 0 9 57
Short Stay Accommodation Under Application 0 0 0 0 1
Storage (non-warehousing) 8 19 12 10 7
Substation/Transmission Line/Pipeline 1 1 0 6 1
Telecommunication 26 1 15 13 12
Traffic Regulation Order 5 1 1 1 2
Transport 3 2 0 1 2
Travelling Persons Site 0 1 1 2 0
Tree 16 10 4 22 11
Warehouse/Distribution 0 0 0 3 3
Waste Disposal 6 4 0 0 1
Water/Sewage 19 8 8 8 10
Wayleave 43 51 8 44 84
Wind Farm (two or more turbines) 17 12 23 24 16
Wind turbine (single) 2 1 3 0 0
Windows - Timber 4 6 1 7 4
Windows - UPVC 26 21 6 12 15

Table 4a: Appeal Cases Success Rates By Method Of Determination

Appeal Cases Success Rates By Method Of Determination
Number decided Considered by oral process Considered by site visit/review of written submissions All cases allowed
Total Allowed Percentage Total Allowed Percentage Allowed Percentage
Delegate appeals
Planning permission 166 7 3 43% 159 84 53% 87 52%
Planning enforcement 73 0 - - 73 17 23% 17 23%
Conservation area consent, listed building consent and listed building enforcement 56 0 - - 56 21 38% 21 38%
Advertisement consent, discontinuance notice and advertisement enforcement 37 0 - - 37 26 70% 26 70%
High hedge 15 0 - - 15 11 73% 11 73%
All others 43 1 1 100% 42 21 50% 22 51%
All Delegated Appeals 390 8 4 50% 382 180 47% 184 47%
Non-delegated Appeals 7 2 1 50% 5 1 20% 2 29%
All Appeals 397* 10 5 50% 387 181 47% 186 47%

*In addition a further 112 appeals were turned away as we had no powers to determine them

Table 4b: Non-Appeal Cases Success Rates By Method Of Determination

Non-Appeal Cases Success Rates By Method Of Determination
Case types Number decided Considered by oral process Considered by site visit/review of written submissions All cases allowed
Total Allowed Percentage Total Allowed Percentage Allowed Percentage
Called-in application 3 1 0 0% 2 1 50% 1 33%
Compulsory Purchase Order 4 4 3 75% 0 - - 3 75%
Extinguishment of Public Right of Way 1 1 1 100% 0 - - 1 100%
Notification Direction 1 1 1 100% 0 - - 1 100%
Notified application 9 0 - - 9 6 67% 6 67%
Public path creation/diversion/ extinguishment order 1 1 1 100% 0 - - 1 100%
Roads order 3 3 3 100% 0 - - 3 100%
Section 36 Wind Farm 4 4 4 100% 0 - - 4 100%
Stopping up order 6 6 5 83% 0 - - 5 83%
Traffic Regulation Order 1 1 1 100% 0 - - 1 100%
Wayleave 3 2 2 100% 1 1 100% 3 100%
Total: All Non-appeal Cases 36 24 21 88% 12 8 67% 29 81%

Table 5: Success Rates For Delegated Appeals By Planning Authority

Success Rates For Delegated Appeals Planning Authority
Planning authority Appeals decided Appeals allowed Success rate
Aberdeen City Council 18 9 50%
Aberdeenshire Council 19 8 42%
Angus Council 4 1 25%
Argyll and Bute Council 3 3 100%
Cairngorms National Park Authority 2 1 50%
City of Edinburgh Council 98 44 45%
Clackmannanshire Council 1 1 100%
Comhairle nan Eilean Siar (Western Isles Council) 1 0 0%
Dumfries and Galloway Council 14 5 36%
Dundee City Council 9 7 78%
East Ayrshire Council 4 0 0%
East Dunbartonshire Council 13 10 77&
East Lothian Council 2 2 100%
East Renfrewshire Council 2 0 0%
Falkirk Council 6 2 33%
Fife Council 28 10 36%
Glasgow City Council 23 7 30%
Highland Council 16 8 50%
Inverclyde Council 1 0 0%
Loch Lomond and the Trossachs National Park Authority 3 2 67%
Midlothian Council 8 3 38%
Moray Council 11 7 64%
North Ayrshire Council 5 1 20%
North Lanarkshire Council 7 4 57%
Orkney Islands Council 3 3 100%
Perth and Kinross Council 13 5 38%
Renfrewshire Council 9 7 78%
Scottish Borders Council 4 2 50%
South Ayrshire Council 3 0 0%
South Lanarkshire Council 4 3 75%
Stirling Council 7 2 29%
West Dunbartonshire Council 5 2 40%
West Lothian Council 40 24 60%
Total 386 183 47%
Note: if an authority is not listed in table 5 it means no delegated decisions have been issued for sites within said authority’s area within the period.

Table 6a: Development Plan Examinations Completed

Development Plan Examinations Completed
Development plans Number of reporters Weeks to complete
Proposed Aberdeen Local Development Plan 2020 5 60
Proposed Aberdeenshire Local Development Plan 2020 7 67
East Dunbartonshire Proposed Local Development Plan 2 55

Table 6b: Development Plan Examinations In Hand Or Completed After End Of March

Development Plan Examinations In Hand/Completed After End of March
Development plans Received Report Date
Inner Moray Firth Proposed Local Development Plan 2 24/03/2023
East Ayrshire Local Development Plan 2 24/02/2023
Edinburgh Local Development Plan – Proposed City Plan 2030 08/12/2022
Scottish Borders Proposed Local Development Plan 14/07/2022
Argyll & Bute Proposed Local Development Plan 25/01/2022 13/06/2023

Table 7: Expenses Claims

Expenses Claims
Number of claims Successful claims
By an authority against:
A main contact 2 0
By a main contact against:
An authority 38 8

Table 8: Performance Against Our Targets

Performance Against Our Targets
Procedure Target number of weeks to determine Number of appeals Performance against target Average weeks taken to determine
No Further Procedure 8 7 86% 7.6
Site Inspection 12 252 87% 11.6
Further Written Submission 20 125 70% 21.6
Hearing 26 6 0% 47.3
Inquiry 32 2 0% 48.3

Table 9: Time Taken To Submit Reports

Time Taken To Submit Reports
Case types Reports submitted Average weeks taken to submit
Recalled Planning Permission Appeals 2 45.1
Called-in & Notified Applications 18 20.0
Compulsory Purchase Orders 3 78.8
Other Orders 13 72.6
Section 36 Wind Farm Applications 5 74.2
Wayleave Applications 11 35.9
Community Asset Transfer Appeals 3 16.7
Core Paths Plans 1 48.6

Contact