Planning, Infrastructure and Place Advisory Group: annual report 2024
Annual report covering the activities of the Planning Infrastructure and Place Advisory Group in 2024. Prepared in Collaboration with Scottish Futures Trust.
4. Year 1 Learning & Progress
4.1 Year 1 Outputs
The key Year 1 outputs were:
- Case studies produced on each Place Review and/or learning event, which champion good practice and make recommendations for more widely applicable solutions to explore. The case studies are presented in Appendix B, with key learnings and common themes summarised in section 4.2. These represent a snapshot in time, therefore it is likely that further progress has been made in the months since capture.
- Write-up of other learning activities, including the presentation from Scottish Power Energy Network (SPEN) on net zero energy infrastructure strategic challenges.
- Meeting minutes were prepared for each Advisory Group meeting including actions for the secretariat and the establishment of a short life working group where value could be added.
- A Short Life Working Group (SLWG) was established to undertake a deep dive into issues of funding and finance, exploring approaches and mechanisms to financial risk (and return) sharing in planning and development. A summary note was produced making conclusions and recommendations.
- Further meetings on specific opportunity/challenge areas, including:
- a meeting of core advisory group members and key Scottish Government officials and external representatives, to explore opportunities and challenges around data quality and availability. A summary note was produced with actions identified for PIPAG to progress to discussion. Although this action is still underway, early progress was made in 2024 and there is scope for data to be a priority for the 2025 work programme.
- an initial exploration of how to capture and promote place good practice, with future action anticipated in 2025.
- This PIPAG annual report (2024) assessing lessons and progress made by PIPAG in Year 1, providing the basis for agreeing the Year 2 (2025) focus for the group.
4.2 Summary of Emerging Themes
Common themes have emerged across the advisory group meetings, despite the different topic focus of each review and learning session. In many cases there are successful and innovative examples of solutions to address specific infrastructure delivery challenges, but these are often localised and therefore not embedded into best practice approaches that others can adopt easily.
There is no ‘one size fits all’ solution and the aim is for a place-based approach which recognises the specific challenges and opportunities which are unique to the place and its needs. However, there are common challenges that can be addressed more effectively through sharing lessons, knowledge and building capacity. These are summarised in the 4 below.
Area | Emerging Themes | Future opportunity |
---|---|---|
Case for investment |
|
|
Case for public investment |
|
|
Capacity Building |
|
|
Coordination |
|
|
Planning tools |
|
|
Risk (and return) sharing |
|
|
Alternative funding & finance |
|
|
4.3 Assessing progress
To assess progress, taking into consideration that this is only Year 1 of PIPAG activity, a high-level qualitative assessment has been made using the following RAG rating system.
Status | RAG rating | Definition |
---|---|---|
Significant progress achieved | Green | Strategic objective has been a high/priority focus |
Some progress achieved | Amber | Strategic objective has been a low/medium focus |
Not started | Red | Strategic objective has not yet been a focus |
Progress against strategic objectives
Using the above assessment framework, the Table below summarises PIPAG progress in Year 1 against the overarching strategic objectives for the advisory group.
Strategic Objectives (source: ToR, September 2023) | Progress | Comments | Possible Actions for Year 2 (2025) |
---|---|---|---|
Advise on the delivery of National Planning Framework 4. | Amber | The work of the group is included in the NPF Delivery programme versions 2 and 3. The focus on infrastructure and place reflect NPF4 priorities and is an element of its implementation. | Include National Development monitoring as part of the scope for Year 2 activity. |
Provide strategic input to the development of the next Infrastructure Investment Plan (IIP). | Red | A work programme was agreed for 2024 that was based on thematic case studies. Work on the development of the next IIP has been progressed, albeit not through the auspices of PIPAG. Providing input to the development of the IIP is anticipated to be a key focus for PIPAG during 2025. | Support the development of IIP (critical activity in 2025). |
Advise on prioritisation and targeting of public and private investment to optimise outcomes and achieve place-based transformational change and identify gaps in funding and finance. | Green | Significant progress made through the SLWG focused on the specific financing mechanism utilised at the Winchburgh development. The subject of getting the best value for money from investment has come up frequently. This work summarises how to translate key experiences into lessons to learn for the future. | Develop further findings on funding and finance to provide advice that supports place-based transformational change. |
Guide improved alignment and integration of place-based and spatial approaches in public and private sector decision-making. | Green | The case study work highlights opportunities for improved alignment and integration to optimise outcomes. | Continue to foster this approach and underpinning principle through the IIP. |
Demonstrate what good infrastructure delivery looks like and promote innovation and best practice. | Green | The case studies identify many examples of good practice. These are being shared more widely through the publication of this annual report. | Consider how to further crystalise and disseminate good practice to achieve change on the ground. |
Review progress in delivering the spatial strategy, National Developments and national planning policy set out in NPF4. | Red | The agreed work programme didn’t explicitly cover this. The NPF4 Monitoring report is the main vehicle for reviewing this progress, and this work has been progressed, albeit not through the auspices of PIPAG. | Include National Developments monitoring as part of the scope for Year 2 activity. |
Visibly champion delivery and challenge decision-makers to consider new ways of working, in the spirit of public service reform. | Amber | The group has promoted projects which have delivered change on the ground. These projects are included as case studies at Appendix B. | Further consideration to be given to how delivery is championed and how this is communicated. |
Identify issues and blockers to development, regeneration and implementation of an ‘infrastructure first’ approach in practice. | Amber | Issues and blockers summarised in case studies and lessons learnt covered in Section 0, with further detail in the Appendix B case studies. | Any additional issues and blockers identified through analysis of National Developments / other developments to be added. |
Identify, explore and share solutions and scope for innovation to overcome barriers to development and infrastructure delivery, including by applying the Place Principle in practice. | Amber | Winchburgh example – financial risk-return sharing issues explored. Place principle work to be taken forward by other areas of Government. | To follow up with Scottish Government to discuss how the findings of the SLWG have been used to inform thinking on support for future developments; and that the place principle continues to be championed, through demonstrating the benefits of spatial alignment. |
Reflect on the impacts and opportunities arising from wider change, including the implications of wider Scottish Government policy and programmes as they evolve. | Amber | A number of specific issues emerged during 2023/24. In developing a work programme, PIPAG has considered a number of these and has sought to consider which of those it is best place to consider directly or indirectly. Issues include:
|
Work programme to reflect on drivers of change, including Budget (Dec 2024) implications and any other policy and programme announcements. |
Progress against the PIPAG Monitoring & Evaluation (M&E) Framework
Indicator | Progress | Comments |
---|---|---|
Demonstrate improved integration of place, planning and infrastructure policy. | This indicator requires integration of learnings into the Infrastructure Investment Plan (IIP) which is a critical Year 2 (2025) activity for PIPAG. Key learnings are summarised in this annual report but are yet to be used to help inform and shape the next IIP. | |
Clear demonstration of barriers, solutions and learning to infrastructure development. | This annual report provides a summary of barriers, solutions and learning to infrastructure development through the case studies, additional working group and research workstreams. | |
National Developments (NDs) are monitored to support implementation. | Year 2 (2025) of PIPAG activity will pick up National Development monitoring to support implementation. |
Contact
Email: chief.planner@gov.scot
There is a problem
Thanks for your feedback