Planning performance statistics: third quarter, 2016-2017
Summary of statistics on planning decision-making and timescales, as well as historic data going back to 2012 to 2013.
4. Processing Agreements
Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. When an application is subject to a processing agreement it is removed from average decision time calculations and reported separately. In quarter three of 2016/17 there were 381 applications that were subject to a processing agreement, and 83.5% of these were decided within agreed timescales. ( Quarter 3, 2016/17 - Table 1).
Table 1: Processing Agreements, 2016/17, Quarter 3
Category of development | Number of Decisions | % Within Agreed Timescales |
---|---|---|
Major Applications | 25 | 64.0% |
Local Applications | 312 | 85.9% |
EIA Developments | 0 | - |
Other Consents | 44 | 77.3% |
Total | 381 | 83.5% |