Planning Performance Statistics 2020/21: Quarterly (October 2020 To March 2021)

This report presents summary statistics on planning application decision-making timescales for October 2020 to March 2021, as well as historic data back to 2016/17. It is based on data collected from Local and Planning Authorities as part of the Planning Performance Framework (introduced in 2012).


10. Legacy Cases

One legacy case was decided in quarter three. The decided application was subject to a processing agreement. Two legacy cases were decided in quarter four, one with and one without a processing agreement.

Tables 4 to 9 show the legacy cases decided in the final six months of 2020/21 by planning authority and development type.

Quarter 3 2020/21 - Decided legacy applications with processing agreements

Table 4
Local Authority Number of Legacy Cases % meeting agreed timescales
East Lothian 1 100%
Total 1 100%
Table 5
Development Type Number of Legacy Cases % meeting agreed timescales
Listed Building Consent 1 100%
Total 1 100%

Quarter 4 2020/21 - Decided legacy applications without processing agreements

Table 6
Local Authority Number of Legacy Cases Average Decision Time (weeks)
West Dunbartonshire 1 939.0
Total 1 939.0
Table 7
Development Type Number of Legacy Cases Average Decision Time (weeks)
Minerals - Local with EIA 1 939.0
Total 1 939.0

Quarter 4 2020/21 - Decided legacy applications with processing agreements

Table 8
Local Authority Number of Legacy Cases % meeting agreed timescales
East Ayrshire 1 0%
Total 1 0%
Table 9
Development Type Number of Legacy Cases % meeting agreed timescales
Housing - Major 1 0%
Total 1 0%