Planning performance statistics: second quarter, 2017-2018
The latest statistics on planning application decision-making and timescales from July to September 2017-2018.
4. Processing Agreements
Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. When an application is subject to a processing agreement it is removed from average decision time calculations and reported separately. In quarter two of 2017/18 there were 532 applications that were subject to a processing agreement, 61 (13 per cent) more than in the previous quarter, and 80.5 per cent of these were decided within agreed timescales ( Quarter 2, 2017/18 – Table 1).
Table 1: Processing Agreements, 2017/18, Quarter 2
Category of development | Number of Decisions | % Within Agreed Timescales |
---|---|---|
Major Applications | 23 | 78.3% |
Local Applications | 423 | 81.3% |
EIA Developments | 1 | 100% |
Other Consents | 85 | 76.5% |
Total | 532 | 80.5% |