Water Industry - Scottish Government Investment Group - Committed List performance progress report: quarter two 2023-2024
Sets out how Scottish Water is progressing with the delivery of projects and programmes included on the ‘Committed List’ and confirms the position up to the end of September 2023 (Q2 2023/24).
Appendix B: Wastewater Sub-portfolios
The list of projects included in the sub-portfolios can be found by filtering the Committed List by column E.
Wastewater SR15 Completion Projects
The overall IPOD points for the Wastewater SR15 Completion sub-portfolio is below the range at 66 points against a range of 74 to 77 points for Q2 2023/24.
Start on Site
The Wastewater Completion sub-programme is within the forecast range at the time of commitment. 7 projects have achieved this milestone against a target of 7.
Acceptance
1 project (SW843 Wellgate Lanark) achieved acceptance during Q2, bringing the total number of completed projects delivering benefit to customers to 30 which is out with the target of 34 points. 4 in the SR15 Completion sub-portfolio have been reforecast.
Reasons for reforecasting:
- 4 projects have been impacted due to third party issues: QS3b AR - P014 UID Westbank Quadrant at Eldon Street Bridge Combined Sewer Overflow (CSO) NS273667, S043 - UID - Cambuslang Road Richmond Laundry - South East of Railway Rutherglen, S087 - UID - Scotwood Overflow North East of Lay-by Busby Road, SR15 ES - Main Street Newtonmore
Project ID | Description | Reason For Reforecast | Baseline Quarter | Forecast Quarter |
---|---|---|---|---|
404026 | SR15 ES - Main Street Newtonmore | Third party issues | 2022/23 Q1 | 2024/25 Q3 |
401705 | S087 - UID - Scotwood Overflow North East of Lay-by Busby Road | Third party issues | 2021/22 Q3 | 2024/25 Q1 |
401668 | S043 - UID - Cambuslang Road Richmond Laundry - South East of Railway Rutherglen | Third party issues | 2021/22 Q2 | 2024/25 Q1 |
403106 | QS3b AR - P014 UID Westbank Quadrant at Eldon Street Bridge CSO NS273667 | Third party issues | 2022/23 Q4 | 2023/24 Q3 |
Total | 4 projects behind |
Financial Approval
2 projects (Londornoch WTW Sludge Lagoon Upgrade, SR15 ES - Sanday Sludge Storage Area and Drying Beds) achieved financial completion during Q2, taking the total achieved to 29 which is out with the target range of 33 to 36 points. 6 in the SR15 Completion sub-portfolio have been reforecast.
Reasons for reforecasting:
- 1 project has been impacted due to construction risks realised: Dalmarnock WWTW Improvements
- 5 projects have been impacted due to third party issues: SW843 Wellgate Lanark, QS3b AR - P010 UID Botanic Gardens Nr Junc of Garrioch Drive Garrioch Rd and Shakespeare St, S043 - UID - Cambuslang Road Richmond Laundry - South East of Railway Rutherglen, S087 - UID - Scotwood Overflow North East of Lay-by Busby Road, SR15 ES - Main Street Newtonmore
Project ID | Description | Reason For Reforecast | Baseline Quarter | Forecast Quarter |
---|---|---|---|---|
404026 | SR15 ES - Main Street Newtonmore | Third party issues | 2023/24 Q1 | 2024/25 Q4 |
401705 | S087 - UID - Scotwood Overflow North East of Lay-by Busby Road | Third party issues | 2022/23 Q2 | 2024/25 Q2 |
401668 | S043 - UID - Cambuslang Road Richmond Laundry - South East of Railway Rutherglen | Third party issues | 2022/23 Q1 | 2024/25 Q3 |
403102 | QS3b AR - P010 UID Botanic Gardens Nr Junc of Garrioch Drive Garrioch Rd and Shakespeare St | Third party issues | 2022/23 Q1 | 2023/24 Q4 |
503269 | Dalmarnock WWTW Improvements | Construction risks realised | 2022/23 Q4 | 2024/25 Q1 |
500681 | SW843 Wellgate Lanark | Third party issues | 2023/24 Q1 | 2023/24 Q4 |
Total | 6 projects behind |
Wastewater Network Projects
The overall IPOD points for the Wastewater Network sub-portfolio is below the range at 89 points against a range of 90 to 102 points for Q2 2023/24.
Start on Site
1 project (Internal Flooding Overloaded Sewers (IFOS) - Peatville Terrace Edinburgh Mitigation v.3) started on site during Q2 bringing the total number of projects achieving the Start On Site milestone to 18 with performance being in the top half of the range of 13 to 20 points.
Acceptance
1 project (ICF - Forres Strategic Wastewater upgrade) achieved acceptance during Q2, bringing the total number of completed projects delivering benefit to customers to 38 which is out with the target range of 39 to 43 points. 4 in the Wastewater Network sub-portfolio have been reforecast.
Reasons for reforecasting:
- 1 project has been impacted due to construction risks realised: Shieldhall WWTW Grade 5 HC Sewer Ph1
- 3 projects have been impacted due to third party issues: IR18 CAS Compliance Improvements - Networks East & North, Complex, Dunfermline Wellwood Waste Water Infrastructure, Infra-Kingdom Park
Project ID | Description | Reason For Reforecast | Baseline Quarter | Forecast Quarter |
---|---|---|---|---|
503362 | Infra-Kingdom Park | Third party issues | 2021/22 Q2 | 2024/25 Q2 |
502949 | Dunfermline Wellwood Waste Water Infrastructure | Third party issues | 2021/22 Q4 | 2023/24 Q4 |
501683 | Shieldhall WWTW Grade 5 HC Sewer Ph1 | Construction risks realised | 2021/22 Q3 | 2023/24 Q3 |
502944 | IR18 CAS Compliance Improvements - Networks East & North, Complex | Third party issues | 2021/22 Q2 | 2023/24 Q4 |
Total | 4 projects behind |
Financial Approval
1 project (Oban, Stevenson Street SPS - Replace Screw Pumps) achieved financial completion during Q2, taking the total achieved to 33 which is outwith the target range of 38 to 39 points. 7 in the Wastewater Network sub-portfolio have been reforecast.
Reasons for reforecasting:
- 3 projects have been impacted due to construction risks realised: Shieldhall WWTW Grade 5 HC Sewer Ph1, Ayr Shore Road SPS - Emergency Repairs to Transfer Pumps and Wet Well Guide Rails, NRSWA Construction Sewer Greenhills Road Widening East Kilbride
- 4 projects have been impacted due to third party issues: Bothwell Sewer - Replacement of approximately 130m of 600mm, IR18 CAS Compliance Improvements - Networks East & North, Complex, Dunfermline Wellwood Waste Water Infrastructure, W462 - Coalburn Road Coalburn
Project ID | Description | Reason For Reforecast | Baseline Quarter | Forecast Quarter |
---|---|---|---|---|
500302 | W462 - Coalburn Road Coalburn | Third party issues | 2022/23 Q4 | 2023/24 Q3 |
502949 | Dunfermline Wellwood Waste Water Infrastructure | Third party issues | 2022/23 Q4 | 2024/25 Q1 |
502866 | NRSWA Construction Sewer Greenhills Road Widening East Kilbride | Construction risks realised | 2022/23 Q3 | 2023/24 Q4 |
503393 | Ayr Shore Road Sewerage Pumping Station (SPS) - Emergency Repairs to Transfer Pumps and Wet Well Guide Rails | Construction risks realised | 2022/23 Q2 | 2023/24 Q4 |
501683 | Shieldhall WWTW Grade 5 HC Sewer Ph1 | Construction risks realised | 2022/23 Q2 | 2024/25 Q1 |
502944 | IR18 CAS Compliance Improvements - Networks East & North, Complex | Third party issues | 2022/23 Q1 | 2024/25 Q1 |
503415 | Bothwell Sewer - Replacement of approximately 130m of 600mm | Third party issues | 2022/23 Q4 | 2023/24 Q4 |
Total | 7 projects behind |
Wastewater Treatment Projects
The overall IPOD points for the Wastewater Treatment sub-portfolio is within the range at 126 points against a range of 125 to 146 points for Q2 2023/24.
Start on Site
5 projects (E-WW-NI-070422-Banchory STW Chemical Dosing, Shieldhall WWTW - Storm Screen Refurbishment x No.6, E-WW-NI-161222-Banchory Inlet Screen and Grit System Construction, Oban WwTW - 2 No Replacement SHTs, ICF - Bertha Park Strategic Wastewater Infrastructure) started on site during Q2 bringing the total number of projects achieving the Start On Site (SOS) milestone to 35 with performance being in the top half of the range of 28 to 37 points.
Acceptance
2 projects (Forres WWTW 1973 NJ038595 - SR15 Capital Maintenance, Banchory WwTW - Growth) achieved acceptance during Q2, bringing the total number of completed projects delivering benefit to customers to 49 which is out with the target range of 51 to 58 points. 6 in the Wastewater Treatment sub-portfolio have been reforecast.
Reasons for reforecasting:
- 1 project has been impacted due to additional scope required to complete: Alloa STW
- 2 projects have been impacted due to construction risks realised: Carstairs Village WwTW - Growth, DALDERSE WWTW 1966 NS903822
- 3 projects have been impacted due to third party issues: Kennethmont WwTW Growth, East Linton WwTW - Growth, Burrelton WwTW - Growth
Project ID | Description | Reason For Reforecast | Baseline Quarter | Forecast Quarter |
---|---|---|---|---|
500233 | Burrelton WwTW - Growth | Third party issues | 2021/22 Q4 | 2023/24 Q3 |
500229 | East Linton WwTW - Growth | Third party issues | 2023/24 Q2 | 2024/25 Q3 |
501579 | DALDERSE WWTW 1966 NS903822 | Construction risks realised | 2022/23 Q3 | 2023/24 Q3 |
500052 | Carstairs Village WwTW - Growth | Construction risks realised | 2022/23 Q2 | 2023/24 Q3 |
501159 | Alloa STW | Additional scope required to complete | 2023/24 Q1 | 2025/26 Q3 |
403782 | Kennethmont WwTW Growth | Third party issues | 2023/24 Q1 | 2023/24 Q4 |
Total | 6 projects behind |
Financial Approval
3 projects (Canonbie WwTW - Upgrade Growth (Transfer from 403465), Aboyne WwTW - Capital Maintenance, E-WW-NI-140721-Inverurie Old STW Redundant Assets Demo) achieved financial completion during Q2, taking the total achieved to 42 which is out with the target range of 46 to 51 points. 10 in the Wastewater Treatment sub-portfolio have been reforecast.
Reasons for reforecasting:
- 2 projects have been impacted due to additional scope required to complete: Stewarton WwTW - Growth, Kinneil Kerse WwTW - Capital Maintenance
- 4 projects have been impacted due to construction risks realised: Catrineholm WwTW- Emergency Project to Maintain CAR Licence Compliance, Carstairs Village WwTW - Growth, DALDERSE WWTW 1966 NS903822, Lochwinnoch WwTW - Inlet Screw Pumps Refurbishment - 500k
- 4 projects have been impacted due to third party issues: Banchory WwTW - Growth, Forres WWTW 1973 NJ038595 - SR15 Capital Maintenance, Burrelton WwTW - Growth, HV Asset Replacement Phase 1 - Shieldhall WwTW
Project ID | Description | Reason For Reforecast | Baseline Quarter | Forecast Quarter |
---|---|---|---|---|
505641 | Lochwinnoch WwTW - Inlet Screw Pumps Refurbishment - 500k | Construction risks realised | 2023/24 Q2 | 2023/24 Q4 |
500579 | Kinneil Kerse WwTW - Capital Maintenance | Additional scope required to complete | 2022/23 Q3 | 2023/24 Q4 |
403939 | Stewarton WwTW - Growth | Additional scope required to complete | 2022/23 Q4 | 2023/24 Q3 |
502268 | HV Asset Replacement Phase 1 - Shieldhall WwTW | Third party issues | 2022/23 Q4 | 2023/24 Q3 |
500233 | Burrelton WwTW - Growth | Third party issues | 2022/23 Q3 | 2023/24 Q4 |
501579 | DALDERSE WWTW 1966 NS903822 | Construction risks realised | 2023/24 Q2 | 2023/24 Q4 |
500052 | Carstairs Village WwTW - Growth | Construction risks realised | 2023/24 Q1 | 2023/24 Q4 |
500580 | Forres WWTW 1973 NJ038595 - SR15 Capital Maintenance | Third party issues | 2023/24 Q2 | 2023/24 Q4 |
501021 | Banchory WwTW - Growth | Third party issues | 2022/23 Q3 | 2023/24 Q3 |
507933 | Catrineholm WwTW- Emergency Project to Maintain CAR Licence Compliance | Construction risks realised | 2023/24 Q2 | 2023/24 Q3 |
Total | 10 projects behind |