Delivery Assurance Group (DAG) report: quarter 2 2021-2022

Report summarising what has been achieved for customers against Scottish Water's Delivery Plan for the 2021 to 2027 period during the first quarter of 2021 to 2022.


Appendix A - summary of milestone attainment position at Q2 2021/22

Table 1: summary of milestone attainment position at Quarter 2 2021-22
Gate
Committed Min (-3 months)
Committed Forecast (baseline)
Committed Max (+ 3 months)
Actual Status
Start on site 18 32 43 32 On track
Project acceptance (G100) 52 112 149 79 On track, (behind baseline)
Financial close (G110) 5 5 37 17 On track (ahead of baseline)
Total 75 149 229 128