Delivery Assurance Group (DAG) report: quarter 2 2021-2022
Report summarising what has been achieved for customers against Scottish Water's Delivery Plan for the 2021 to 2027 period during the first quarter of 2021 to 2022.
Appendix B - SR15 Completion Programme
SR15 Completion Programme – Delayed Projects Status | |||
---|---|---|---|
Stage | Forecast at March 2021 | Actual at Q2 2021-22 | Variance |
Pre Start on Site | 5 | 8 | 3 |
In Construction | 32 | 42 | 10 |
Construction Complete | 49 | 36 | -13 |
Total | 86 | 86 | 0 |