Report on the work of the 2021 Affordable Housing Investment Benchmarks Working Group

Report on the work of the 2021 Affordable Housing Investment Benchmarks Working Group.


  • A review of Affordable Housing Investment Benchmarks was undertaken between March and June 2021.  The review was carried out by a cross-sector working group of officials and was jointly chaired by the Scottish Government and COSLA.                                                       
  • Benchmark assumptions are not grant rates or grant ceilings, and therefore have no role in shaping expectations of grant funding levels for any particular project.  Projects that can be delivered with grant funding at or below the relevant benchmark assumption follow a streamlined application and approval process, with projects which are seeking grant funding in excess of the relevant benchmark assumption following a more detailed value for money assessment. 
  • The working group recognised that the Affordable Housing Supply Programme had worked well in delivering significantly increased numbers of affordable homes in recent years.  While the flexibility of the system was welcomed, unit costs had risen significantly over this time and it was recognised that the benchmarks therefore needed to be increased.
  • Local government and Registered Social Landlord (RSL) representatives on the group were also of the view that current benchmark assumptions were driving up rents ahead of inflation, thereby putting further strain on affordability – local government representatives reported that the level of costs falling on council tenants was now at 62%.  The Scottish Government was clear however that Affordable Housing Investment Benchmarks should have no bearing on rent setting processes as they were simply a tool for determining the appraisal route for grant applications.  When determining the level of grant funding that they need to apply for in order to deliver affordable housing projects, the Scottish Government noted that grant applicants must be comfortable with the level of borrowing that they plan to take on – as well as being satisfied that tenants’ rents remain affordable (including, in the case of RSLs, ensuring that social rent levels at the point of completion comply with Scottish Government published guidance).
  • With the removal of (a) ‘outlier’ projects – that is those that were below or over the relevant benchmark by more than £20,000 per unit (to avoid skewing of the data in either direction) and (b) projects in Glasgow (given that the City Council (i) has a separate standard that it requires RSLs to deliver to and (ii) undertakes detailed appraisals of all projects), the Scottish Government reported that between April 2016 to September 2020 70% of social rented units were approved at or below the relevant grant subsidy benchmark assumption which was introduced in early 2016, with 33% of those homes being approved below benchmark.    
  • It was noted however, that an increasing number of projects were being approved above benchmark as time progressed, with sector representatives pointing out that by 2019-20 the majority of RSL projects were above benchmark.  Sector representatives also argued that the delivery of projects at or below current benchmark assumptions was largely due to an unsustainable increase in the use of council and RSL resources (thus reducing the grant being sought).
  • Following consideration of information presented during the review, the Scottish Government is proposing that baseline benchmark assumptions increase by between £14,500 to £26,000 for a council social rented home (an increase of between 25% and 46% depending on geography); by between £8,000 and £13,500 for an RSL social rented home (an increase of between 11% and 17% depending on geography); and by between £9,500 to £14,500 for an RSL mid-market rented home (an increase of between 22% and 33% depending on geography).  The Scottish Government’s proposals result in the following set of baseline benchmark assumptions:

 

West Highland, Island authorities, and remote/ rural Argyll

 

Other rural

City and urban

Current

Proposed

Current

Proposed

Current

Proposed

 

RSL social rent

£82,000

(3 person equivalent)

£95,500

(3 person equivalent)

 

£72,000

(3 person equivalent)

£83,000

(3 person equivalent)

£70,000

(3 person equivalent)

£78,000

(3 person equivalent)

Council social rent

£57,000

(flat rate per unit)

£83,000

(3 person equivalent)

 

£57,000

(flat rate per unit)

£75,500

(3 person equivalent)

£57,000

(flat rate per unit)

£71,500

(3 person equivalent)

RSL mid-market rent

£44,000

(3 person equivalent)

£58,500

(3 person equivalent)

 

£44,000

(3 person equivalent)

£56,500

(3 person equivalent)

£44,000

(3 person equivalent)

£53,500

(3 person equivalent)

Council mid-market rent

N/A

£53,000

(3 person equivalent)

 

N/A

£51,500

(3 person equivalent)

N/A

£49,000

(3 person equivalent)

  • It was COSLA’s agreed position that baseline benchmark assumptions should be the same for councils and RSLs, and that these should be based on the six-fold geographic classification.  Having considered the evidence, the Scottish Government is proposing to reduce the differential from the current range of between £13,000 and £25,000 per unit to between £6,500 and £12,500 per unit.  The Scottish Government is of the view that complete removal of the differential is not justified given evidence of the cheaper costs of borrowing for new build for councils, alongside councils having the option to use council tax on second homes.  RSL representatives on the group supported the proposal to maintain a differential, alongside the continuing use of the current approach to determining a project’s geographic classification. 
  • All other aspects of the baseline benchmarks system have been aligned so that the regime for councils and RSLs are now identical – this means that council benchmarks will now be at the three-person equivalent level (rather than at a flat rate per unit), council benchmarks will now attract the geographic differential (rather than being the same regardless of geography), and councils will now be able to apply for grant support to deliver homes for mid-market rent (in addition to RSLs).
  • The group also noted that the additional quality measures that are being phased into the Affordable Housing Supply Programme from 2021-22 – such as the requirement to install automatic fire suppression systems – were likely to increase unit costs further.  Following consideration of the information gathered during the review, the Scottish Government is proposing that benchmarks should be introduced for each of these quality improvements such that a project qualifying for all of these additional measures would see the relevant benchmark assumption rising by a further £17,300 per unit, three-person equivalent level.  To respond to concerns that some of these benchmark assumptions may be too low, the Scottish Government will work with councils and RSLs to gather information on the costs associated with certain measures, with a view to closely monitoring these moving forward.
  • The group agreed that any new set of benchmark assumptions should be reviewed each year.  The Scottish Government proposed that the Scottish Social Housing Tender Price Index be used for this purpose, with local government representatives also proposing that other material evidence based issues should be taken into account. 
  • In order to demonstrate improvement in quality and value for money over time, the Scottish Government proposed the introduction of a consistent national programme of continuous improvement.  The housing association sector suggested however that further research and sector engagement is needed to design a continuous improvement programme that is realistic, achievable and meaningful in its impact.   
  • The group did not consider all of the elements within its remit in detail.  Local government and housing association representatives on the group noted that they would wish to see these discussed as part of a second stage review process, alongside consideration of the following issues which they raised during the review – the requirement for detailed information on built form and type, procurement routes, land and remediation costs, the three-person equivalent, brownfield versus greenfield sites, homes delivered through Section 75 agreements, and space standards.
  • In favouring a ‘staged approach’ rather than a second stage review process, the Scottish Government confirmed that it would convene discussions with the sector should the following situations arise:
  • there be any variations to the Scottish Government specified quality standards for homes delivered through the Affordable Housing Supply Programme which would have a material impact on development costs,
  • evidence demonstrates that there is an increase in the number of applications requiring above benchmark grant funding, which is having a material impact on the speed of Affordable Housing Supply Programme delivery (with the exception of projects in Glasgow for the reasons specified above), and/ or
  • evidence suggests that a disproportionate number of projects with an average unit size of less than three bedspaces are subject to detailed scrutiny (again with the above exception).

The Scottish Government agreed that some of the other issues which were not covered in detail during the review deserved discussion and analysis, and noted that decisions taken on some could be better informed through an evidence-based continuous improvement system for housing development.

Back to top