Building standards - building warrant fee model: research project
The purpose of this study is to develop proposals and a model that can be used to deliver a funding model that is flexible and can be adjusted to allow changes to building warrant fees in Scotland.
5. Model Results
5.1 Introduction
5.1.1 The new fee model buildings on the Phase 1 model and continues to be based on the number of building warrant applications by value of work bands. However, the model has the flexibility to estimate the additional fee required to deliver the new activities shown in Boxes 2 to 4 in Figure 3.2. The model has been developed at the Scotland-wide level but it can be applied at the sub-national level. Some sub-national modelling has been undertaken for five broad categories of authorities – urban, primarily urban, mixed, primarily rural and rural.
5.1.2 The structure of the model is shown in Figure 5.1. The core model estimates fee income from building warrant applications by type and value of work bands. It then makes an allowance for discounts provided for certification to determine total building warrant fee income net of certification discounts.
Figure 5.1: Structure of Building Warrant Fee Model
- No. of Cases by Building Warrant Type
- Fee per Case
- Income by Warrant Type and Total
- Discounts for Certification
- Building Warrant Fee Income Post Certification
5.1.3 The model was developed using data from 2021/22 and tested on historic application data (e.g. number of applications by value of work band) for the five year period 2017/18 to 2021/22. These historic data form the baseline of the model.
5.1.4 The modelling has been undertaken for two scenarios:
- Scenario 1: Overheads in building standards are assumed to be 30% of staff costs which is consistent with KPO5.
- Scenario 2: Overheads in building standards are assumed to be 20% of staff costs.
5.1.5 In the two scenarios, it is assumed that there is £1 million of funds already in the system and the additional funds for the future delivery of the existing building standards service (Box 1 in Figure 3.2) is reduced by this amount. All other additional funds are assumed to be raised through fees and an allowance for inflation. Inflation has been dealt with in the model in two ways:
- For fixed fee rates, an inflationary increase of 22.9%[12] has been applied to allow for the effects of inflation between 2017 and 2022. Inflation is forecast to be 7% between 2022 and 2023 and 2.5% per annum thereafter[13].
- Increasing construction costs will, over time, move an application up the value of work scale. To allow for this, we have assumed that the cost of the building warrant increases by 7% between 2022 and 2023 and 2.5% per annum thereafter11.
5.1.6 The additional funds raised through the inflationary effects on non-fixed fee rates have been used to reduce the amount of additional funds required to be raised from increased fee rates as extra fees will be delivered. It is also only the non-fixed fees which contribute to the additional funds required to deliver the future building standards service.
5.2 Scenario 1: 30% Uplift for Overheads
5.2.1 Table 5.1 sets out the fee scales for non-HRB projects under Scenario 1 (30% overhead uplift). Table 5.2 provides the fee rates for HRB projects. It is assumed that most HRB projects are likely to be in the higher value of work bands. However, the compliance plan process will also apply to extensions and alterations of HRBs, therefore there is a HRB fee rate for all value of work bands excluding the lowest (£0 to £10,000) value of work band. Total HRB fee rates include both the non-HRB fee plus the HRB uplift. The results are shown for each of the three forecast years with the percentage increase between current and 2026/27 fees also shown.
5.2.2 The Tables shows:
- The largest percentage increases for non-HRB buildings are in the fixed fee category which reflects the effects of inflation from 2017 to each of the forecast years.
- The phased approach to HRBs results in more modest increases in fees in the first two years. The increase in 2026/27 in the lower value of work categories (£10,001 to £50,000 and £50,001 to £250,000) is high relative to the current rate. This is primarily driven by the fixed cost assumed for pre-application discussions at either £900 for values of work over £250,000 or £450 for lower values of work. The pre-application discussion cost dominates the extra HRB cost at value of work bands up to £1 million.
Value of Work Band | Current Fee, £ | 2024/25, £ | 2025/26, £ | 2026/27, £ | % Change Current to 2026/27 | |
---|---|---|---|---|---|---|
0-£10,000 |
Conversion Demolition Extension Zero Fee <£5000 £5k - £10k |
150 150 100 - 150 245 |
207 207 138 - 207 261 |
212 212 142 - 212 276 |
218 218 145 - 218 293 |
45.2 45.2 45.2 - 45.2 19.6 |
£10,001-£50,000 |
Zero Fee All Others |
- 593 |
- 631 |
- 669 |
- 709 |
- 19.6 |
£50,001-£250,000 | 1,240 | 1,319 | 1,399 | 1,483 | 19.6 | |
£250,001-£1 million | 2,682 | 2,854 | 3,025 | 3,208 | 19.6 | |
>£1 million | £1-£5m £5-10m £10-£25m £25-50m >£50m |
7,910 18,789 33,970 79,509 142,759 |
8,416 19,991 36,143 84,595 151,891 |
8,922 21,193 38,316 89,681 161,022 |
9,462 22,475 40,633 95,105 170,762 |
19.6 19.6 19.6 19.6 19.6 |
Amendments | <£5k >£5k |
100 435 |
138 463 |
142 491 |
145 520 |
45.2 19.5 |
Note: 2022/23 and 2023/24 have not been modelled as the existing fee rates will apply in these rates.
Inflation increases are built into the modelled fee rates.
Value of Work Band | Current Fee, £ | 2024/25, £ | 2025/26, £ | 2026/27, £ | % Change Current to 2026/27 | |
---|---|---|---|---|---|---|
0-£10,000 | - | - | - | - | - | |
£10,001-£50,000 | 593 | 645 | 699 | 1,222 | 106.1 | |
£50,001-£250,000 | 1,240 | 1,350 | 1,461 | 2,063 | 66.4 | |
£250,001-£1 million | 2,682 | 2,919 | 3,161 | 4,390 | 63.7 | |
>£1 million | £1-£5m £5-10m £10-£25m £25-50m >£50m |
7,910 18,789 33,970 79,509 142,759 |
8,609 20,450 36,973 86,538 155,380 |
9,323 22,144 40,036 93,708 168,253 |
11,192 25,346 45,099 104,350 186,645 |
41.5 34.9 32.8 31.2 30.7 |
Note: 2022/23 and 2023/24 have not been modelled as the existing fee rates will apply in these rates.
Inflation increases are built into the modelled fee rates.
5.2.3 Table 5.3 sets out the fee income raised from the various fee activities for Scenario 1 using the fee rates in Tables 5.1 and 5.2. The total income raised (net of certification discounts[14] is estimated to be £36.8 million in 2024/25, rising to £43.3 in 2026/27.
Income from: | 2024/25 | 2025/26 | 2026/27 |
---|---|---|---|
Current fee rates Inflation to fixed fees rates Inflation drag (non-fixed rates) Extra fee existing LA/BSD activities Extra fee additional LA activities Extra fee for Hub Extra fee for HRBs |
36.227 0.776 (4.246) 5.503 - 0.930 0.271 |
36.227 0.846 (5.207) 6.871 1.696 1.014 0.561 |
36.227 0.918 (6.192) 8.287 3.515 1.098 2.199 |
Total Income Before Certification Discount | 39.461 | 42.009 | 46.052 |
Certification Discount | 2.637 | 2.703 | 2.770 |
Total Income Post Certification Discount | 36.824 | 39.306 | 43.281 |
Note: The income raised from inflation drag reduces the amount of additional funds required to be raised from increased fee rates as extra fees will be delivered.
5.3 Scenario 2: 20% Overhead Uplift
5.3.1 Table 4.5 sets out the additional funds required to deliver the future building standards service using the box numbers in Figure 3.2 when a 20% overhead uplift is adopted and the phasing of activities set out in para 4.3.2. The building standards service is forecast to require an additional £6.2 million in 2024/25, rising to £14.1 million in 2026/27. The largest individual component is the additional funds required to deliver the existing service. The increase in the cost of delivering the existing service is reflected in the additional staff numbers forecast and the effect of inflation.
5.3.2 Table 5.4 sets out the fee scales for non-HRB projects under Scenario 2 (20% overhead uplift). As fixed fees are only changing as a result of inflation, the fixed fees in Scenario 2 are the same as those in Scenario 1.
5.3.3 Table 5.5 provides the fee rates for HRB projects. It is assumed that there would not be any HRB projects in the £0 to £10,000 value of work band. The point made under Scenario 1 (paragraph 5.2.2) regarding the effect of the fixed cost for pre-application discussions in the lower value of work bands also applies in this Scenario. Total HRB fee rates include both the non-HRB fee plus the HRB uplift. The results are shown for each of the three forecast years with the percentage increase between current and 2026/27 fees also shown.
5.3.4 Comparison of the fee rates in the two scenarios shows that the 30% uplift for overheads (Scenario 1) adds approximately 2% to fees compared to the 20% overhead uplift.
Value of Work Band | Current Fee, £ | 2024/25, £ | 2025/26, £ | 2026/27, £ | % Change Current to 2026/27 | |
---|---|---|---|---|---|---|
0-£10,000 | Conversion Demolition Extension Zero Fee <£5000 £5k - £10k |
150 150 100 - 150 245 |
207 207 138 - 207 257 |
212 212 142 - 212 271 |
218 218 145 - 218 286 |
45.2 45.2 45.2 - 45.2 16.7 |
£10,001-£50,000 |
Zero Fee All Others |
- 593 |
- 623 |
- 657 |
- 693 |
- 16.9 |
£50,001-£250,000 | - | 1,240 | 1,303 | 1,373 | 1,449 | 16.9 |
£250,001-£1 million | - | 2,682 | 2,817 | 2,971 | 3,134 | 16.9 |
>£1 million | £1-£5m £5-10m £10-£25m £25-50m >£50m |
7,910 18,789 33,970 79,509 142,759 |
8,309 19,737 35,683 83,519 149,959 |
8,761 20,811 37,626 88,067 158,125 |
9,245 21,959 39,701 92,923 166,845 |
16.9 16.9 16.9 16.9 16.9 |
Amendments | <£5k >£5k |
100 435 |
138 457 |
142 482 |
145 508 |
45.2 16.8 |
Note: 2022/23 and 2023/24 have not been modelled as the existing fee rates will apply in these rates.
Inflation increases are built into the modelled fee rates.
Value of Work Band | Current Fee, £ | 2024/25, £ | 2025/26, £ | 2026/27, £ | % Change Current to 2026/27 | |
---|---|---|---|---|---|---|
0-£10,000 | - | - | - | - | - | - |
£10,001-£50,000 | - | 593 | 636 | 685 | 1,200 | 102.4 |
£50,001-£250,000 | - | 1,240 | 1,331 | 1,431 | 2,019 | 62.8 |
£250,001-£1 million | - | 2,682 | 2,878 | 3,096 | 4,294 | 60.1 |
>£1 million | £1-£5m £5-10m £10-£25m £25-50m >£50m |
7,910 18,789 33,970 79,509 142,759 |
8,487 20,161 36,450 85,313 153,181 |
9,131 21,690 39,215 91,784 164,799 |
10,911 24,679 43,892 101,526 181,575 |
37.9 31.3 29.2 27.7 27.2 |
Note: 2022/23 and 2023/24 have not been modelled as the existing fee rates will apply in these rates.
Inflation increases are built into the modelled fee rates.
5.3.5 Table 5.6 sets out the fee income raised from the various fee activities for Scenario 2 using the fee rates in Tables 5.4 and 5.5. The total income raised (net of certification discounts[15] is estimated to be £36.3 million in 2024/25, rising to £42.3 in 2026/27.
Income from: | 2024/25 | 2025/26 | 2026/27 |
---|---|---|---|
Current fee rates Inflation to fixed fees rates Inflation drag (non-fixed rates) Extra fee existing LA/BSD activities Extra fee additional LA activities Extra fee for Hub Extra fee for HRBs |
36.227 0.776 (4.246) 5.041 - 0.930 0.250 |
36.227 0.846 (5.207) 6.308 1.566 1.014 0.518 |
36.227 0.918 (6.192) 7.619 3.245 1.098 2.109 |
Total Income Before Certification Discount | 38.977 | 41.271 | 45.024 |
Certification Discount | 2.637 | 2.703 | 2.770 |
Total Income Post Certification Discount | 36.341 | 38.569 | 42.253 |
Note: The income raised from inflation drag reduces the amount of additional funds required to be raised from increased fee rates as extra fees will be delivered.
5.4 Sub-National Analysis
5.4.1 Fee rates have been estimated at the sub-national level for five areas:
- Urban: Aberdeen, Dundee, Edinburgh, Glasgow.
- Primarily Urban: East Dunbartonshire, East Renfrewshire, Falkirk, Inverclyde, North Lanarkshire, Renfrewshire, West Dunbartonshire, West Lothian.
- Mixed: Clackmannanshire, East Lothian, Fife, Midlothian, North Ayrshire, South Lanarkshire.
- Primarily Rural: Aberdeenshire, Angus, Dumfries & Galloway, East Ayrshire, Moray, Perth & Kinross, Scottish Borders, South Ayrshire, Stirling.
- Very Rural/Island: Argyll & Bute, Highland, Na h-Eileanan Siar, Orkney, Shetland.
5.4.2 For each of these area models the structure of the model is the same as the Scotland model. The distribution of applications by value of work band varies by area type, except in the over £1 million band where the distribution is the same across all areas. This is due to limitations which may have a slight bearing on the results.
5.4.3 The following parameters have been changed in each area model:
- Number of building warrant applications, amendments and late completion certificate applications.
- Distribution of applications by value of work band.
- Number of certificates of design and construction by scheme.
- Verification and total staff costs.
- The areas share of total (Scotland) applications to calculate the share of BSD and hub costs to be covered by the area.
- Workforce demand.
- Share of surplus funds in each area. Only the urban and mixed areas returned a surplus of building warrant fee income over total costs in 2021/22. These two areas share the £1m surplus in the system which effectively reduces the additional funds required to be raised in each of these areas. The other areas received no share of the surplus.
5.4.4 As the fixed fee rates are being increased by inflation only, these rates remain the same at the Scotland and sub-national levels.
5.4.5 Table 5.7 sets out the non-fixed fee rates for 2026/27 for each of the five areas for non-HRB projects and Scotland (from Tables 5.1 and 5.2) with a 30% overhead uplift. The results are shown for 2026/27 as this is the year when all proposed changes to the building standards service will be fully implemented.
5.4.6 Table 5.8 sets out the same results for HRB projects. As for the Scotland model, it is assumed there will be no HRB projects in the £0 to £10,000 fee band.
5.4.7 The Tables show that urban and very rural/island areas have rates below the Scotland level. Primarily urban and mixed areas have rates which are broadly similar to the Scotland rates and primarily rural areas have relatively high rates.
5.4.8 The following points can be made in relation to each area:
- Urban: the urban area receives the majority of the system surplus which reduces the additional funds to be raised through fees. Forecast staff numbers are a key driver of future costs and these are relatively stable in urban areas.
- Primarily Urban: these areas have not returned a surplus of building warrant fee income over costs. Hence, all additional funds required have to be raised through higher fees.
- Mixed: the area returned a surplus of building warrant fee income over costs and receives a share of the £1 million system surplus. This reduces the amount to be raised through fees. However, this area is forecast to increase staff numbers by approximately 12% which is a key component of future costs.
- Primarily Rural: this area type has relatively high fees reflecting no system surplus and an increase in staff of 17%.
- Very Rural/Island: this area type has relatively low fees, despite there being no system surplus. Staff numbers however are forecast to reduced slightly which is a key determinant of future costs.
Value of Work Band | Scotland | Urban | Primarily Urban | Mixed | Primarily Rural | Very Rural/Island |
---|---|---|---|---|---|---|
0-£10,000 | 293 | 265 | 296 | 296 | 326 | 264 |
£10,001 - £50,000 | 709 | 642 | 717 | 717 | 789 | 638 |
£50,001 - £250,000 | 1,483 | 1,341 | 1,499 | 1,500 | 1,650 | 1,334 |
£250,001 - £1 million | 3,208 | 2,902 | 3,242 | 3,244 | 3,570 | 2,886 |
>£1 million: £1- £5 m £5- £10m £10- £25m £25- £50m >£50m |
9,462 22,475 40,633 95,105 170,762 |
8,557 20,327 36,750 86,016 154,443 |
9,563 22,715 41,068 96,122 171,589 |
9,568 22,727 41,090 96,174 172,680 |
10,528 25,008 45,214 105,825 190,010 |
8,512 20,219 36,555 85,559 153,623 |
Value of Work Band | Scotland | Urban | Primarily Urban | Mixed | Primarily Rural | Very Rural/Island |
---|---|---|---|---|---|---|
0-£10,000 | ||||||
£10,001 - £50,000 | 1,222 | 1,151 | 1,224 | 1,234 | 1,312 | 1,138 |
£50,001 - £250,000 | 2,063 | 1,917 | 2,069 | 2,089 | 2,253 | 1,889 |
£250,001 - £1 million | 4,390 | 4,072 | 4,402 | 4,445 | 4,800 | 4,013 |
>£1 million: £1- £5 m £5- £10m £10- £25m £25- £50m >£50m |
11,192 25,346 45,099 104,350 186,645 |
10,256 23,123 41,079 94,941 169,751 |
11,228 25,433 45,255 104,716 187,302 |
11,357 25,738 45,807 106,007 189,620 |
12,402 28,222 50,297 116,517 208,492 |
10,080 22,706 40,324 93,174 166,579 |
Contact
Email: buildingstandards@gov.scot
There is a problem
Thanks for your feedback