Annex A: Table 2 - SRDP 2014 - 2020 Policy Development: Key Milestones
Task | Revised Deadline |
---|---|
Scotland RD financial allocation determined | December 2013 (estimated for consultation) |
Financial allocations per priority | December 2013 (based on estimate for consultation) |
Environmental Impact Assessment consultation launched | December 2013/January 2014 |
RD Regulation agreed | December 2013 (political agreement reached) |
Delivery structure framework (includes final approach to PA) | January 2014 |
UK PA (including Scottish chapter) sent to European Commission | February 2014 |
Targeting (2nd stage complete) | March 2014 |
Option design (2nd stage complete) | March 2014 |
Produce stage 2 consultation response | Spring 2014 |
Ex-ante & SEA complete | Spring 2014 |
SG approval of SRDP | Spring 2014 |
Formal submission of SRDP | Spring 2014 |
EC SRDP approval (EC has 6 months to approve) | Autumn 2014 |
Legislation approved | Autumn/winter 2014 |
Open to applications | January 2015 |
These dates are subject to the timetable in Europe for finalising the regulations and their approval of the SRDP.