Autumn budget 2019-2020: supporting document
The 2019-2020 autumn budget revision to the Budget (Scotland) Act for the year ending 31 March 2020.
Rural Economy
Schedule 2.1 Total Changes for the Autumn Budget Revision
Operating | Capital | Total | |
---|---|---|---|
£m | £m | £m | |
Total Budget in the Budget Act | 323.8 | 22.3 | 346.1 |
Changes Proposed | |||
Funding Changes | 1.3 | 0.0 | 1.3 |
Technical Adjustments | 0.1 | 0.0 | 0.1 |
Net Whitehall Transfers | 4.8 | 0.0 | 4.8 |
Net Transfers within Scottish Block | 11.2 | -1.1 | 10.1 |
Total changes proposed | 17.4 | -1.1 | 16.3 |
Proposed Budget following Autumn Budget Revisions | 341.2 | 21.2 | 362.4 |
Operating | Capital | Total | |
£m | £m | £m | |
Expenditure Limit: | |||
EU Support and Related Services | 161.6 | 13.9 | 175.5 |
Rural Services | 36.2 | 0.0 | 36.2 |
Fisheries & Aquaculture Grants | 5.9 | 0.0 | 5.9 |
Rural Economy Enterprise | 67.2 | 7.3 | 74.5 |
Scottish Forestry | 53.2 | 0.0 | 53.2 |
Forestry and Land Scotland | 17.0 | 0.0 | 17.0 |
Total Expenditure Limit | 341.1 | 21.2 | 362.3 |
UK Funded AME: EU Support and Related Services | 0.0 | 0.0 | 0.0 |
Total UK Funded AME | 0.0 | 0.0 | 0.0 |
Other Expenditure: | |||
Animal License Fees | 0.1 | 0.0 | 0.1 |
Total Other Expenditure | 0.1 | 0.0 | 0.1 |
Total Budget | 341.2 | 21.2 | 362.4 |
Total Limit on Income (accruing resources) | 800.0 |
Schedule 3.1 EU Support & Related Services
Details of Proposed Budget
Proposed Changes | Operating | Capital | Total |
---|---|---|---|
£m | £m | £m | |
Original Budget | 162.9 | 13.9 | 176.8 |
Proposed changes | -1.3 | 0.0 | -1.3 |
ABR Proposed Budget | 161.6 | 13.9 | 175.5 |
Proposed changes | |||
SBR Proposed Budget | |||
Summary of proposed changes | |||
Transfer to Rural Services to fund the bovine ScotEID project. | -1.5 | 0.0 | -1.5 |
Transfer from Finance, Economy and Fair Work contribution towards Scottish Rural Development Programme. | 0.5 | 0.0 | 0.5 |
Re-prioritisation of operating costs budget to Environment, Climate Change and Land Reform. | -0.3 | 0.0 | -0.3 |
-1.3 | 0.0 | -1.3 | |
Proposed Budget following Autumn Budget Revision | Operating | Capital | Total |
£m | £m | £m | |
Gross Expenditure | 692.5 | 15.3 | 707.8 |
Less: Retained Income | -530.9 | 0.0 | -530.9 |
Capital Receipts Applied | 0.0 | -1.4 | -1.4 |
161.6 | 13.9 | 175.5 | |
Budget Analysis | |||
CAP Pillar 1 Basic Payments | 262.0 | 0.0 | 262.0 |
CAP Pillar 1 Greening Payments | 131.5 | 0.0 | 131.5 |
CAP Pillar 1 Other Payments | 44.5 | 0.0 | 44.5 |
Broadband | 0.0 | 0.0 | 0.0 |
Agri Environmental Measures | 41.5 | 0.0 | 41.5 |
Business Development | 20.6 | 4.0 | 24.6 |
CAP Compliance Improvements | 0.0 | 0.0 | 0.0 |
Crofting Assistance | 1.7 | -0.9 | 0.8 |
EU Income | -533.7 | 0.0 | -533.7 |
Forestry | 0.9 | 0.0 | 0.9 |
Leader | 20.4 | 0.0 | 20.4 |
Less Favoured Area Support Scheme | 52.4 | 0.0 | 52.4 |
ARE Operations (including Non-Cash) | 118.8 | 10.8 | 129.6 |
Technical Assistance | 1.0 | 0.0 | 1.0 |
Net Expenditure | 161.6 | 13.9 | 175.5 |
Schedule 3.2 Rural Services
Details of Proposed Budget
Proposed Changes | Operating | Capital | Total |
---|---|---|---|
£m | £m | £m | |
Original Budget | 35.0 | 0.0 | 35.0 |
Proposed changes | 1.2 | 0.0 | 1.2 |
ABR Proposed Budget | 36.2 | 0.0 | 36.2 |
Proposed changes | |||
SBR Proposed Budget | |||
Summary of proposed changes | |||
Transfer from EU Support to fund the bovine ScotEID project. | 1.5 | 0.0 | 1.5 |
Transfer to Finance, Economy and Fair Work to support Food and Drink export plan. | -0.2 | 0.0 | -0.2 |
Transfer to Finance, Economy and Fair Work to support market driven supply chains. | -0.1 | 0.0 | -0.1 |
1.2 | 0.0 | 1.2 | |
Proposed Budget following Autumn Budget Revision | Operating | Capital | Total |
£m | £m | £m | |
Gross Expenditure | 36.2 | 0.0 | 36.2 |
Less: Retained Income | 0.0 | 0.0 | 0.0 |
Capital Receipts Applied | 0.0 | 0.0 | 0.0 |
36.2 | 0.0 | 36.2 | |
Budget Analysis | |||
Agricultural & Horticultural Advice & Support | 2.2 | 0.0 | 2.2 |
Animal Health | 19.3 | 0.0 | 19.3 |
Crofting Commission | 2.7 | 0.0 | 2.7 |
Food Industry Support | 6.2 | 0.0 | 6.2 |
Rural Cohesion | 0.6 | 0.0 | 0.6 |
Veterinary Surveillance | 5.2 | 0.0 | 5.2 |
Net Expenditure | 36.2 | 0.0 | 36.2 |
Schedule 3.3 Fisheries & Aquaculture Grants
Details of Proposed Budget
Proposed Changes | Operating | Capital | Total |
---|---|---|---|
£m | £m | £m | |
Original Budget | 5.9 | 0.0 | 5.9 |
Proposed changes | 0.0 | 0.0 | 0.0 |
ABR Proposed Budget | 5.9 | 0.0 | 5.9 |
Proposed changes | |||
SBR Proposed Budget | |||
Summary of proposed changes | |||
0.0 | 0.0 | 0.0 | |
0.0 | 0.0 | 0.0 | |
Proposed Budget following Autumn Budget Revision | Operating | Capital | Total |
£m | £m | £m | |
Gross Expenditure | 15.1 | 0.0 | 15.1 |
Less: Retained Income | -9.2 | 0.0 | -9.2 |
Capital Receipts Applied | 0.0 | 0.0 | 0.0 |
5.9 | 0.0 | 5.9 | |
Budget Analysis | |||
EU Fisheries Grants | 14.1 | 0.0 | 14.1 |
Fisheries Harbour Grants | 1.0 | 0.0 | 1.0 |
Marine EU Income | -9.2 | 0.0 | -9.2 |
Net Expenditure | 5.9 | 0.0 | 5.9 |
Schedule 3.4 Rural Economy Enterprise
Details of Proposed Budget
Proposed Changes | Operating | Capital | Total |
---|---|---|---|
£m | £m | £m | |
Original Budget | 61.0 | 8.4 | 69.4 |
Proposed changes | 6.2 | -1.1 | 5.1 |
ABR Proposed Budget | 67.2 | 7.3 | 74.5 |
Proposed changes | |||
SBR Proposed Budget | |||
Summary of proposed changes | |||
Transfer from Transport, Infrastructure and Connectivity for Wave Energy Scotland. | 5.4 | 0.0 | 5.4 |
Transfer from Transport, Infrastructure and Connectivity for Dales Voe Decommissioning. | 0.5 | 0.0 | 0.5 |
Transfer from Communities and Local Government to fund the Strengthening Communities Programme. | 0.5 | 0.0 | 0.5 |
Transfer to Education and Skills to support the delivery of a South Of Scotland Economic Partnership project. | -0.2 | -1.1 | -1.3 |
6.2 | -1.1 | 5.1 | |
Proposed Budget following Autumn Budget Revision | Operating | Capital | Total |
£m | £m | £m | |
Gross Expenditure | 67.2 | 7.3 | 74.5 |
Less: Retained Income | 0.0 | 0.0 | 0.0 |
Capital Receipts Applied | 0.0 | 0.0 | 0.0 |
67.2 | 7.3 | 74.5 | |
Budget Analysis | |||
Highlands and Islands Enterprise | 62.5 | 0.0 | 62.5 |
South of Scotland Enterprise | 4.7 | 7.3 | 12.0 |
Net Expenditure | 67.2 | 7.3 | 74.5 |
Schedule 3.5 Scottish Forestry
Details of Proposed Budget
Proposed Changes | Operating | Capital | Total |
---|---|---|---|
£m | £m | £m | |
Original Budget | 43.2 | 0.0 | 43.2 |
Proposed changes | 10.0 | 0.0 | 10.0 |
ABR Proposed Budget | 53.2 | 0.0 | 53.2 |
Proposed changes | |||
SBR Proposed Budget | |||
Summary of proposed changes | |||
Additional funding to fund the Increase in employer pension contributions | 0.2 | 0.0 | 0.2 |
Whitehall funding from DEFRA iro Cross Border Forestry in Scotland | 4.8 | 0.0 | 4.8 |
Transfer from Transport, Infrastructure and Connectivity for the Strategic Timber Transport Scheme. | 5.0 | 0.0 | 5.0 |
10.0 | 0.0 | 10.0 | |
Proposed Budget following Autumn Budget Revision | Operating | Capital | Total |
£m | £m | £m | |
Gross Expenditure | 53.2 | 0.0 | 53.2 |
Less: Retained Income | 0.0 | 0.0 | 0.0 |
Capital Receipts Applied | 0.0 | 0.0 | 0.0 |
53.2 | 0.0 | 53.2 | |
Budget Analysis | |||
Programme and Running Costs | 20.8 | 0.0 | 20.8 |
Depreciation | 0.5 | 0.0 | 0.5 |
Policy Regulation and Administration | 0.0 | 0.0 | 0.0 |
Woodland Grants | 52.7 | 0.0 | 52.7 |
EC Receipts | -20.8 | 0.0 | -20.8 |
Net Expenditure | 53.2 | 0.0 | 53.2 |
Schedule 3.6 Forestry and Land Scotland
Details of Proposed Budget
Proposed Changes | Operating | Capital | Total |
---|---|---|---|
£m | £m | £m | |
Original Budget | 15.7 | 0.0 | 15.7 |
Proposed changes | 1.3 | 0.0 | 1.3 |
ABR Proposed Budget | 17.0 | 0.0 | 17.0 |
Proposed changes | |||
SBR Proposed Budget | |||
Summary of proposed changes | |||
Additional funding to fund the Increase in employer pension contributions | 1.1 | 0.0 | 1.1 |
Miscellaneous minor transfer | 0.2 | 0.0 | 0.2 |
1.3 | 0.0 | 1.3 | |
Proposed Budget following Autumn Budget Revision | Operating | Capital | Total |
£m | £m | £m | |
Gross Expenditure | 17.0 | 0.0 | 17.0 |
Less: Retained Income | 0.0 | 0.0 | 0.0 |
Capital Receipts Applied | 0.0 | 0.0 | 0.0 |
17.0 | 0.0 | 17.0 | |
Budget Analysis | |||
Forestry and Land Scotland Resource | 15.4 | 0.0 | 15.4 |
Forestry and Land Scotland Capital | 1.6 | 0.0 | 1.6 |
Net Expenditure | 17.0 | 0.0 | 17.0 |