Scotland's Digital Future - Delivery of Public Services
Scotland's national digital public services strategy and action plan.
Annex B Action Plan
Citizen Focus
Priority Objective |
Action |
Timeline |
---|---|---|
Identity Assurance and Authentication |
Project Set Up
Analysis and Investigation
Decision Making
|
September 2012 |
Single point of entry to services and redesign of services for digital delivery |
Project Set Up
Engagement
Development
Implementation
|
September 2012 to October 2012 October 2012 and continuing October 2012 2012-13 2013 2014 |
Privacy and Openness
Priority Objective |
Action |
Timeline |
---|---|---|
Data Sharing |
Project Set Up
Engagement
Implementation
|
December 2012 March 2013 |
Cyber Security Strategy |
Project Set Up
Engagement
Development
Consultation
Implementation
|
May 2012 July 2012 August 2012 November 2012 |
Open Data and Reuse of Public Data |
|
August 2011 November 2012 Mid-2013 |
Data Linkage Framework Establish a collaborative Data Linkage Framework for Statistics and Research |
Project Set Up
Investigation and Analysis
Engagement
Development
Consultation
|
May 2011 January 2012 August 2012 Winter 2012 2013 |
A Skilled and Empowered Workforce
Priority Objective |
Action |
Timeline |
---|---|---|
Workforce Identify the key skills and capabilities required within our ICT and wider public sector workforce to deliver on national and sectoral strategies and identify capabilities and gaps. ICT Workforce Work collaboratively to identify cross sector opportunities for sharing ICT workforce capacity and the training and development of ICT staff and seek to address any barriers to collaboration. |
Project Set Up
Investigation and Analysis
Engagement
Developing a Workforce Action Plan
Implementation
|
September 2012 September 2012 to March 2013 March to April 2012 June 2013 August/ September 2013 onwards |
Collaboration and Value for Money
Priority Objective |
Action |
Timeline |
---|---|---|
High Level ICT Operating Framework |
Project Set Up
Investigation and Analysis
Options Appraisal
Decision Making
|
May 2012 June 2012 October 2012 November 2012 |
Scottish Wide-Area Network Establish a Scottish Wide-Area Network ( SWAN). |
Project Set Up
Investigation and Analysis
Decision Making
Implementation
|
July 2012 Ongoing September 2012 Ongoing |
Work in partnership with sectoral centres of procurement expertise to: Maximise value from existing national procurement frameworks and explore opportunities for new national frameworks and contracts. Measure the savings achieved across the public sector through the use of procurement frameworks and contracts. Support the development of a joined-up approach to buying technology, where it supports public service delivery. Encourage sustainability, innovation and growth and make better use of public procurement to promote jobs and training opportunities. Make it easier for Scottish SMEs to access public sector contracts by improving and standardising procurement process, whilst encouraging public bodies to consider the economic impact of their procurement activities. |
Project Set Up
Action Plan
Monitoring and Development
Engagement
Legislation
Launch
Engagement
|
December 2012 December 2012 December 2012 Monthly Every 3 Months Stage 1 of the parliamentary 'Bill' process due March 2013 Q1 2013 Monthly frequency Initial scoping/ introductory meetings held in August/ September 2012 November 2012 |
National approach to Data Management and storage Develop a national strategy to consolidate and reuse the world-class data centres available in the public and private sectors across Scotland. |
Project Set Up
Investigation and Analysis
Options Appraisal
Decision Making
|
October 2012 December 2012 February 2013 March 2013 |
Open Source Principles Building on the existing Scottish Open Source Strategy and wider good practice and lessons learned across Europe agree a set of open source principles for use by the Scottish public sector. |
Project Set Up
Investigation and Analysis
Engagement and Consultation
Decision Making and Implementation
|
October 2012 |
Measurements and Benefits Create an agreed Measurements and Benefits Framework by: Determining current measurements undertaken in Scottish public sector. Establishing a common set of quantitative measures that support overall framework for delivery. Developing qualitative measures to measure improvement in citizen experience and value for money. |
Project Set Up
Investigation/Analysis
Engagement on Findings
|
June 2012 to Complete June to August 2012 August to September 2012 |
Measurements and Benefits Create an agreed Measurements and Benefits Framework by: Determining current measurements undertaken in Scottish public sector. Establishing a common set of quantitative measures that support overall framework for delivery. Developing qualitative measures to measure improvement in citizen experience and value for money. |
Developing the framework
Sign off of the framework
Measuring
Review and Refresh
|
September to October 2012 November 2012 March 2013 Ongoing |