5. Looking Forward
Planned investment and improvement works programmed for 2020-21 were put on hold, with only essential maintenance carried out over the course of the year. These will be resumed when appropriate to continue to improve efficiency and sustainability performance and meet Ministers' targets on building-related climate matters.
The building-wide heating system upgrade at Victoria Quay, involving boiler replacements and the installation of gas-fired Combined Heat and Power (CHP) plant started in 2019-20. Delayed phases two and three, planned for 2020-21, are now programmed for the first half of 2021-22.