Scottish Government Investment Group Progress Report on Performance Against the Committed List for Quarter 3 2023/24
Sets out how Scottish Water is progressing with the delivery of projects and programmes included on the ‘Committed List’ and confirms the position up to the end of December 2023 (Q3 2023/24).
Appendix B – Wastewater Sub-portfolios
The list of projects included in the sub-portfolios can be found by filtering the Committed List by column E.
Wastewater SR15 Completion Projects
With overall IPOD points of 66, the SR15 Completion sub-portfolio is out with the target range of 75 to 77.
Start on Site
No projects started on site during Q3 bringing the total number of projects achieving the Start On Site (SOS) milestone to 7 with performance being on target at 7 points.
Acceptance
No projects achieved acceptance during Q3, bringing the total number of completed projects delivering benefit to customers to 30 which is behind the target of 34 points. 4 projects in the SR15 Completion sub-portfolio have been reforecast. Reasons for reforecasting can be found in the table below.
Project ID |
Description |
Reason For Reforecast |
Baseline Quarter |
Forecast Quarter |
---|---|---|---|---|
401668 |
S043 - UID - Cambuslang Road Richmond Laundry - South East of Railway Rutherglen |
Third party issues |
2021/22 Q2 |
2024/25 Q2 |
401705 |
S087 - UID - Scotwood Overflow North East of Lay-by Busby Road |
Third party issues |
2021/22 Q3 |
2024/25 Q1 |
403106 |
QS3b AR - P014 UID Westbank Quadrant at Eldon Street Bridge CSO NS273667 |
Third party issues |
2022/23 Q4 |
2025/26 Q2 |
404026 |
SR15 ES - Main Street Newtonmore |
Third party issues |
2022/23 Q1 |
2024/25 Q3 |
Financial Approval
No projects achieved financial completion during Q3, taking the total achieved to 29 which is outwith the target range of 34 to 36 points. 7 projects in the SR15 Completion sub-portfolio have been reforecast. Reasons for reforecasting can be found in the table below.
Project ID |
Description |
Reason For Reforecast |
Baseline Quarter |
Forecast Quarter |
---|---|---|---|---|
401668 |
S043 - UID - Cambuslang Road Richmond Laundry - South East of Railway Rutherglen |
Third party issues |
2022/23 Q1 |
2024/25 Q3 |
401705 |
S087 - UID - Scotwood Overflow North East of Lay-by Busby Road |
Third party issues |
2022/23 Q2 |
2024/25 Q2 |
403102 |
QS3b AR - P010 UID Botanic Gardens Nr Junc of Garrioch Drive Garrioch Rd and Shakespeare St |
Third party issues |
2022/23 Q1 |
2023/24 Q4 |
403106 |
QS3b AR - P014 UID Westbank Quadrant at Eldon Street Bridge CSO NS273667 |
Third party issues |
2023/24 Q3 |
2025/26 Q3 |
404026 |
SR15 ES - Main Street Newtonmore |
Third party issues |
2023/24 Q1 |
2024/25 Q4 |
500681 |
SW843 Wellgate Lanark |
Third party issues |
2023/24 Q1 |
2024/25 Q1 |
503269 |
Dalmarnock WWTW Improvements |
Construction risks realised |
2022/23 Q4 |
2025/26 Q1 |
Wastewater Network Projects
With overall IPOD points of 97, the Wastewater Network sub-portfolio is in within the target range of 96 to 109.
Start on Site
4 projects (S-WW-NI-061222-Esk WWPS-Refurbish - replace rising mains within the wet well, IFOS - Burn Road Inverness - CSO, Provost Driver Court - Sewer repair and ground stabilisation project, E-WW-I-070222-Lossiemouth Coulardbank No1 Storm WWPS Screw pump and MCC replacement) started on site during Q3 bringing the total number of projects achieving the Start On Site (SOS) milestone to 22 with performance being in the top half of the range of 16 to 25 points.
Acceptance
1 project (Shieldhall WWTW Grade 5 HC Sewer Ph1) achieved acceptance during Q3, bringing the total number of completed projects delivering benefit to customers to 39 which is out with the target range of 42 to 44 points. 4 in the Wastewater Network sub-portfolio have been reforecast. Reasons for reforecasting can be found in the table below.
Project ID |
Description |
Reason For Reforecast |
Baseline Quarter |
Forecast Quarter |
---|---|---|---|---|
501017 |
SW1015 - Shieldaig Road Glasgow |
Third party issues |
2023/24 Q3 |
2024/25 Q2 |
502944 |
IR18 CAS Compliance Improvements - Networks East & North, Complex |
Third party issues |
2021/22 Q2 |
2023/24 Q4 |
502949 |
Dunfermline Wellwood Waste Water Infrastructure |
Third party issues |
2021/22 Q4 |
2023/24 Q4 |
503362 |
Infra-Kingdom Park |
Third party issues |
2021/22 Q2 |
2024/25 Q2 |
Financial Approval
3 projects (W462 - Coalburn Road Coalburn, Main Street Kirkconnel Pipe Bridge, ICF - Forres Strategic Wastewater upgrade) achieved financial completion during Q3, taking the total achieved to 36 which is out with the target range of 38 to 40 points. 6 in the Wastewater Network sub-portfolio have been reforecast. Reasons for reforecasting can be found in the table below.
Project ID |
Description |
Reason For Reforecast |
Baseline Quarter |
Forecast Quarter |
---|---|---|---|---|
501683 |
Shieldhall WWTW Grade 5 HC Sewer Ph1 |
Construction risks realised |
2022/23 Q2 |
2024/25 Q1 |
502866 |
NRSWA Construction Sewer Greenhills Road Widening East Kilbride |
Construction risks realised |
2022/23 Q3 |
2023/24 Q4 |
502944 |
IR18 CAS Compliance Improvements - Networks East & North, Complex |
Third party issues |
2022/23 Q1 |
2024/25 Q1 |
502949 |
Dunfermline Wellwood Waste Water Infrastructure |
Third party issues |
2022/23 Q4 |
2024/25 Q1 |
503393 |
Ayr Shore Road SPS - Emergency Repairs to Transfer Pumps and Wet Well Guide Rails |
Construction risks realised |
2022/23 Q2 |
2023/24 Q4 |
503415 |
Bothwell Sewer - Replacement of approximately 130m of 600mm |
Third party issues |
2022/23 Q4 |
2023/24 Q4 |
Wastewater Treatment Projects
With overall IPOD points of 142, the Wastewater Treatment sub-portfolio is within the target range of 139 to 156.
Start on Site
6 projects (SR21 ES Forfar STW Control Systems Replacement, E-WW-NI-020821-Kennethmont WWTW Inlet screen and washwater replacement, MCC SR15- Shieldhall WWTW MCC Replacement Phase 2, Croy WwTW - Growth, Dalmarnock Sludge Transfer Pumping Station - Capital Maintenance, Gairloch WwTW - Additional Treatment Options) started on site during Q3 bringing the total number of projects achieving the Start On Site (SOS) milestone to 41 with performance being in the top half of the range of 34 to 42 points.
Acceptance
5 projects (SR21 ES Forfar STW Control Systems Replacement, DALDERSE WWTW 1966 NS903822, Rosewell WwTW - Interim Growth Solution SAF, E-WWNI-050821-Kirkcaldy STW-Renew media in 1st stage biopur (BAFF) process, Shieldhall WWTW - cleaning of Inlet Delta Storm Bypass Culvert and Velocity Channels at Pre-Sed Bldng) achieved acceptance during Q3, bringing the total number of completed projects delivering benefit to customers to 54 which is within the target range albeit at the lower threshold of 54 to 61 points.
Financial Approval
5 projects (Stewarton WwTW - Growth, IR18 Allowance - Newton Septic Tank, HV Asset Replacement Phase 1 - Shieldhall WwTW, Lochwinnoch WwTW - Inlet Screw Pumps Refurbishment - 500k, Catrineholm WwTW- Emergency Project to Maintain CAR Licence Compliance) achieved financial completion during Q3, taking the total achieved to 47 which is out with the target range of 51 to 53 points. 6 in the Wastewater Treatment sub-portfolio have been reforecast. Reasons for reforecasting can be found in the table below.
Project ID |
Description |
Reason For Reforecast |
Baseline Quarter |
Forecast Quarter |
---|---|---|---|---|
500052 |
Carstairs Village WwTW - Growth |
Construction risks realised |
2023/24 Q1 |
2024/25 Q1 |
500233 |
Burrelton WwTW - Growth |
Third party issues |
2022/23 Q3 |
2024/25 Q1 |
500579 |
Kinneil Kerse WwTW - Capital Maintenance |
Additional scope required to complete |
2022/23 Q3 |
2023/24 Q4 |
500580 |
Forres WWTW 1973 NJ038595 - SR15 Capital Maintenance |
Third party issues |
2023/24 Q2 |
2023/24 Q4 |
501021 |
Banchory WwTW - Growth |
Third party issues |
2022/23 Q3 |
2023/24 Q4 |
501579 |
DALDERSE WWTW 1966 NS903822 |
Construction risks realised |
2023/24 Q2 |
2023/24 Q4 |
Contact
Email: waterindustry@gov.scot
There is a problem
Thanks for your feedback