Scottish Government Investment Group Progress Report on Performance Against the Committed List for Quarter 3 2023/24

Sets out how Scottish Water is progressing with the delivery of projects and programmes included on the ‘Committed List’ and confirms the position up to the end of December 2023 (Q3 2023/24).


7. Progress in delivering SR15 Completion Projects

SR15 completion projects are reported in each of the water and wastewater portfolios in Sections 4 and 5 of this report. For clarity, all completion projects are summarised in this section. By way of recap, there are two categories of SR15 completion projects:

  • Delayed Projects – projects that were expected to complete by the end of SR15 but were impacted by Covid-19, re-optioneering, scope change, construction risk and third-party risk.
  • Planned Projects – projects that commenced in SR15 but were always expected to complete during SR21.

Table 1 below summarises the current status of each category.

Table 1: SR15 completion programme project status.

Stage

Delayed Projects

Forecast at March 2021

Delayed Projects

Actual at Q3
2023-24

Delayed

Projects

Variance

Planned Projects

Forecast at March 2021

Planned Projects

Actual at Q3 2023-24

Planned Projects

Variance

Pre-Start On Site

0

3

3

0

2

2

In Construction

2

20

18

2

9

7

Acceptance

84

63

-21

55

46

-9

Total

86

86

0

57

57

0

The remaining investment represents circa 2% of the total SR15 programme.

By way of further explanation:

Delayed Projects

At the end of Q3 2023/24 we had planned to have 84 of the 86 delayed SR15 projects through acceptance (Table 1). However, we still have 23 delayed projects (3 pre-start on site and 20 in construction - shown in the 'Actual at Q3 2023-24' column of Table 1) to achieve Gate 100 acceptance.

There are 3 projects forecasting acceptance in Q4: IR18 CAS Compliance Improvements, Newmore WTW and Yarrowfues.

The following projects that are yet to start on site are:

  • Rockcliffe Bathing Water (BW) - Improvement to Sufficient Status. Temporary treatment is in place to deliver bathing water compliance. Extensive community engagement has taken place - planning consents and marine licensing applications are being worked through and, if achieved, will allow a start on site circa July 2024 and a revised acceptance date will be established.
  • IR18 - Boardhouse WTW Inlet Screen. The SR15 output was for the installation of a silt curtain. During project development further essential requirements were identified and developed which created a much larger project which is now in place and expected to start on site circa July 2024 – consideration will be given to signing off the SR15 output once the silt curtain is in place.
  • Roberton WTW - pH correction for coagulation. An operational solution was put in place to deliver the SR15 output but was unsuccessful – a new project to install a coagulation control system has been developed and is expected to start on site in March 2024 and reach acceptance by February 2026.

Planned Projects

46 projects have now achieved Gate 100 acceptance against a target for Q3 2023/24 of 55.

1 of the Planned projects is forecasting completion in Q4 (Invercannie). Sanday WTW started on site in Q3 and the following projects are yet to start on site:

  • South Uist WTW New Source. The SR15 output is being delivered by refurbishment works.
  • IR18 - Upperton (Longriggend) WWTW. The project had to be re-scoped and to ensure the SR15 output will be delivered – expected to start on site by April 2024.

More detail on the SR15 Completion projects is given in the presentation slide decks shared and discussed with DWQR and SEPA.

Contact

Email: waterindustry@gov.scot

Back to top