Social housing: net zero progress report - quarter 2 2024
Quarter 2 2024 progress reports on the social housing net zero heat fund.
Project Title: Pre 1919 - Tenements - Retrofit up to 60 pre-1919 Sandstone Tenement Flats with a view to achieving EPC B rating
Project Organisation: Wheatley Group
Technology Type(s): HHRSH, Double Glazing, IWI, RI, UFI
Location(s): Edinburgh, Edinburgh City Council
Grant Value: £455,868
Completion Date: March 2024
Project Headline: Project involved retrofitting 30 void pre-1919 tenement buildings to achieve an EPC ‘B’ rating using combined measures
Project Description:
This project targeted void properties to allow a deep retrofit compared to when tenants are in place.
The measures installed varied according to the individual property and existing heating solution in place with measures including:
- Improvement of existing windows with double glazing
- Improvement and treatment to walls/roof/floor with insulation
- Deployment of air tightness measures
- Installation of an appropriate clean heating system, primarily high heat retention storage heaters
This project aimed to identify a method for retrofitting pre-1919 tenements and allow these learnings to be deployed more widely.
Phase 2 of this project was awarded in financial year 2024/25 with roll out to more properties in Edinburgh and Glasgow City.