Social Housing Net Zero Progress Report Q2 2024
Social Housing Net Zero Heat Fund Progress Reports Quarter 2, 2024
Project Title: B and C Listed Double Glazing and Insulation Works
Project Organisation: Yorkhill Housing Association
Technology Type(s): Double Glazing Windows, LITU and Internal and External Door Draft Proofing
Location(s): Glasgow, Glasgow City Council
Grant Value: £364,454
Completion Date: Projected January 2025
Project Headline: Fabric First retrofit of 37 listed pre-1919 sandstone tenements in Glasgow
Project Description:
This project will provide fabric first energy efficiency measures to 37 pre 1919 sandstone tenements in Yorkhill, Glasgow. All of the properties in this project are listed: 24 are B-listed and 13 are C-listed.
Each property will receive timber framed double glazed windows which will comply with Glasgow City Council's planning permission conditions which took Yorkhill Housing Association 8 years to achieve. Window upgrades will retain the traditional features of the listed buildings while reducing heat loss.
Loft insulation top-ups will be installed alongside draught proofing to internal and external doors to further minimise heat loss.
The installation of these measures will save tenants on energy bills, alleviating fuel poverty and providing thermal comfort for tenants as the properties currently have single glazed windows due the planning restrictions.
Contact
There is a problem
Thanks for your feedback