Spring Budget Revision 2022 to 2023: supporting document

Supporting document to the Budget (Scotland) Act 2022 Amendment (No. 2) Regulations 2023. Provides details of Level 2 and 3 budgets.


Constitution, External Affairs and Culture

Schedule 2.1 Total Changes for the Spring Budget Revision
  Operating Capital Total
  £m £m £m
Total Budget in the Autumn Budget Revision 282.227 0.000 282.227
Changes Proposed
Funding Changes -7.487 -0.515 -8.002
Technical Adjustments -3.040 0.000 -3.040
Net Whitehall Transfers 1.655 0.000 1.655
Net Transfers within Scottish Block -1.802 0.000 -1.802
Total changes proposed -10.674 -0.515 -11.189
Proposed Budget following Spring Budget Revision 271.553 -0.515 271.038
  Operating Capital Total
  £m £m £m
Expenditure Limit:
Culture & Major Events 177.951 -0.515 177.436
External Affairs 31.422 0.000 31.422
Historic Environment Scotland 62.180 0.000 62.180
Total Expenditure Limit 271.553 -0.515 271.038
UK Funded AME:
Total UK Funded AME 0.000 0.000 0.000
Other Expenditure:
Total Other Expenditure 0.000 0.000 0.000
Total Budget 271.553 -0.515 271.038
Total Limit on Income (accruing resources)     200.000
Schedule 3.1 Culture and Major Events
Details of Proposed Budget
Proposed Changes Operating Capital Total
  £m £m £m
Original Budget 197.867 0.000 197.867
ABR Changes -15.583 0.000 -15.583
ABR Budget 182.284 0.000 182.284
Proposed Changes -2.688 -0.515 -3.203
SBR Proposed Budget 179.596 -0.515 179.081
Summary of Proposed changes
Additional budget for Historic Scotland Legacy costs 3.200 0.000 3.200
Budget surrenders from Other Arts Budget to support SG priorities -3.500 0.000 -3.500
Historic Scotland AME Legacy Costs -3.000 0.000 -3.000
Whitehall transfers for Project Unicorn 1.655 0.000 1.655
Transfer to Sport Scotland within Health for UCI 2023 Cycling World Championships -1.000 0.000 -1.000
Miscellaneous Minor Transfers -1.688 -0.515 -2.203
  -2.688 -0.515 -3.203
Proposed Budget following Spring Budget Revision Operating Capital Total
  £m £m £m
Gross Expenditure 177.951 -0.515 177.436
Less: Retained Income 0.000 0.000 0.000
Capital Receipts Applied 0.000 0.000 0.000
  177.951 -0.515 177.436
Budget Analysis
Architecture and Place 2.030 0.000 2.030
Creative Scotland & Other Arts 63.834 0.000 63.834
Culture and Major Events Staffing 4.845 0.000 4.845
Cultural Collections 82.064 0.000 82.064
Historic Scotland AME Legacy Costs -3.000 0.000 -3.000
Historic Scotland - Legacy Costs 3.200 0.000 3.200
Major Events 0.112 0.000 0.112
National Performing Companies 22.661 -0.515 22.146
Royal and Ceremonial 2.205 0.000 2.205
Net Expenditure 177.951 -0.515 177.436
Schedule 3.2 External Affairs
Details of Proposed Budget
Proposed Changes Operating Capital Total
  £m £m £m
Original Budget 33.433 0.000 33.433
ABR Changes -0.670 0.000 -0.670
ABR Budget 32.763 0.000 32.763
Proposed Changes -1.341 0.000 -1.341
SBR Proposed Budget 31.422 0.000 31.422
Summary of Proposed changes
Miscellaneous Minor Transfers -1.341 0.000 -1.341
  -1.341 0.000 -1.341
Proposed Budget following Spring Budget Revision Operating Capital Total
  £m £m £m
Gross Expenditure 31.422 0.000 31.422
Less: Retained Income 0.000 0.000 0.000
Capital Receipts Applied 0.000 0.000 0.000
  31.422 0.000 31.422
Budget Analysis
British Irish Council 0.100 0.000 0.100
International & European Relations 31.322 0.000 31.322
Net Expenditure 31.422 0.000 31.422
Schedule 3.3 Historic Environment Scotland
Details of Proposed Budget
Proposed Changes Operating Capital Total
  £m £m £m
Original Budget 67.100 0.000 67.100
ABR Changes 0.080 0.000 0.080
ABR Budget 67.180 0.000 67.180
Proposed Changes -5.000 0.000 -5.000
SBR Proposed Budget 62.180 0.000 62.180
Summary of proposed changes
Funding surrendered to support SG priorities -5.000 0.000 -5.000
Miscellaneous Minor Transfers 0.000 0.000 0.000
  -5.000 0.000 -5.000
Proposed Budget following Spring Budget Revision Operating Capital Total
  £m £m £m
Gross Expenditure 100.480 0.000 100.480
Less: Retained Income -38.300 0.000 -38.300
Capital Receipts Applied 0.000 0.000 0.000
  62.180 0.000 62.180
Budget Analysis
Operational Costs 62.180 0.000 62.180
Net Expenditure 62.180 0.000 62.180

Contact