Open Government Action Plan commitment 4: be more accountable for public services
Progress reports on our commitment to improve accountability of public services as part of our open government action plan.
Progress to September 2019
Milestones | Update | Progress | |
1 | Engage with Commitment Signatories |
Met with each Signatory individually, and held collaborative workshop to build shared understandings and purpose of work moving forwards, Spring 2019 |
✔ Complete |
2 | Form civil society partnerships working group |
Held first meeting April 2019; workshop on co-design of citizens engagement June 2019 |
✔ Complete |
3 | Commission baseline research into accountability landscape |
Contracted EKOS Consultants Ltd. to conduct desk-based research to assess existing accountability bodies operating in Scotland for public services, and to assess some examples of citizens engagement in scrutiny activities to help inform best practice (if taken forward) |
✔ Complete |
4 | Conduct vulnerable citizens engagement to complement wider national engagement |
CAS have been commissioned to take forward an OGP project under their consumer advocacy work-plan for 2019/20, to be conducted alongside and complementing the national engagement activities led by SG (via contractor). Project due to conclude late November. |
🙂 On Track |
5 | Conduct in-depth citizens and public bodies engagement to identify challenges and inform solutions development |
Contract awarded to We Are Snook to take forward this work – plan to hold 4 public events, a national survey and interviews, a public bodies consultation event, and to establish a Citizens Panel that will lead on development of at least one solution in 2020. Final report with recommendations for viable pilot solutions due January 2020 |
🙂 On Track |
6 | Hold one-off engagement w/academics and other scrutiny and accountability experts to test potential solutions under consideration |
December 2019 – January 2020 (TBC) |
🙂 On Track |
7 | CWG endorsement of identified pilot solutions to be taken forward |
To be confirmed January – February 2020 |
🙂 On Track |
8 | Pilot development and implementation, working w/CWG, Citizens Panel and other relevant supporting stakeholders |
February – September 2020
(*work likely to continue beyond September to ensure proper and effective implementation) |
🙂 On Track |
There is a problem
Thanks for your feedback